Projects / Meta plus Moss Bluff / Timeline

Meta plus Moss Bluff, in order

What happened with this project, oldest first: the stages it reached, what the county and its cities decided, and every dated step on the record. Each entry links its source.

2 events, April 2026 to August 12, 2026. Also on the record, under the month each belongs to: 6 statements, 2 figures from other sources and 7 lines that are not events of their own. The facts, newest first: the record; the place: Louisiana.

A plain date is the day it happened, as the source states it, or as the line's own sentence states it ("voted on July 6"), which is where the line sits even when it was filed later. "Reported" and a date is the day a source published a line that carries no date of its own. Those lines, and lines that describe rather than report an act, sit under their month rather than on the timeline, with what was said and the figures other sources gave. Every timeline on the site reads its lines by this one rule. How dates are read.

Stages

  1. reported

Now: reported. A stage is the record's status after the entry that set it (the definitions).

2026 2 events

  1. (the month its own sentence names; no day is given; filed under Sep 10, 2026)

    Entry

    Azimuth Renewables signed option to purchase about 1,200 acres in Moss Bluff in April 2026 [2]

  2. (source date; the content gives no date of its own)

    reported

    Discussions appear to be in early stages between landowner Kenny Nichols and a potential developer [4]

  3. Also in August 2026: 2 statements and 1 line that is not an event of its own
    1. (source date; the content gives no date of its own)

      Decision · Calcasieu Parish (county)

      Calcasieu Parish Police Jury confirmed no permits have been obtained or proposals submitted for a data center in Moss Bluff as of Tuesday theadvocate.com

    2. (said in the source itself)

      Statement · Brett Geymann, State Rep., R-Lake Charles

      State Rep. Brett Geymann said no project is currently moving forward through Louisiana Economic Development or the Southwest Louisiana Economic Alliance theadvocate.com local outlet

    3. (said in the source itself)

      Statement · Brett Geymann, State Rep., R-Lake Charles

      Geymann said he does not believe there should be a data center in Moss Bluff because it is a bedroom community and nonindustrial theadvocate.com local outlet

  4. Also in September 2026: 4 statements, 2 figures from other sources and 6 lines that are not events of their own
    1. (source date; the content gives no date of its own)

      Entry

      Data center would occupy fraction of 1,168 acres in wooded rural portion of Moss Bluff [2]

    2. (source date; the content gives no date of its own)

      Entry

      Azimuth Renewables has three years to purchase property with optional one year extension [2]

    3. (source date; the content gives no date of its own)

      Decision · Calcasieu Parish (county)

      Project requires Calcasieu Parish Planning and Zoning Board approval theadvocate.com

    4. (said in the source itself)

      Statement · Louisiana state

      Project must fully fund its own power generation and grid infrastructure costs The Advocate local outlet

    5. (source date; the content gives no date of its own)

      Figure · The Advocate

      200,000,000 USD: To qualify for state tax incentives project must commit to minimum $200 million capital investment The Advocate local outlet

    6. (source date; the content gives no date of its own)

      Figure · The Advocate

      50 jobs: To qualify for state tax incentives project must create at least 50 new permanent jobs The Advocate local outlet

    7. (source date; the content gives no date of its own)

      Entry

      Plans are still in early stages and nothing firm has been decided yet [1]

    8. (source date; the content gives no date of its own)

      Entry

      Company has option to purchase 1,100 acres [1]

    9. (source date; the content gives no date of its own)

      Entry

      Azimuth Renewables considering building a data center on 1,100 acres near Coffey Road in Moss Bluff [1]

    10. (said in the source itself)

      Statement · Brett Geymann, Louisiana State Rep.

      Brett Geymann stated that news of the considered data center has fueled opposition to competing solar farm proposal American Press local outlet

    11. (said in the source itself)

      Statement · Brett Geymann, State Representative

      Residents of Moss Bluff oppose data center because houses border the proposed property and residents do not want to live that close to such facilities louisianaradionetwork.com local outlet

    12. (said in the source itself)

      Statement · Brett Geymann, State Representative

      Moss Bluff was planned strictly as a residential community with no heavy commercial, light industrial or heavy industrial zoning louisianaradionetwork.com local outlet

On the timeline: a stage change; an entry that reports an act on the day the source or its own sentence gives; and a decision, a published scorecard event on a row at or under the record's county, that reports an act. Under the months: a statement that names this record, a figure another source gave about it, matched by place and developer, an entry dated only by the day its source was published, and an entry or a decision that describes rather than reports an act. Each is on the record in its own right and keeps its own link.

For researchers
Slug
meta-plus-moss-bluff-la
Status value
rumored
Events on the timeline
2
Under the months
15
Stage changes
1
Decisions
2
Statements
6
Figures
2
Entries and decisions under the months
7