Data Center Record.
Projects / Project Hazelnut / Timeline

Project Hazelnut, in order

What happened with this project, oldest first: the stages it reached, what the county and its cities decided, and every dated step on the record. Each entry links its source.

2 events, November 10, 2025 to August 27, 2026. Also on the record, under the month each belongs to: 5 figures from other sources and 2 lines that are not events of their own. The facts, newest first: the record; the place: Pennsylvania.

A plain date is the day it happened, as the source states it, or as the line's own sentence states it ("voted on July 6"), which is where the line sits even when it was filed later. "Reported" and a date is the day a source published a line that carries no date of its own. Those lines, and lines that describe rather than report an act, sit under their month rather than on the timeline, with what was said and the figures other sources gave. Every timeline on the site reads its lines by this one rule. How dates are read.

Stages

  1. waiting on permits

Now: waiting on permits. A stage is the record's status after the entry that set it (the definitions).

2025 1 event

  1. (content date)

    waiting on permits

    NorthPoint Development's preliminary and final major land development plan for Project Hazelnut, 15 data center buildings with ancillary buildings, parking, utilities, landscaping and stormwater on a 1,282 acre industrial technology campus north of Humboldt Industrial Park North, was before the Hazle Township Board of Supervisors on November 10, 2025, which tabled it. [3]

2026 1 event

  1. Also in June 2026: 4 figures from other sources
    1. (source date; the content gives no date of its own)

      Figure · NorthPoint Development

      1,300 construction jobs: Project Hazelnut would create more than 1,300 construction jobs over a six year development period NorthPoint Development primary source

    2. (source date; the content gives no date of its own)

      Figure · NorthPoint Development

      165,000,000 USD: NorthPoint committed to $165 million community benefit fund including $45 million direct resident grants, $15 million community support fund, and $105 million long term commitment over 15 years NorthPoint Development primary source

    3. (source date; the content gives no date of its own)

      Figure · NorthPoint Development

      1,100 acres: For every 1 acre cleared, 2 acres will be conserved, protecting 1,100 acres of open space and forest NorthPoint Development primary source

    4. (source date; the content gives no date of its own)

      Figure · NorthPoint Development

      900 jobs: Project Hazelnut would create over 900 permanent operational jobs NorthPoint Development primary source

  2. (the weekday its sentence names, the last before the report; filed under Sep 1, 2026)

    Decision · Salem Township (city)

    Planning Commission voted Thursday to recommend township supervisors approve expansion of data center overlay district for third project despite court stay order thecentersquare.com

  3. Also in August 2026: 1 figure from another source and 1 line that is not an event of its own
    1. (source date; the content gives no date of its own)

      Figure · finance.yahoo.com

      40,400,000 dollars: PPL and Blackstone joint investment is more than 40.4 million US dollars. finance.yahoo.com national outlet

    2. (source date; the content gives no date of its own)

      Decision · Salem Township (city)

      Salem Township Board of Supervisors scheduled to meet Wednesday to decide on data center overlay zone expansion timesleader.com

  4. Also in September 2026: 1 line that is not an event of its own
    1. (source date; the content gives no date of its own)

      Decision · Luzerne County (county)

      Plains Township to host hearing on AI data center zoning map changes to accommodate data centers on September 22 in Luzerne County paenvironmentdaily.blogspot.com

On the timeline: a stage change; an entry that reports an act on the day the source or its own sentence gives; and a decision, a published scorecard event on a row at or under the record's county, that reports an act. Under the months: a statement that names this record, a figure another source gave about it, matched by place and developer, an entry dated only by the day its source was published, and an entry or a decision that describes rather than reports an act. Each is on the record in its own right and keeps its own link.

For researchers
Slug
project-hazelnut-hazle-township-pa
Status value
permitting
Events on the timeline
2
Under the months
7
Stage changes
1
Decisions
3
Statements
0
Figures
5
Entries and decisions under the months
2