Meta Kuna Data Center, in order

What happened with this project, oldest first: the stages it reached, what the county and its cities decided, and every dated step on the record. Each entry links its source.

4 events, January 1, 2022 to September 4, 2026. Also on the record, under the month each belongs to: 8 statements, 7 figures from other sources and 13 dates when source pages were read and verified. The facts, newest first: the record; the place: Idaho.

A plain date is the day it happened, as the source states it, or as the line's own sentence states it ("voted on July 6"), which is where the line sits even when it was filed later. "Reported" and a date is the day a source published a line that carries no date of its own. Those lines, and lines that describe rather than report an act, sit under their month rather than on the timeline, with what was said and the figures other sources gave. Every timeline on the site reads its lines by this one rule. How dates are read.

Stages

  1. running

Now: running. A stage is the record's status after the entry that set it (the definitions).

2022 1 event

  1. (the year its own sentence names; filed under Sep 8, 2026)

    Entry

    Data center broke ground in 2022 [7]

  2. Also in February 2022: 2 statements and 1 date when a source page was read and verified
    1. (source date; the content gives no date of its own)

      Entry

      Meta is building a data center in Idaho for $800 million [3]

    2. (content date; reported from elsewhere)

      Statement · Joe Stear, Mayor

      Kuna welcomes Meta to our city and values their commitment to our community. As the first large anchor in the city's East Kuna Industrial area, their infrastructure investment is a catalyst for expanding the city's ability to support well-paying jobs and attract other industrial and manufacturing users the Kuna. Data Center Dynamics (opens in a new tab) trade press

    3. (content date; reported from elsewhere)

      Statement · Darcy Nothnagle, Director of Community and Economic Development

      We are thrilled to be breaking ground on our newest data center in Kuna, Idaho. Thank you to all of our partners who helped us move this project forward. Kuna is a great place to call home and we are committed to investing in the community's long-term vitality. We look forward to having a strong, fruitful partnership for years to come. Data Center Dynamics (opens in a new tab) trade press

2026 3 events

  1. (the day its own sentence names; filed under Sep 18, 2026)

    Entry

    Meta's data center in Kuna, Idaho held grand opening on September 3, 2026. [6]

  2. (the day its own sentence names; filed under Sep 19, 2026)

    Entry

    Meta's Kuna data center grand opening held September 3, 2026 [4]

  3. (source date; the content gives no date of its own)

    running

    Meta's Kuna data center formally opened on September 4, 2026 [9]

  4. Also in September 2026: 6 statements, 7 figures from other sources and 12 dates when source pages were read and verified
    1. (source date; the content gives no date of its own)

      Entry

      Meta formally turned on Kuna data center with closed loop cooling system [8]

    2. (source date; the content gives no date of its own)

      Entry

      This is Meta's first data center in Idaho [9]

    3. (source date; the content gives no date of its own)

      Entry

      This is Meta's 28th American data center [9]

    4. (source date; the content gives no date of its own)

      Entry

      The largest building on the Kuna campus is 350,000 square feet [9]

    5. (source date; the content gives no date of its own)

      Entry

      Meta paid $100 million to build transmission infrastructure for the data center [9]

    6. (source date; the content gives no date of its own)

      Entry

      Meta backed three solar projects expected to add 645 megawatts to offset the data center's power consumption [9]

    7. (source date; the content gives no date of its own)

      Entry

      The Kuna data center uses a closed loop cooling system that requires about 200,000 gallons of water [9]

    8. (source date; the content gives no date of its own)

      Entry

      The Kuna data center is 750,000 square feet [9]

    9. (source date; the content gives no date of its own)

      Entry

      The Kuna data center cost $1.2 billion [9]

    10. (said in the source itself)

      Statement · Scott Stillings, critical operations manager

      Scott Stillings, critical operations manager, said the same water used to cool the facility today will be used for the next 10 years Coeur d'Alene Press (opens in a new tab) news outlet

    11. (said in the source itself)

      Statement · Brad Davis, Meta Director of Global Economic Development

      Brad Davis, Meta Director of Global Economic Development, said the closed loop cooling system runs without extra cooling water for much of the year and needs refill every 7 to 10 years Coeur d'Alene Press (opens in a new tab) news outlet

    12. (source date; the content gives no date of its own)

      Figure · GovTech

      1,200,000,000 dollars: Meta Kuna facility cost 1.2 billion dollars over four years GovTech (opens in a new tab) national outlet

    13. (source date; the content gives no date of its own)

      Figure · GovTech

      645 MW: Meta backing three solar projects expected to add 645 megawatts to grid to offset data center power consumption GovTech (opens in a new tab) national outlet

    14. (source date; the content gives no date of its own)

      Entry

      Meta Kuna Data Center is online and fully operational [7]

    15. (source date; the content gives no date of its own)

      Figure · latimes.com

      1,200,000,000 dollars: Meta data center in Kuna, Idaho cost 1.2 billion dollars latimes.com (opens in a new tab) local outlet

    16. (source date; the content gives no date of its own)

      Entry

      Meta's data center in Kuna, Idaho held grand opening event with community members, stakeholders, and policy experts [5]

    17. (source date; the content gives no date of its own)

      Entry

      Groundbreaking was in 2022 [4]

    18. (said in the source itself)

      Statement · Meta

      Meta aims to be net water positive by 2030 Idaho Press (opens in a new tab) local outlet

    19. (said in the source itself)

      Statement · Meta

      Closed water loop design uses 87 times less water than original plan Idaho Press (opens in a new tab) local outlet

    20. (said in the source itself)

      Statement · Meta

      Zero operational water use for majority of year with closed loop system Idaho Press (opens in a new tab) local outlet

    21. (source date; the content gives no date of its own)

      Figure · Idaho Press

      200,000 USD: Meta donated $200,000 to Swan Falls High School for robotics and engineering labs Idaho Press (opens in a new tab) local outlet

    22. (source date; the content gives no date of its own)

      Figure · Idaho Press

      100,000,000 USD: Meta built new $100 million water and wastewater infrastructure for Kuna Idaho Press (opens in a new tab) local outlet

    23. (source date; the content gives no date of its own)

      Figure · Idaho Press

      1,500,000 USD: Meta contributed over $1.5 million to Ada County schools and local nonprofits Idaho Press (opens in a new tab) local outlet

    24. (source date; the content gives no date of its own)

      Figure · KBOI

      4,000,000 square feet: Meta Kuna data center is more than four times smaller than proposed Rhea Data Center of 4 million square feet. KBOI (opens in a new tab) local outlet

    25. (said in the source itself)

      Statement · Lisa Grow, Idaho Power President and CEO

      Lisa Grow says the pace and scale of Idaho's growth is unprecedented and Idaho Power must adapt and innovate to keep up with growth statewide and manage resources to keep costs down. Idaho Business Review (opens in a new tab) local outlet

On the timeline: a stage change; an entry that reports an act on the day the source or its own sentence gives; and a decision, a published scorecard event on a row at or under the record's county, that reports an act. Under the months: a statement that names this record, a figure another source gave about it, matched by place and developer, an entry dated only by the day its source was published, and an entry or a decision that describes rather than reports an act. Each is on the record in its own right and keeps its own link.

For researchers
Stage
running
Events on the timeline
4
Under the months
28
Stage changes
1
Decisions
0
Statements
8
Figures
7
Entries and decisions under the months
13