Novva Salt Lake City data center, in order

What happened with this project, oldest first: the stages it reached, what the county and its cities decided, and every dated step on the record. Each entry links its source.

4 events, October 24, 2022 to January 1, 2024. Also on the record, under the month each belongs to: 2 figures from other sources and 7 lines that are not events of their own. The facts, newest first: the record; the place: Utah.

A plain date is the day it happened, as the source states it, or as the line's own sentence states it ("voted on July 6"), which is where the line sits even when it was filed later. "Reported" and a date is the day a source published a line that carries no date of its own. Those lines, and lines that describe rather than report an act, sit under their month rather than on the timeline, with what was said and the figures other sources gave. Every timeline on the site reads its lines by this one rule. How dates are read.

Stages

  1. running

Now: running. A stage is the record's status after the entry that set it (the definitions).

2022 1 event

  1. (source date; the content gives no date of its own)

    running

    Novva began construction on 100 megawatt data center in North Las Vegas, Nevada, expected to open late 2023, 275,000 square feet, $400 million, on 20 acre campus [3]

  2. Also in October 2022: 2 figures from other sources
    1. (source date; the content gives no date of its own)

      Figure · Data Center Frontier

      1 GW: Novva long term goal to deploy up to 1 gigawatt capacity by 2027 Data Center Frontier trade press

    2. (source date; the content gives no date of its own)

      Figure · Data Center Frontier

      355,000,000 USD: CIM Group and Novva announced agreement on additional investment of up to $355 million in June 2022 Data Center Frontier trade press

2023 2 events

  1. (the year its own sentence names; filed under Mar 13, 2025)

    Entry

    Phase 2 construction started in late 2023, covers 318,000 sq ft and adds 72 MW of capacity [4]

  2. (the year its own sentence names; filed under Mar 13, 2025)

    Entry

    Phase 1 facility began operating in 2023, built by Layton Construction Co. [4]

2024 1 event

  1. (the year its own sentence names; filed under Mar 13, 2025)

    Entry

    Phase 3 construction started last year, covers 318,000 sq ft and adds 72 MW of capacity [4]

  2. Also in May 2024: 1 line that is not an event of its own
    1. (source date; the content gives no date of its own)

      Decision · Salt Lake County (county)

      Salt Lake County Mayor and County Council voted against the tax breaks datacenterknowledge.com

2025 3 under the months

  1. Also in March 2025: 3 lines that are not events of their own
    1. (source date; the content gives no date of its own)

      Entry

      Campus already leased to a leading global tech company in 2023 [4]

    2. (source date; the content gives no date of its own)

      Entry

      Novva data centers use cooling system with ambient air, heat exchange coils and refrigerant, consuming about 84% less water than similar data centers in the area [4]

    3. (source date; the content gives no date of its own)

      Entry

      Phases 2 and 3 are expected to be completed next year (2026) [4]

2026 3 under the months

  1. Also in September 2026: 3 lines that are not events of their own
    1. (the day the page was read; it gives no date of its own)

      Entry

      Novva Data Centers lists Novva Salt Lake City data center at Salt Lake City, Utah on its own page of data center locations, read September 14, 2026. [2]

    2. (source date; the content gives no date of its own)

      Decision · Salt Lake County (county)

      County staff will look at every legal option available for data center regulations in unincorporated parts of the county. sltrib.com

    3. (source date; the content gives no date of its own)

      Decision · Salt Lake County (county)

      Salt Lake County hit pause on data centers and is developing new regulations. sltrib.com

On the timeline: a stage change; an entry that reports an act on the day the source or its own sentence gives; and a decision, a published scorecard event on a row at or under the record's county, that reports an act. Under the months: a statement that names this record, a figure another source gave about it, matched by place and developer, an entry dated only by the day its source was published, and an entry or a decision that describes rather than reports an act. Each is on the record in its own right and keeps its own link.

For researchers
Slug
novva-salt-lake-city-data-center-ut
Status value
operational
Events on the timeline
4
Under the months
9
Stage changes
1
Decisions
3
Statements
0
Figures
2
Entries and decisions under the months
7