Project Eisenhower Data Center Campus (Augusta, DRI #4171), in order
What happened with this project, oldest first: the stages it reached, what the county and its cities decided, and every dated step on the record. Each entry links its source.
1 event, March 27, 2024. The facts, newest first: the record; the place: Georgia.
A plain date is the day it happened, as the source states it, or as the line's own sentence states it ("voted on July 6"), which is where the line sits even when it was filed later. "Reported" and a date is the day a source published a line that carries no date of its own. Those lines, and lines that describe rather than report an act, sit under their month rather than on the timeline, with what was said and the figures other sources gave. Every timeline on the site reads its lines by this one rule. How dates are read.
Stages
2024 1 event
-
(content date)
waiting on permits
Eagle South, LLC filed Georgia DCA DRI #4171 on March 27, 2024 for Project Eisenhower, a 6 building, 2,155,800 square foot data center campus along Gordon Highway in Augusta, Richmond County. [1]
Local jurisdiction rules 2 decisions
County and municipal actions on the record in Richmond County County, listed separately from this facility's own timeline.
-
(source date; the content gives no date of its own)
Decision · Augusta (city)
Augusta leaders hosted meeting on data center ordinance wrdw.com (opens in a new tab)
-
(source date; the content gives no date of its own)
Decision · Augusta (city)
Augusta Commission planned to vote on data center ordinance on September 15, 2026 wfxg.com (opens in a new tab)
On the timeline: a stage change; an entry that reports an act on the day the source or its own sentence gives; and a decision, a published scorecard event on a row at or under the record's county, that reports an act. Under the months: a statement that names this record, a figure another source gave about it, matched by place and developer, an entry dated only by the day its source was published, and an entry or a decision that describes rather than reports an act. Each is on the record in its own right and keeps its own link.
For researchers
- Stage
- waiting on permits
- Events on the timeline
- 1
- Under the months
- 0
- Stage changes
- 1
- Decisions
- 2
- Statements
- 0
- Figures
- 0
- Entries and decisions under the months
- 0