Mississippi, year by year.
Every act on the record for Mississippi, on the day it happened, newest first by month. Under each month, one tap away, the background, plans and statements the same sources carried. The counts are the state hub's records; nothing is estimated.
The record by year
On the record as of October 27, 2026.
An act sits on the day it happened: the day its own sentence names, or the day its source gives for it. An act the record knows only from the date of the article that reported it sits under that article's month, one tap away, marked Reported with the article's date. So do background, plans and statements, which are not acts. The same act reported by several sources is one line with the reports behind it, on its day where any of them dates it. The milestones alone, for every state, are on the timeline.
15 acts on the line for Mississippi, from 39 dated lines in the records' histories and the scorecard. 10 more acts are dated only by the article that reported them and sit under their month. 2 lines report an act already listed. 12 lines are background, plans or statements. 6 lines sit on a date other than the one they were filed under, because their own sentence names the day, the month or the year it happened; each says so. Where a line sits is read from its own words and the row is never changed (how dates are read).
2026 12 acts on the line from 14 reports; 10 reported, dated only by the article; 12 lines of background, plans and statements
September 2026 1 act on the line; 1 reported; 2 lines of background, plans and statements
On September 15-16, 2026, the Mississippi Association of Supervisors Minority Caucus hosted the Mississippi Data Center Development Information Convening in Jackson to discuss data center development, infrastructure, water and energy use, economic development, and community impacts with local officials.
jacksonadvocateonline.com (opens in a new tab), news outlet
Reported in September 2026, dated only by the article that carried it: 1 act
Town of Walls approved rezoning of over 1,000 acres from agricultural to light industrial use
desotocountynews.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)
Also on the record for September 2026, not acts of their own: 2 lines of background, plans and statements
SpaceXAI facility at 2875 Stanton Road in Southaven operating with multiple jet engines powering natural gas turbines
dailymemphian.com (opens in a new tab) (no act in the sentence)
County supervisors in Mississippi are meeting to learn about data centers
wapt.com (opens in a new tab) (a description, not an act)
August 2026 No acts on the line; 7 reported; 8 lines of background, plans and statements
Reported in August 2026, dated only by the article that carried them: 7 acts
Mississippi Public Service Commission approved rate plan keeping Entergy Mississippi rates below national average
entergy.com (opens in a new tab), primary source (dated only by the report that carried it, so under the month of the report)
Two more SpaceXAI data centers announced by January 2026
cbsnews.com (opens in a new tab), national outlet (dated only by the report that carried it, so under the month of the report)
Department of Justice separately sought to intervene and have the case thrown out, arguing that the matter touches on national security and Mississippi's legal permitting process
thecooldown.com (opens in a new tab), national outlet (dated only by the report that carried it, so under the month of the report)
Two additional data centers were announced by January 2026
thecooldown.com (opens in a new tab), national outlet (dated only by the report that carried it, so under the month of the report)
The Madison County Board of Aldermen upheld the tax assessor's valuation of $292 million per data center
desotocountynews.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)
Olive Branch Board of Mayor and Aldermen approved new zoning ordinance changes restricting data center development
yahoo.com (opens in a new tab), national outlet (dated only by the report that carried it, so under the month of the report)
Generator power restricted between 2 and 5 p.m. with highest emission standards required
yahoo.com (opens in a new tab), national outlet (dated only by the report that carried it, so under the month of the report)
Also on the record for August 2026, not acts of their own: 8 lines of background, plans and statements
A power plant powering SpaceXAI data centers in the Memphis area is generating noise pollution affecting residents on a 2 acre family property in Southaven
cbsnews.com (opens in a new tab) (a description, not an act)
The plant will replace 69 temporary turbines with 41 permanent turbines over the course of a year
cbsnews.com (opens in a new tab) (a plan or a schedule, not an act yet)
In June, SpaceXAI asked that the lawsuit be dismissed
thecooldown.com (opens in a new tab) (a statement; who said what is on the statements pages)
Musk said in July that another nearby site called Minihard was coming
thecooldown.com (opens in a new tab) (a statement; who said what is on the statements pages)
