A plain date is the day it happened, as the source states it, or as the line's own sentence states it ("voted on July 6"), which is where the line sits even when it was filed later. "Reported" and a date is the day a source published a line that carries no date of its own. Those lines, and lines that describe rather than report an act, sit under their month rather than on the timeline, with what was said and the figures other sources gave. Every timeline on the site reads its lines by this one rule. How dates are read.
Stages
2026 1 event
-
Also in March 2026: 1 figure from another source
-
(content date)
Figure · Monitoring Analytics, Independent Market Monitor for PJM, 2025 State of the Market Report for PJM, Volume 1
23,100,955,341 USD: Increase in PJM capacity market revenues across the 2025/2026, 2026/2027 and 2027/2028 base residual auctions that resulted from existing and forecast data center load Monitoring Analytics, Independent Market Monitor for PJM, 2025 State of the Market Report for PJM, Volume 1 (opens in a new tab) primary source
-
-
(content date)
waiting on permits
The Whiting-Turner Contracting Company filed Georgia DCA DRI #4735 on May 5, 2026 for Project Squash, a 200 MW data center campus on 325 acres at 6423 Wrightsboro Road near Harlem in unincorporated Columbia County. [1]
-
Also in September 2026: 3 figures from other sources
-
(source date; the content gives no date of its own)
Figure · WFXG FOX54
1,600 jobs, households, students: The study projects the development could lead to roughly 1,600 new jobs, 472 new local households and 307 additional students in the Columbia County School System. WFXG FOX54 (opens in a new tab) local outlet
-
(source date; the content gives no date of its own)
Figure · WRDW
1,600 jobs, households, students: The study projects the project could create 1,600 new jobs, 472 new local households and 307 new students in the Columbia County School System. WRDW (opens in a new tab) local outlet
-
(source date; the content gives no date of its own)
Figure · WRDW
22,000 USD: The land currently generates $22,000 a year in taxes for the county and schools. The county's projected tax revenue from the site is $12 billion. WRDW (opens in a new tab) local outlet
-
Local jurisdiction rules 1 decision
County and municipal actions on the record in Columbia County County, listed separately from this facility's own timeline.
-
(source date; the content gives no date of its own)
Decision · Columbia County (county)
Economic Development Authority of Columbia County is working with Google on a Memorandum of Understanding for a data center partnership yahoo.com (opens in a new tab)
On the timeline: a stage change; an entry that reports an act on the day the source or its own sentence gives; and a decision, a published scorecard event on a row at or under the record's county, that reports an act. Under the months: a statement that names this record, a figure another source gave about it, matched by place and developer, an entry dated only by the day its source was published, and an entry or a decision that describes rather than reports an act. Each is on the record in its own right and keeps its own link.
For researchers
- Stage
- waiting on permits
- Events on the timeline
- 1
- Under the months
- 4
- Stage changes
- 1
- Decisions
- 1
- Statements
- 0
- Figures
- 4
- Entries and decisions under the months
- 0