Data Center Record.
Projects / Leola Data Center / Timeline

Leola Data Center, in order

What happened with this project, oldest first: the stages it reached, what the county and its cities decided, and every dated step on the record. Each entry links its source.

2 events, January 1, 2023 to September 2, 2026. Also on the record, under the month each belongs to: 1 statement and 4 lines that are not events of their own. The facts, newest first: the record; the place: South Dakota.

A plain date is the day it happened, as the source states it, or as the line's own sentence states it ("voted on July 6"), which is where the line sits even when it was filed later. "Reported" and a date is the day a source published a line that carries no date of its own. Those lines, and lines that describe rather than report an act, sit under their month rather than on the timeline, with what was said and the figures other sources gave. Every timeline on the site reads its lines by this one rule. How dates are read.

Stages

  1. reported

Now: reported. A stage is the record's status after the entry that set it (the definitions).

2023 1 event

  1. (the year its own sentence names; filed under Sep 2, 2026)

    Entry

    In 2023, South Dakota PUC approved Montana Dakota Utilities request to establish new rate available to data center type facilities housing high density computer processing technology [1]

2026 1 event

  1. Also in August 2026: 1 line that is not an event of its own
    1. (source date; the content gives no date of its own)

      Decision · McPherson County (county)

      McPherson County Planning and Zoning Commission voted to postpone a decision following an executive session at a special meeting dakotanewsnow.com

  2. (source date; the content gives no date of its own)

    reported

    Leola Data Center is a 50 megawatt facility proposed in a one story building 120 feet wide by 400 feet long at 116th Street and 358th Avenue, about four miles west of Leola [1]

  3. Also in September 2026: 1 statement and 3 lines that are not events of their own
    1. (source date; the content gives no date of its own)

      Entry

      Montana Dakota Utilities would provide electricity to Leola Data Center in second half of 2027 [1]

    2. (source date; the content gives no date of its own)

      Entry

      Construction could start this fall after conditional use permit received [1]

    3. (source date; the content gives no date of its own)

      Decision · McPherson County (county)

      McPherson County Commission, acting as county Board of Adjustment, will decide on conditional use permit for Leola Data Center yahoo.com

    4. (said in the source itself)

      Statement · Frank Kloucek, Democratic PUC candidate

      Democratic candidates and PUC candidate Frank Kloucek called for one year moratorium on new data centers Yahoo national outlet

On the timeline: a stage change; an entry that reports an act on the day the source or its own sentence gives; and a decision, a published scorecard event on a row at or under the record's county, that reports an act. Under the months: a statement that names this record, a figure another source gave about it, matched by place and developer, an entry dated only by the day its source was published, and an entry or a decision that describes rather than reports an act. Each is on the record in its own right and keeps its own link.

For researchers
Slug
leola-data-center-sd
Status value
rumored
Events on the timeline
2
Under the months
5
Stage changes
1
Decisions
2
Statements
1
Figures
0
Entries and decisions under the months
4