TierPoint Oklahoma City Data Centers, in order
What happened with this project, oldest first: the stages it reached, what the county and its cities decided, and every dated step on the record. Each entry links its source.
2 events, January 1, 2003 to January 1, 2008. Also on the record, under the month each belongs to: 14 figures from other sources and 6 dates when source pages were read and verified. The facts, newest first: the record; the place: Oklahoma.
A plain date is the day it happened, as the source states it, or as the line's own sentence states it ("voted on July 6"), which is where the line sits even when it was filed later. "Reported" and a date is the day a source published a line that carries no date of its own. Those lines, and lines that describe rather than report an act, sit under their month rather than on the timeline, with what was said and the figures other sources gave. Every timeline on the site reads its lines by this one rule. How dates are read.
Stages
2003 1 event
-
(the year its own sentence names; filed under Jan 1, 2003)
Entry
TierPoint first Oklahoma City data center began operation in 2003, is 4000 square feet, cooled with 100 tons of computer room air conditioning [6]
2008 1 event
-
(the year its own sentence names; filed under Jan 1, 2008)
Entry
TierPoint second Oklahoma City data center built in 2008, 22500 square feet with 15000 square feet raised floor capacity, withstands winds up to 150 miles per hour, cooled with 150 tons of computer room air conditioning under floor and in line cooling [6]
2016 1 under the months
-
Also in February 2016: 1 date when a source page was read and verified
-
(source date; the content gives no date of its own)
Entry
TierPoint delivers largest commercial data center in Oklahoma [7]
-
2018 1 under the months
-
Also in February 2018: 1 date when a source page was read and verified
-
(source date; the content gives no date of its own)
Entry
TierPoint completes fourth data center in Oklahoma [3]
-
2026 18 under the months
-
Also in August 2026: 1 figure from another source
-
(source date; the content gives no date of its own)
Figure · Yahoo
3,000,000 gallons: A data center leaked over 3 million gallons of water in Oklahoma. Yahoo (opens in a new tab) national outlet
-
-
Also in September 2026: 12 figures from other sources and 4 dates when source pages were read and verified
-
(source date; the content gives no date of its own)
Figure · KOKH
330,000,000 dollars: Project would help repay a 330 million dollar municipal debt Enid owes KOKH (opens in a new tab) local outlet
-
(source date; the content gives no date of its own)
Figure · KOKH
600 jobs: Project Thunderbird would create 600 jobs KOKH (opens in a new tab) local outlet
-
(source date; the content gives no date of its own)
Figure · KOKH
1,735 acres: Project Thunderbird covers about 1,735 acres KOKH (opens in a new tab) local outlet
-
(source date; the content gives no date of its own)
Figure · KOKH
3.3 GW: Project Thunderbird would require up to 3.3 gigawatts of power KOKH (opens in a new tab) local outlet
-
(source date; the content gives no date of its own)
Figure · KOKH
15,000 dollars: Those who decide to stay will receive a 15,000 dollar improvement grant KOKH (opens in a new tab) local outlet
-
(source date; the content gives no date of its own)
Figure · The Lawton Constitution
50 count: According to OSU, there are approximately 50 data centers in the United States, with at least three new ones being constructed in Oklahoma. In the U.S. there are 8,242 data centers that are active or under construction. The Lawton Constitution (opens in a new tab) news outlet
-
(source date; the content gives no date of its own)
Entry
Data center meets FEMA Zone 4 rated and Seismic 2 rated earthquake standards [4]
-
(source date; the content gives no date of its own)
Entry
MIDCON data center located in Quail Springs Business Park [4]
-
(source date; the content gives no date of its own)
Entry
MIDCON Recovery Solutions data center has been operational since about 2016 [4]
-
(the day the page was read; it gives no date of its own)
Entry
TierPoint lists TierPoint Oklahoma City Data Centers at Oklahoma City, Oklahoma on its own page of data center locations, read September 14, 2026. [2]
-
(source date; the content gives no date of its own)
Figure · cnhinews.com
600 jobs: Project organizers are projecting a conservative 600 full time jobs once the project is completed cnhinews.com (opens in a new tab) local outlet
-
(source date; the content gives no date of its own)
Figure · cnhinews.com
10,500,000 gallons per day: City has current capacity to pump 10.5 million gallons a day from Kaw Lake cnhinews.com (opens in a new tab) local outlet
-
(source date; the content gives no date of its own)
Figure · News 9
60,000 square feet: MIDCON data center is 60,000 square feet News 9 (opens in a new tab) local outlet
-
(source date; the content gives no date of its own)
Figure · cnhinews.com
1,540,000 gallons per day: Data centers and power plant would use about 1.54 million gallons of water each day cnhinews.com (opens in a new tab) local outlet
-
(source date; the content gives no date of its own)
Figure · BIC Magazine
100 to 150 jobs: AB Energy USA will support 100-150 service and maintenance positions from the secured data center projects. BIC Magazine (opens in a new tab) news outlet
-
(source date; the content gives no date of its own)
Figure · BIC Magazine
2 GW: AB Energy USA secured approximately 2 GW of on site data center power capacity across five projects in Texas and Oklahoma. BIC Magazine (opens in a new tab) news outlet
-
-
Also in October 2026: 1 figure from another source
-
(source date; the content gives no date of its own)
Figure · news9.com
100,000,000 gallons a year: A data center would require 300,000 gallons of water per day, adding up to 100 million gallons per year, according to Kyle Spotted Horse news9.com (opens in a new tab) local outlet
-
On the timeline: a stage change; an entry that reports an act on the day the source or its own sentence gives; and a decision, a published scorecard event on a row at or under the record's county, that reports an act. Under the months: a statement that names this record, a figure another source gave about it, matched by place and developer, an entry dated only by the day its source was published, and an entry or a decision that describes rather than reports an act. Each is on the record in its own right and keeps its own link.
For researchers
- Stage
- running
- Events on the timeline
- 2
- Under the months
- 20
- Stage changes
- 0
- Decisions
- 0
- Statements
- 0
- Figures
- 14
- Entries and decisions under the months
- 6