NTT Mesa data center campus, in order

What happened with this project, oldest first: the stages it reached, what the county and its cities decided, and every dated step on the record. Each entry links its source.

10 events, January 1, 2025 to May 18, 2026. Also on the record, under the month each belongs to: 6 statements, 2 figures from other sources and 16 lines that are not events of their own. The facts, newest first: the record; the place: Arizona.

A plain date is the day it happened, as the source states it, or as the line's own sentence states it ("voted on July 6"), which is where the line sits even when it was filed later. "Reported" and a date is the day a source published a line that carries no date of its own. Those lines, and lines that describe rather than report an act, sit under their month rather than on the timeline, with what was said and the figures other sources gave. Every timeline on the site reads its lines by this one rule. How dates are read.

Stages

  1. approved
  2. being built
  3. waiting on permits

Now: waiting on permits. A stage is the record's status after the entry that set it (the definitions).

2025 7 events

  1. (the year its own sentence names; filed under Jun 9, 2026)

    Entry

    Tokyo based NTT Data Group purchased 173 acres at 10126 E. Pecos Road for 300 million dollars in 2025 [6]

  2. (the day its own sentence names; filed under Apr 9, 2025)

    Entry

    NTT Global Data Centers purchased 174 acres in southeast Mesa at northeast corner of Pecos and Crimson roads on March 25, 2025 [2]

  3. (content date)

    approved

    NTT Data Centers acquired 173 acre planned data center park in Mesa for $300 million in March 2025 [1]

  4. Also in April 2025: 1 line that is not an event of its own
    1. (content date)

      Entry

      NTT also owns a 102 acre data campus in the Elliot Road Technology Corridor in Mesa with first of seven planned data centers opened in 2022 with 126,000 square feet [2]

  5. Also in June 2025: 2 lines that are not events of their own
    1. (source date; the content gives no date of its own)

      Decision · Mesa (city)

      Proposed 60 foot height limit for data centers themesatribune.com

    2. (source date; the content gives no date of its own)

      Decision · Mesa (city)

      Proposed 400 foot setback from residential areas for data centers themesatribune.com

  6. (the month its own sentence names; no day is given; filed under Jul 14, 2025)

    Decision · Mesa (city)

    Mesa City Council adopted new zoning rules for data centers and their operations in a City Council vote in July 2025 kjzz.org

  7. (content date)

    Decision · Mesa (city)

    Mesa City Council unanimously approved data center amendments on July 8, 2025, with two members absent themesatribune.com

  8. Also in July 2025: 1 line that is not an event of its own
    1. (source date; the content gives no date of its own)

      Decision · Mesa (city)

      Mesa data center ordinance restricts future projects to land zoned for industrial use themesatribune.com

  9. (the day its own sentence names; filed under Jun 9, 2026)

    Entry

    Project grandfathered under Mesa's tighter data center rules because NTT submitted application August 4, 2025, four days before city's new data center ordinance took effect [6]

  10. Also in August 2025: 2 lines that are not events of their own
    1. (source date; the content gives no date of its own)

      Decision · Mesa (city)

      Mesa data centers will need City Council approval to build under new regulations kjzz.org

    2. (source date; the content gives no date of its own)

      Decision · Mesa (city)

      New Mesa zoning amendments direct data centers to heavy industrial zones and general industrial zones kjzz.org

  11. (the month its own sentence names; no day is given; filed under Dec 11, 2025)

    Decision · Maricopa County (county)

    Maricopa County Board of Supervisors overhauled its zoning ordinance at a meeting Wednesday in December 2025 kjzz.org

  12. Also in December 2025: 3 lines that are not events of their own
    1. (source date; the content gives no date of its own)

      Decision · Maricopa County (county)

      It is the first time data centers have been defined in county zoning rules kjzz.org

    2. (source date; the content gives no date of its own)

      Decision · Maricopa County (county)

      The modernized ordinance updated how the county defines a data center and restricts them to industrial areas kjzz.org

    3. (source date; the content gives no date of its own)

      Decision · Maricopa County (county)

