Verrus Oakline Mill Creek Data Center, in order
What happened with this project, oldest first: the stages it reached, what the county and its cities decided, and every dated step on the record. Each entry links its source.
9 events, July 2026 to August 28, 2026. Also on the record, under the month each belongs to: 10 statements, 4 figures from other sources and 5 dates when source pages were read and verified. The facts, newest first: the record; the place: Oregon.
A plain date is the day it happened, as the source states it, or as the line's own sentence states it ("voted on July 6"), which is where the line sits even when it was filed later. "Reported" and a date is the day a source published a line that carries no date of its own. Those lines, and lines that describe rather than report an act, sit under their month rather than on the timeline, with what was said and the figures other sources gave. Every timeline on the site reads its lines by this one rule. How dates are read.
Stages
2026 9 events
-
(the month its own sentence names; no day is given; filed under Sep 8, 2026)
Entry
Verrus CEO Nelson Abramson filed land use application for data center with two 600,000 square foot buildings in late July 2026 [19]
-
(content date)
proposed
The City of Salem disclosed a proposed Verrus data center campus at the Mill Creek Corporate Center after being released from a nondisclosure agreement. [22]
-
(content date)
Entry
Residents filled Salem City Council chambers for about five hours of public comment on the proposal. [24]
-
(content date)
Entry
Governor Tina Kotek directed the Department of Administrative Services to terminate the sale of 32 acres of state land at Mill Creek to Verrus. [25]
-
(content date)
waiting on permits
Alderstone LLC filed a land use application with the City of Salem for two data center buildings on three lots at the Mill Creek Corporate Center. [27]
-
(the day its own sentence names; filed under Sep 21, 2026)
Entry
Verrus submitted a data center application for the Mill Creek Corporate Center on July 31, 2026, for a $5.1 billion project. [17]
-
(content date)
Entry
Salem City Council voted unanimously at a special meeting to initiate a moratorium on new data center applications. [28]
-
(content date)
Entry
City officials deemed the Verrus application incomplete, citing a missing noise study and archaeological review. [30]
-
(the day its own sentence names; filed under Sep 21, 2026)
Entry
Verrus application was deemed incomplete on August 28, 2026. [17]
-
Also in August 2026: 7 statements, 4 figures from other sources and 2 dates when source pages were read and verified
-
(source date; the content gives no date of its own)
Figure · Yahoo
5,100,000,000 dollars: A proposed $5.1 billion AI data center facility was brought before Salem City Council. Yahoo (opens in a new tab) national outlet
-
(source date; the content gives no date of its own)
Entry
SEDCOR selected Verrus over multiple other prospective companies for a data center at Mill Creek Corporate Center despite Verrus having never built a data center before [33]
-
(said in the source itself)
Statement · Erik Andersson, SEDCOR director
SEDCOR director Erik Andersson cited Verrus's more sustainable approach as reason for selection Salem Reporter (opens in a new tab) local outlet
-
(source date; the content gives no date of its own)
Figure · Salem Reporter
29,000,000 gallons: Salem's average daily water demand is 29 million gallons with a peak day being 51 million gallons per day Salem Reporter (opens in a new tab) local outlet
-
(said in the source itself)
Statement · Nelson Abramson, Verrus (implied leadership)
Nelson Abramson spent 20 years at Google including on its data center team, then ran infrastructure at X Salem Reporter (opens in a new tab) local outlet
-
(source date; the content gives no date of its own)
Entry
Application for roughly 100 acre AI data center in Salem Mill Creek Corporate Center deemed incomplete by city planning staff [30]
-
(said in the source itself)
Statement · Salem city planning staff
Verrus, the Google backed company, must resubmit application with noise study, separate application for each development site, and archaeological review Salem Reporter (opens in a new tab) local outlet
-
(said in the source itself)
Statement · Flood Light News
Microsoft backed data center in Vineland was caught with 27 unpermitted gas fired generators, disclosed more energy use and more air pollution than promised to community Salem Reporter (opens in a new tab) local outlet
-
(said in the source itself)
Statement · The Oregonian/OregonLive
Oregon data center market is one of the largest in the world due to property tax incentives and lack of a sales tax, with data centers first appearing around 2006 Salem Reporter (opens in a new tab) local outlet
-
(said in the source itself)
Statement · Salem community members
Verrus submitted Salem data center project on Friday to move ahead before Monday city council moratorium vote Salem Reporter (opens in a new tab) local outlet
-
(said in the source itself)
Statement · Salem community members
Verrus operated under nondisclosure agreement from March 2025 through July 10, 2026 before submitting Salem project Salem Reporter (opens in a new tab) local outlet
-
(source date; the content gives no date of its own)
Figure · Salem Reporter
75 jobs: Proposed Salem data center (Verrus project) expected to employ 75 people, according to public comment discussion Salem Reporter (opens in a new tab) local outlet
-
(source date; the content gives no date of its own)
Figure · Salem Reporter
6,700,000 dollars: Contract shows state agreed to sell 32 acres to Verrus for 6.7 million dollars Salem Reporter (opens in a new tab) local outlet
-
-
Also in September 2026: 3 statements and 3 dates when source pages were read and verified
-
(source date; the content gives no date of its own)
Entry
Verrus submitted a land use application for the first phase of a $5.1 billion AI data center at Mill Creek Corporate Center [21]
-
(source date; the content gives no date of its own)
Entry
Verrus is building a $5.1 billion data center in Salem's Mill Creek Corporate Center [16]
-
(said in the source itself)
Statement · Verrus
Verrus hired a lobbyist, Drew Hagedorn, registered September 4, 2026, for data center development, energy and utilities, land use and permitting salemreporter.com (opens in a new tab) local outlet
-
(said in the source itself)
Statement · Salem city officials
Town hall focused on hearing input on data center water usage, noise, job creation and electricity consumption KPTV (opens in a new tab) local outlet
-
(said in the source itself)
Statement · Dan Atchison, Salem city attorney
The city could extend the moratorium by six months if approved. Salem Reporter (opens in a new tab) local outlet
-
(source date; the content gives no date of its own)
Entry · Moratorium
Verrus $5.1 billion data center project at Mill Creek Corporate Center prohibited from construction phase as long as moratorium is in effect [18]
-
On the timeline: a stage change; an entry that reports an act on the day the source or its own sentence gives; and a decision, a published scorecard event on a row at or under the record's county, that reports an act. Under the months: a statement that names this record, a figure another source gave about it, matched by place and developer, an entry dated only by the day its source was published, and an entry or a decision that describes rather than reports an act. Each is on the record in its own right and keeps its own link.
For researchers
- Stage
- waiting on permits
- Events on the timeline
- 9
- Under the months
- 19
- Stage changes
- 2
- Decisions
- 0
- Statements
- 10
- Figures
- 4
- Entries and decisions under the months
- 5