Data Center Record.
Projects / NextEra and Brookfield Kentucky Data Center Campus / Timeline

NextEra and Brookfield Kentucky Data Center Campus, in order

What happened with this project, oldest first: the stages it reached, what the county and its cities decided, and every dated step on the record. Each entry links its source.

Nothing on the record is dated to the day it happened yet. Also on the record, under the month each belongs to: 8 figures from other sources. The facts, newest first: the record; the place: Kentucky.

A plain date is the day it happened, as the source states it, or as the line's own sentence states it ("voted on July 6"), which is where the line sits even when it was filed later. "Reported" and a date is the day a source published a line that carries no date of its own. Those lines, and lines that describe rather than report an act, sit under their month rather than on the timeline, with what was said and the figures other sources gave. Every timeline on the site reads its lines by this one rule. How dates are read.

2026 8 under the months

  1. Also in September 2026: 8 figures from other sources
    1. (source date; the content gives no date of its own)

      Figure · Daily Energy Insider

      2 GW: Project will include 2 gigawatts natural gas generation Daily Energy Insider (opens in a new tab) news outlet

    2. (source date; the content gives no date of its own)

      Figure · Daily Energy Insider

      2.6 GW: Project will include 2.6 gigawatts battery energy storage Daily Energy Insider (opens in a new tab) news outlet

    3. (source date; the content gives no date of its own)

      Figure · Daily Energy Insider

      4.6 GW: Project will generate 4.6 gigawatts of newly built generation resources Daily Energy Insider (opens in a new tab) news outlet

    4. (source date; the content gives no date of its own)

      Figure · Daily Energy Insider

      8,000 jobs: Project expected to create 8000 construction jobs Daily Energy Insider (opens in a new tab) news outlet

    5. (source date; the content gives no date of its own)

      Figure · Daily Energy Insider

      1.8 GW: Campus will provide 1.8 gigawatts utility capacity Daily Energy Insider (opens in a new tab) news outlet

    6. (source date; the content gives no date of its own)

      Figure · Daily Energy Insider

      600 jobs: Project expected to create 600 permanent operations jobs Daily Energy Insider (opens in a new tab) news outlet

    7. (source date; the content gives no date of its own)

      Figure · Daily Energy Insider

      1.2 GW: Campus will provide 1.2 gigawatts computing capacity Daily Energy Insider (opens in a new tab) news outlet

    8. (source date; the content gives no date of its own)

      Figure · WPSD Local 6

      8,000 jobs: The Paducah American Energy Hub data center at the Department of Energy Paducah Site is a historic $100 billion investment that will potentially create 8,000 construction jobs and 600 permanent ones. WPSD Local 6 (opens in a new tab) news outlet

On the timeline: a stage change; an entry that reports an act on the day the source or its own sentence gives; and a decision, a published scorecard event on a row at or under the record's county, that reports an act. Under the months: a statement that names this record, a figure another source gave about it, matched by place and developer, an entry dated only by the day its source was published, and an entry or a decision that describes rather than reports an act. Each is on the record in its own right and keeps its own link.

For researchers
Stage
reported
Events on the timeline
0
Under the months
8
Stage changes
0
Decisions
0
Statements
0
Figures
8
Entries and decisions under the months