Nscale is developing a 240 MW artificial intelligence data center campus in Ward County near Pyote, Texas under a Phase 1 lease agreement with Microsoft, while Microsoft declined in November 2026 to exercise an option for a multibillion dollar Phase 2 expansion at the site. [1] Updated project status from approved to proposed: TCEQ Construction Stormwater General Permit TXR1548ZO is an administrative stormwater registration rather than a vertical building permit or final county tax abatement approval. [1]
How much water it would use and who would use it have not been disclosed.
Sources:
A comparison is arithmetic on two published rows and is never a new fact (how comparisons are made).
Connected government officials, corporate entities, utilities and local rules on the public record.
Citizen privacy standard: Elected officials, corporate applicants and utility executives are named in full. Private residents who speak at public comment are cited as Resident First L. unless they hold public office or speak on behalf of an organization.
Disclosed engineering ceilings, reported actuals and primary regulatory basis for Nscale Ward County AI Data Center Campus.
| Field / Parameter | Permitted / Disclosed Ceiling | Reported Actual | Basis & Primary Source |
|---|---|---|---|
| Electrical Capacity (MW) | 240 MW | the developer's figure [1] .tceq.texas.gov | |
| Site Footprint (Acres) | |||
| Data Hall Buildings | |||
| Cooling & Water System | |||
| Backup Diesel / Gas Generators | |||
| Tax Abatement & Annual Revenue |
Blank cell: not disclosed by any source on file.
The record adds each the day a source gives it. Why these documents.
Chronological regulatory, corporate and permitting events on the record, newest first.
· Status: proposed (content date)
Updated project status from approved to proposed: TCEQ Construction Stormwater General Permit TXR1548ZO is an administrative stormwater registration rather than a vertical building permit or final county tax abatement approval.
· Project status (approved to proposed)
Updated stage from approved to proposed because a TCEQ construction stormwater general permit registration (TXR1548ZO) is a preliminary grading notice of intent rather than a vertical building permit or final development approval.
Verified exact site address and applicant legal entity from TCEQ Construction Stormwater General Permit TXR1548ZO issued September 28, 2026.
Every correction on the record is on the corrections page.
No other verified data center record in Texas is located within 60 miles of this site. Browse all data centers in Texas.
Answered directly from the verified filings and local actions on this page.
Nscale is the developer, datacenterdynamics.com (opens in a new tab). No construction contractor is named on the record yet.
Power: 240 MW (the developer's figure, www2.tceq.texas.gov (opens in a new tab)). Water: not disclosed by any source on file.
It is proposed, since November 9, 2026. The newest entry, November 9, 2026: Updated project status from approved to proposed: TCEQ Construction Stormwater General Permit TXR1548ZO is an administrative stormwater registration rather than a vertical building permit or final county tax abatement approval. [1]
No decision by Pyote or Ward County about data centers is on the record. The Ward County page and the Texas scorecard list every rated row the day a person publishes one.
2 sources on file.
This site is in the ERCOT All (ERCT) regional power market.
Every number on this page comes from a named source. Click any source to open the document in a new tab.
If a link has moved or a document has changed, let us know and we will update the record and log the change.
Every record on this page carries its sources and the date it was last verified. When you cite it in a story, a study or a public filing, link to this page and give the date you accessed it.
Data Center Record. Nscale Ward County AI Data Center Campus. Last verified November 9, 2026. https://datacenterrecord.org/projects/nscale-ward-county-data-center-tx. Accessed November 17, 2026.
Every row on this page is available to download with its source, its basis and the date it was last verified.
Download this page's records (CSV) JSON
Licensed CC BY-NC 4.0. Say where it came from and do not sell it or use it to train a commercial model without a license.
Free to use and republish with attribution for reporting, research, teaching and public filings under CC BY-NC 4.0. Commercial, enterprise, financial or AI training use needs a commercial license.
Data Center Record takes no money from data center developers, operators, utilities or trade groups. That rule does not change for licensing.
Data Center Record is an independent project and takes no money from data center developers, operators, utilities or trade groups. Reader support keeps the record free to read, with no ads and no paywall.
Last verified , first recorded . Every correction is logged on the corrections page and under What happened. Report a correction · Send a tip about Nscale Ward County AI Data Center Campus