A plain date is the day it happened, as the source states it, or as the line's own sentence states it ("voted on July 6"), which is where the line sits even when it was filed later. "Reported" and a date is the day a source published a line that carries no date of its own. Those lines, and lines that describe rather than report an act, sit under their month rather than on the timeline, with what was said and the figures other sources gave. Every timeline on the site reads its lines by this one rule. How dates are read.
2026 1 event
-
(content date)
Decision · Rapid City (city)
Rapid City Planning Commission voted unanimously on September 10 to delay a vote on proposed data center ordinance amendments to the November 4 meeting rapidcityjournal.com
-
Also in September 2026: 1 statement and 3 lines that are not events of their own
-
(source date; the content gives no date of its own)
Decision · Rapid City (city)
Micro data centers are defined as having a peak power demand of up to 10 megawatts and no more than 3,000 gallons of water per day rapidcityjournal.com
-
(source date; the content gives no date of its own)
Decision · Rapid City (city)
Large scale data centers are defined as using more than 10 megawatts but up to a maximum of 30 megawatts at peak demand and using a maximum of 10,000 gallons of water a day rapidcityjournal.com
-
(source date; the content gives no date of its own)
Decision · Rapid City (city)
The proposed ordinance would define hyperscale data centers as centers using 30 or more megawatts of power at peak demand or more than 10,000 gallons of water a day rapidcityjournal.com
-
(said in the source itself)
Statement · Eric Wolff, Black Hills Energy business development manager
Eric Wolff, business development manager for Black Hills Energy, said Sequitor Edge data center may be at risk of not coming to fruition due to the city's regulatory efforts Rapid City Journal local outlet
-
On the timeline: a stage change; an entry that reports an act on the day the source or its own sentence gives; and a decision, a published scorecard event on a row at or under the record's county, that reports an act. Under the months: a statement that names this record, a figure another source gave about it, matched by place and developer, an entry dated only by the day its source was published, and an entry or a decision that describes rather than reports an act. Each is on the record in its own right and keeps its own link.
For researchers
- Slug
- rapid-city-data-center-sd
- Status value
- rumored
- Events on the timeline
- 1
- Under the months
- 4
- Stage changes
- 0
- Decisions
- 4
- Statements
- 1
- Figures
- 0
- Entries and decisions under the months
- 3