Amazon will pay discounted fees of one third of typical property taxes for the first 10 years of each data center's operations over a 30 year term
desotocountynews.com (opens in a new tab) (a plan or a schedule, not an act yet)
New ordinance requires data centers to operate closed loop cooling systems
yahoo.com (opens in a new tab) (a description, not an act)
Hyperscale data centers must not exceed 45 decibels between 9 p.m. to 6 a.m. and 65 decibels at any time at facility boundaries
yahoo.com (opens in a new tab) (a description, not an act)
Hyperscale data centers categorized as Tier 3, requiring mandatory 2,000 foot setback from public schools, residential areas, parks, and roads
yahoo.com (opens in a new tab) (no act in the sentence)
July 2026 4 acts on the line from 5 reports; 2 reported; 1 line of background, plans and statements
Jackson passed state's first data center moratorium on July 14, 2026
mississippitoday.org (opens in a new tab), local outlet (the day its own sentence names)
Jackson City Council voted to pause new data center development on July 14, 2026
clarionledger.com (opens in a new tab), local outlet (the day its own sentence names)
Jackson City Council approved a moratorium on data centers on July 14, 2026
wlbt.com (opens in a new tab), local outlet (the day its own sentence names)
1 more report of this
- Reported July 15 Jackson implemented a moratorium on data centers wapt.com (opens in a new tab)
A third SpaceXAI data center named Minihard was confirmed in July 2026
cbsnews.com (opens in a new tab), national outlet (the month its own sentence names; no day is given; filed under Aug 27, 2026)
Reported in July 2026, dated only by the article that carried them: 2 acts
Jackson implemented a six month moratorium on data centers due to local opposition
mississippifreepress.org (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)
The City of Jackson paused data center construction
mississippifreepress.org (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)
Also on the record for July 2026, not acts of their own: 1 line of background, plans and statements
Pause is until Jackson passes data center regulations
mississippifreepress.org (opens in a new tab) (a description, not an act)
June 2026 3 acts on the line from 4 reports
Amazon established a workforce partnership for its Mississippi data centers
mississippitoday.org (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)
Class action lawsuit filed Monday, June 8, 2026 by Southaven residents against xAI
mississippifreepress.org (opens in a new tab), local outlet
1 more report of this
- Reported June 17 Class action lawsuit filed in United States District Court for Northern District of Mississippi against xAI Corp., SpaceX, and MZX Tech LLC lawmbg.com (opens in a new tab)
SpaceXAI filed motion to dismiss the case in June 2026
cbsnews.com (opens in a new tab), national outlet (the month its own sentence names; no day is given; filed under Aug 27, 2026)
April 2026 4 acts on the line; 1 line of background, plans and statements
Ridgeland data center project faces opposition from Mississippi energy companies
mississippitoday.org (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)
The Mississippi State Conference of the NAACP, represented by the Southern Environmental Law Center and Earthjustice, sued xAI Holdings and MZX Tech under the Clean Air Act in the Northern District of Mississippi, alleging 27 gas turbines operating without an air permit at the Southaven site (alleged in the filing, not a finding)
earthjustice.org (opens in a new tab), news outlet
NAACP and other groups sued xAI and MZX Tech in April alleging the plant emits significant amounts of harmful pollutants
cbsnews.com (opens in a new tab), national outlet (the month its own sentence names; no day is given; filed under Aug 27, 2026)
In April, the National Association for the Advancement of Colored People and other organizations sued xAI and its subsidiary, MZX Tech, alleging that the plant emits significant amounts of harmful pollutants
thecooldown.com (opens in a new tab), national outlet (the month its own sentence names; no day is given; filed under Aug 26, 2026)
Also on the record for April 2026, not acts of their own: 1 line of background, plans and statements
April 2026 NAACP lawsuit against xAI over use of gas turbines alleging Clean Air Act violation
mississippifreepress.org (opens in a new tab) (a description, not an act)
2025 1 act on the line
August 2025 1 act on the line
Gas fired turbines began operating in or around August 2025
lawmbg.com (opens in a new tab), primary source (the month its source gives; it names no day)
2024 2 acts on the line
2024, no month given 2 acts
Work on the Colossus 1 data center started in 2024
thecooldown.com (opens in a new tab), national outlet (the year its own sentence names; filed under Aug 26, 2026)
Colossus 1 data center construction began in 2024
cbsnews.com (opens in a new tab), national outlet (the year its own sentence names; filed under Aug 27, 2026)