MLP Ventures King of Prussia data center campus, in order

What happened with this project, oldest first: the stages it reached, what the county and its cities decided, and every dated step on the record. Each entry links its source.

1 event, August 6, 2026 to August 6, 2026. Also on the record, under the month each belongs to: 5 statements and 3 lines that are not events of their own. The facts, newest first: the record; the place: Pennsylvania.

A plain date is the day it happened, as the source states it, or as the line's own sentence states it ("voted on July 6"), which is where the line sits even when it was filed later. "Reported" and a date is the day a source published a line that carries no date of its own. Those lines, and lines that describe rather than report an act, sit under their month rather than on the timeline, with what was said and the figures other sources gave. Every timeline on the site reads its lines by this one rule. How dates are read.

Stages

  1. reported

Now: reported. A stage is the record's status after the entry that set it (the definitions).

2026 1 event

  1. (content date)

    reported

    Brian O'Neill of MLP Ventures is seeking approval for a 4.5 million square foot data center campus in King of Prussia [1]

  2. Also in August 2026: 5 statements and 2 lines that are not events of their own
    1. (content date)

      Entry

      Brian O'Neill is seeking approval for a 2 million square foot data center facility at 900 Conshohocken Road in Plymouth Township [1]

    2. (content date; reported from elsewhere)

      Statement · Brian O'Neill, MLP Ventures developer

      O'Neill stated 'Will I win legally? Absolutely. And I'll spend whatever it takes to do that because what I'm building is right, and it's right for the community.' 6abc Philadelphia local outlet

    3. (content date; reported from elsewhere)

      Statement · Brian O'Neill, MLP Ventures developer

      O'Neill said his proposed facilities would use closed loop water systems, generate their own electricity, create no light pollution and comply with local noise limits 6abc Philadelphia local outlet

    4. (content date; reported from elsewhere)

      Statement · Brian O'Neill, MLP Ventures developer

      Brian O'Neill said he is committed to moving forward with the projects despite community opposition 6abc Philadelphia local outlet

    5. (content date; reported from elsewhere)

      Statement · Lynne Viscio, Plymouth Township Council President

      Plymouth Township Council President Lynne Viscio said O'Neill rejected more than 40 proposed safeguards and conditions 6abc Philadelphia local outlet

    6. (content date; reported from elsewhere)

      Statement · Brian O'Neill, MLP Ventures developer

      O'Neill called the township council's claim that he rejected safeguards a 'bald faced lie' and said he agreed to most requests 6abc Philadelphia local outlet

    7. (source date; the content gives no date of its own)

      Decision · Upper Merion (city)

      Developer sued Upper Merion Township planning commission and board of supervisors; vote scheduled for Thursday pending court order cbsnews.com

  3. Also in September 2026: 1 line that is not an event of its own
    1. (source date; the content gives no date of its own)

      Decision · Upper Merion (city)

      Upper Merion Township board rejected proposal for five data centers totaling over 4.6 million square feet relying on natural gas turbines and diesel backup generators northeasttimes.com

On the timeline: a stage change; an entry that reports an act on the day the source or its own sentence gives; and a decision, a published scorecard event on a row at or under the record's county, that reports an act. Under the months: a statement that names this record, a figure another source gave about it, matched by place and developer, an entry dated only by the day its source was published, and an entry or a decision that describes rather than reports an act. Each is on the record in its own right and keeps its own link.

For researchers
Slug
mlp-ventures-king-of-prussia-data-center-campus-pa
Status value
rumored
Events on the timeline
1
Under the months
8
Stage changes
1
Decisions
2
Statements
5
Figures
0
Entries and decisions under the months
3