Prosper data center ($500M), in order

What happened with this project, oldest first: the stages it reached, what the county and its cities decided, and every dated step on the record. Each entry links its source.

1 event, September 9, 2026 to September 9, 2026. Also on the record, under the month each belongs to: 1 statement and 4 figures from other sources. The facts, newest first: the record; the place: Texas.

A plain date is the day it happened, as the source states it, or as the line's own sentence states it ("voted on July 6"), which is where the line sits even when it was filed later. "Reported" and a date is the day a source published a line that carries no date of its own. Those lines, and lines that describe rather than report an act, sit under their month rather than on the timeline, with what was said and the figures other sources gave. Every timeline on the site reads its lines by this one rule. How dates are read.

Stages

  1. cancelled

Now: cancelled. A stage is the record's status after the entry that set it (the definitions).

2026 1 event

  1. (source date; the content gives no date of its own)

    cancelled

    White Rose Partners withdrew $580 million Prosper data center proposal due to intense community opposition and zoning rejection [3]

  2. Also in September 2026: 1 statement and 4 figures from other sources
    1. (said in the source itself)

      Statement · David Bristol, Prosper Mayor

      David Bristol, Prosper Mayor, spoke against Project Tomahawk as a private resident, calling for denial because there were no local or state guidelines for data centers. constructionreviewonline.com local outlet

    2. (source date; the content gives no date of its own)

      Figure · constructionreviewonline.com

      2,500,000 USD: Developers estimated $2.5 million in annual sales and franchise tax revenue for Prosper. constructionreviewonline.com local outlet

    3. (source date; the content gives no date of its own)

      Figure · constructionreviewonline.com

      1,600 petition signatures: Prosper Residents for Responsible Land Use gathered more than 1,600 petition signatures in opposition to Project Tomahawk. constructionreviewonline.com local outlet

    4. (source date; the content gives no date of its own)

      Figure · constructionreviewonline.com

      580,000,000 USD: Project Tomahawk estimated investment is $580 million. constructionreviewonline.com local outlet

    5. (source date; the content gives no date of its own)

      Figure · constructionreviewonline.com

      20 to 50 jobs: Developer estimated 20 to 50 permanent jobs for the region. constructionreviewonline.com local outlet

On the timeline: a stage change; an entry that reports an act on the day the source or its own sentence gives; and a decision, a published scorecard event on a row at or under the record's county, that reports an act. Under the months: a statement that names this record, a figure another source gave about it, matched by place and developer, an entry dated only by the day its source was published, and an entry or a decision that describes rather than reports an act. Each is on the record in its own right and keeps its own link.

For researchers
Slug
prosper-data-center-500m-tx
Status value
cancelled
Events on the timeline
1
Under the months
5
Stage changes
1
Decisions
0
Statements
1
Figures
4
Entries and decisions under the months
0