Projects / PORTS-Pike Technology Campus / Timeline

PORTS-Pike Technology Campus, in order

What happened with this project, oldest first: the stages it reached, what the county and its cities decided, and every dated step on the record. Each entry links its source.

3 events, August 17, 2026 to September 2, 2026. Also on the record, under the month each belongs to: 6 statements, 12 figures from other sources and 8 lines that are not events of their own. The facts, newest first: the record; the place: Ohio.

A plain date is the day it happened, as the source states it, or as the line's own sentence states it ("voted on July 6"), which is where the line sits even when it was filed later. "Reported" and a date is the day a source published a line that carries no date of its own. Those lines, and lines that describe rather than report an act, sit under their month rather than on the timeline, with what was said and the figures other sources gave. Every timeline on the site reads its lines by this one rule. How dates are read.

Stages

  1. being built
  2. approved
  3. waiting on permits

Now: waiting on permits. A stage is the record's status after the entry that set it (the definitions).

2017 1 under the months

  1. Also in January 2017: 1 statement
    1. (content date; reported from elsewhere)

      Statement · Derek Merrin

      Merrin voted in 2017 for Ohio's 2018-19 budget which included tax breaks for data centers. TiffinOhio.net local outlet

2024 2 under the months

  1. Also in September 2024: 1 figure from another source
    1. (content date)

      Figure · TiffinOhio.net

      6,300,000 dollars: American Electric Power Service Corporation received $6.3 million in data center tax breaks from the state as of September 2024. TiffinOhio.net local outlet

  2. Also in December 2024: 1 figure from another source
    1. (content date)

      Figure · TiffinOhio.net

      2,500,000,000 dollars: Between 2017 and 2024, Ohio provided about $2.5 billion in tax incentives to attract data center development. TiffinOhio.net local outlet

2026 3 events

  1. (source date; the content gives no date of its own)

    being built

    OpenAI entered into a 20 year lease agreement with SB Energy and SoftBank Group on Monday [13]

  2. (source date; the content gives no date of its own)

    approved

    Bechtel and Kiewit Corp tapped to provide engineering, procurement, construction and other services for PORTS Pike [4]

  3. Also in August 2026: 3 statements, 9 figures from other sources and 4 lines that are not events of their own
    1. (source date; the content gives no date of its own)

      Entry

      Project is being built at the Portsmouth Gaseous Diffusion Plant, a former uranium enrichment facility [13]

    2. (source date; the content gives no date of its own)

      Entry

      By 2028 facility is set to generate 800 megawatts before construction is complete [13]

    3. (said in the source itself)

      Statement · Jensen Huang, Nvidia CEO and President

      Nvidia CEO Jensen Huang said now is the time to scale the AI infrastructure that will power the next industrial revolution Washington Examiner national outlet

    4. (said in the source itself)

      Statement · Chris Wright, Energy Secretary

      Energy Secretary Chris Wright said the data center will be bigger than any facility ever built in world history Washington Examiner national outlet

    5. (said in the source itself)

      Statement · OpenAI

      OpenAI said this gives a site that once supported American industry and national security a new role building infrastructure for the Intelligence Era Washington Examiner national outlet

    6. (source date; the content gives no date of its own)

      Figure · Washington Examiner

      1.56 GW: Largest operating U.S. data center by power capacity is SpaceXAI Colossus 2 in Tennessee at 1.563 gigawatts Washington Examiner national outlet

    7. (source date; the content gives no date of its own)

      Figure · Washington Examiner

      8 GW: Data center is planned to provide at least 8 gigawatts or 8 billion watts of electrical power Washington Examiner national outlet

    8. (source date; the content gives no date of its own)

      Figure · Washington Examiner

      10 GW: Plans to eventually expand power capacity to 10 gigawatts Washington Examiner national outlet

    9. (source date; the content gives no date of its own)

      Entry

      PORTS Pike data center campus located on site of former Portsmouth Gaseous Diffusion Plant uranium enrichment facility near Columbus, Ohio [4]

    10. (source date; the content gives no date of its own)

      Entry

      SB Energy will develop, own and operate data center campus including power generation [4]

    11. (source date; the content gives no date of its own)

      Figure · enr.com

      1,500,000,000 dollars: NVIDIA will invest 1.5 billion dollars in SB Energy to support its growth enr.com local outlet

    12. (source date; the content gives no date of its own)

      Figure · enr.com

      4.25 GW: Initial deployment expected to provide 4.25 gigawatts of AI factory capacity enr.com local outlet

    13. (source date; the content gives no date of its own)

      Figure · enr.com

      105,000,000,000 dollars: NVIDIA plans to invest up to 105 billion dollars to secure land, power and shell capacity for PORTS Pike Technology Campus enr.com local outlet

    14. (source date; the content gives no date of its own)

      Figure · enr.com

      4,200,000,000 dollars: SB Energy plans to invest at least 4.2 billion dollars in new regional grid infrastructure through partnership with AEP Ohio enr.com local outlet

    15. (source date; the content gives no date of its own)

      Figure · enr.com

      9.2 GW: PORTS Pike power generation capacity about 9.2 gigawatts from natural gas enr.com local outlet

    16. (source date; the content gives no date of its own)

      Figure · enr.com

      10 GW: PORTS Pike Technology Campus planned 10 gigawatt data center campus enr.com local outlet

  4. (source date; the content gives no date of its own)

    waiting on permits

    Prime Data Centers developer detailed Starpointe data center proposal on September 2, 2026 [12]

  5. Also in September 2026: 2 statements, 1 figure from another source and 4 lines that are not events of their own
    1. (source date; the content gives no date of its own)

      Entry

      Construction on each building expected to take between 14 to 16 months [12]

    2. (source date; the content gives no date of its own)

      Entry

      Prime hopes to begin work on the project sometime in early 2027 [12]

    3. (said in the source itself)

      Statement · Kate Nolan Bryden, Prime Data Centers Senior Vice President of Development

      Kate Nolan Bryden, Prime Senior Vice President of Development and project lead, testified that the facility will use advanced closed loop cooling systems Observer-Reporter local outlet

    4. (source date; the content gives no date of its own)

      Entry

      PORTS-Pike Technology Campus is a 10 GW data center with co located gas generator [2]

    5. (source date; the content gives no date of its own)

      Decision · Pike County (county)

      Ohio Power Siting Board public hearing scheduled for Baku Gavin Transmission Line project on October 27, 2026 at 6 p.m. at Jackson High School Auditorium. yahoo.com

    6. (said in the source itself)

      Statement · Derek Merrin, Republican congressional candidate

      Derek Merrin reported capital gains of at least $1,200 from Nvidia stock and options in a financial disclosure covering 2025 through mid-2026. TiffinOhio.net local outlet

    7. (source date; the content gives no date of its own)

      Figure · TiffinOhio.net

      75 percent: 75% of Ohio respondents oppose the construction of data centers in their communities according to a September poll from Bowling Green State University. TiffinOhio.net local outlet

On the timeline: a stage change; an entry that reports an act on the day the source or its own sentence gives; and a decision, a published scorecard event on a row at or under the record's county, that reports an act. Under the months: a statement that names this record, a figure another source gave about it, matched by place and developer, an entry dated only by the day its source was published, and an entry or a decision that describes rather than reports an act. Each is on the record in its own right and keeps its own link.

For researchers
Slug
ports-pike-technology-campus-oh
Status value
permitting
Events on the timeline
3
Under the months
26
Stage changes
3
Decisions
1
Statements
6
Figures
12
Entries and decisions under the months
8