      Maricopa County adopted a new ordinance clarifying guidelines for data center development bizjournals.com

2026 3 events

  1. (content date)

    being built

    NTT Data Centers planning sixth building, phase PH6, at 10256 E. Elliot Road in Mesa [3]

  2. Also in January 2026: 3 lines that are not events of their own
    1. (content date)

      Entry

      City of Mesa park planned on west side of NTT Data Centers site [3]

    2. (content date)

      Entry

      NTT Data Centers phases PH1 to PH5 are under construction or in operation [3]

    3. (content date)

      Entry

      Site covers 101 acres north of Elliot Road and east of Crismon Road [3]

  3. (content date)

    waiting on permits

    Data center project in Mesa moving forward [4]

  4. (content date)

    Entry

    Planning and zoning board approved project with conditions [5]

  5. Also in May 2026: 2 lines that are not events of their own
    1. (content date)

      Entry

      Project still needs city council approval [5]

    2. (content date)

      Entry

      NTT Global Data Centers data center campus is slated for northeast corner of Pecos and Crismon roads in Mesa [5]

  6. Also in June 2026: 3 statements and 1 line that is not an event of its own
    1. (content date; reported from elsewhere)

      Statement · Asif Kazimm, NTT spokesperson

      Each building would have internal closed loop and chiller system on roof with closed loop water cooling system filled up only once Copper Courier local outlet

    2. (content date; reported from elsewhere)

      Statement · Nathan Taylor Taft, Mesa High School student and co-director of East Valley Unite

      Nathan Taylor Taft, Mesa High School student and co director of East Valley Unite, urged Mesa City Council on June 8 to reject the proposed NTT data center Copper Courier local outlet

    3. (content date; reported from elsewhere)

      Statement · Nathan Taylor Taft, Mesa High School student and co-director of East Valley Unite

      Taft expressed concern about the project's potential impact on Arizona's water supply Copper Courier local outlet

    4. (source date; the content gives no date of its own)

      Decision · Chandler (city)

      Chandler capped data center water use youtube.com

  7. Also in August 2026: 3 statements
    1. (content date; reported from elsewhere)

      Statement · Indivisible leaders

      Indivisible leaders claimed they are not given equal speaking time compared to council supporters and data center project no longer appears on public agendas ABC15 Arizona local outlet

    2. (content date; reported from elsewhere)

      Statement · Mesa city spokesperson

      City spokesperson said rule changes were implemented to keep meetings safe and productive ABC15 Arizona local outlet

    3. (content date; reported from elsewhere)

      Statement · Meagan O'Connor and Jillian Ryan, Indivisible leaders

      Meagan O'Connor and Jillian Ryan lead East Valley chapters of Indivisible opposing NTT project ABC15 Arizona local outlet

  8. Also in September 2026: 2 figures from other sources and 1 line that is not an event of its own
    1. (the day the page was read; it gives no date of its own)

      Figure · Copper Courier

      2,200,000 square feet: NTT proposing seven building 2.2 million square foot campus with private power substation and new SRP substation Copper Courier local outlet

    2. (the day the page was read; it gives no date of its own)

      Figure · yourvalley.net

      195,000 square feet: NTT Data Centers PH6 building is 195,000 square feet yourvalley.net local outlet

    3. (source date; the content gives no date of its own)

      Decision · Gilbert (city)

      Gilbert leaders want strict rules on data centers to make it hard for server farms to set up shop; new rules expected in September but delayed to October or November. watereducation.org

On the timeline: a stage change; an entry that reports an act on the day the source or its own sentence gives; and a decision, a published scorecard event on a row at or under the record's county, that reports an act. Under the months: a statement that names this record, a figure another source gave about it, matched by place and developer, an entry dated only by the day its source was published, and an entry or a decision that describes rather than reports an act. Each is on the record in its own right and keeps its own link.

For researchers
Slug
ntt-mesa-data-center-campus-az
Status value
permitting
Events on the timeline
10
Under the months
24
Stage changes
3
Decisions
13
Statements
6
Figures
2
Entries and decisions under the months
16