January 2026
A milestone is an approval, a denial, a moratorium, a groundbreaking, an opening, an expansion, a cancellation, a lawsuit filed, a court ruling, a law signed or taking effect or a federal roll call, on the day it happened; each line links the record it belongs to, the Daily Record lists every row by the day it entered the record instead, and how a day is read is on the methodology page.
3 milestones in January 2026
1 approval · 1 lawsuit filed · 1 law signed
Newest: , law signed, S4928: Requires payment of prevailing wage for certain data center construction..
Tuesday, January 20 1
-
S4928: Requires payment of prevailing wage for certain data center construction., New Jersey
S. 4928 was signed.
njleg.state.nj.us, primary source
January 2026, no day given 2
-
Port Washington, Wisconsin
Metropolitan Milwaukee Association of Commerce and six other business groups filed lawsuit against Port Washington in late January 2026
wpr.org, local outlet (the month its own sentence names; no day is given; filed under Feb 4, 2026)
-
In January, elected officials for the city of Warrenton, Missouri, voted unanimously to approve a data center plan that would include two buildings each four times larger than a Costco warehouse or Walmart supercenter
lailluminator.com, local outlet (the month its own sentence names; no day is given; filed under Sep 12, 2026)
Bill data from LegiScan, licensed CC BY 4.0. The record chooses the bills, writes each stage in its own words and cites the legislature's own page for every bill. A bill or a law on this page was found through LegiScan; the line cites the legislature's own page.