QTS Santa Clara, in order
What happened with this project, oldest first: the stages it reached, what the county and its cities decided, and every dated step on the record. Each entry links its source.
1 event, September 14, 2026 to September 14, 2026. Also on the record, under the month each belongs to: 11 lines that are not events of their own. The facts, newest first: the record; the place: California.
A plain date is the day it happened, as the source states it, or as the line's own sentence states it ("voted on July 6"), which is where the line sits even when it was filed later. "Reported" and a date is the day a source published a line that carries no date of its own. Those lines, and lines that describe rather than report an act, sit under their month rather than on the timeline, with what was said and the figures other sources gave. Every timeline on the site reads its lines by this one rule. How dates are read.
Stages
2026 1 event
-
Also in August 2026: 2 lines that are not events of their own
-
(source date; the content gives no date of its own)
Decision · San Jose (city)
San Jose is considering data center development amid resident environmental concerns kqed.org
-
(source date; the content gives no date of its own)
Decision · San Jose (city)
San Jose residents push for data center moratorium sanjosespotlight.com
-
-
(the day the page was read; it gives no date of its own)
running
QTS Data Centers lists QTS Santa Clara at Santa Clara, California on its own page of data center locations, read September 14, 2026. [2]
-
Also in September 2026: 9 lines that are not events of their own
-
(source date; the content gives no date of its own)
Decision · Gilroy (city)
The moratorium would not affect the Amazon data center already approved and under construction on Camino Arroyo gilroydispatch.com
-
(source date; the content gives no date of its own)
Decision · Gilroy (city)
Approved interim urgency ordinances remain in place for 45 days unless renewed by the council, then can be renewed for an additional 10 months and 15 days, and again for another 12 months if needed gilroydispatch.com
-
(source date; the content gives no date of its own)
Decision · Gilroy (city)
The moratorium would allow the city to review and update design and development standards that would apply to data centers and other industrial developments gilroydispatch.com
-
(source date; the content gives no date of its own)
Decision · Gilroy (city)
Gilroy City Council will consider adopting a temporary moratorium on new data centers at its Sept. 14 meeting gilroydispatch.com
-
(source date; the content gives no date of its own)
Decision · Morgan Hill (city)
Morgan Hill City Council adopted a temporary moratorium on data centers and battery storage facilities while staff develops possibly permanent guidelines gilroydispatch.com
-
(source date; the content gives no date of its own)
Decision · Gilroy (city)
The moratorium could potentially be extended for up to two years. mercurynews.com
-
(source date; the content gives no date of its own)
Decision · Gilroy (city)
Gilroy City Council approved a temporary moratorium on new data center applications effective immediately for at least 45 days. mercurynews.com
-
(source date; the content gives no date of its own)
Decision · San Jose (city)
Santa Clara City is pushing for a plan to require large customers such as data centers to reduce power use when power is scarce mk.co.kr
-
(source date; the content gives no date of its own)
Decision · Santa Clara County (county)
Santa Clara County Sustainability Committee discussed moratorium suspending permits for new data centers for a certain period, strengthening disclosure of resource use, and gap analysis mk.co.kr
-
On the timeline: a stage change; an entry that reports an act on the day the source or its own sentence gives; and a decision, a published scorecard event on a row at or under the record's county, that reports an act. Under the months: a statement that names this record, a figure another source gave about it, matched by place and developer, an entry dated only by the day its source was published, and an entry or a decision that describes rather than reports an act. Each is on the record in its own right and keeps its own link.
For researchers
- Slug
- qts-santa-clara-ca
- Status value
- operational
- Events on the timeline
- 1
- Under the months
- 11
- Stage changes
- 1
- Decisions
- 11
- Statements
- 0
- Figures
- 0
- Entries and decisions under the months
- 11