Digital Realty Kokomo Campus, in order

What happened with this project, oldest first: the stages it reached, what the county and its cities decided, and every dated step on the record. Each entry links its source.

7 events, March 9, 2026 to October 5, 2026. Also on the record, under the month each belongs to: 4 statements. The facts, newest first: the record; the place: Indiana.

A plain date is the day it happened, as the source states it, or as the line's own sentence states it ("voted on July 6"), which is where the line sits even when it was filed later. "Reported" and a date is the day a source published a line that carries no date of its own. Those lines, and lines that describe rather than report an act, sit under their month rather than on the timeline, with what was said and the figures other sources gave. Every timeline on the site reads its lines by this one rule. How dates are read.

Stages

  1. proposed
  2. waiting on permits
  3. proposed

Now: proposed. A stage is the record's status after the entry that set it (the definitions).

2026 7 events

  1. (content date)

    proposed

    The Kokomo Common Council voted 8 to 1 (with Councilmember Bob Stephenson dissenting) to annex and rezone roughly 700 acres on the northeast side of Kokomo near U.S. 31 and County Road 400 North for Industrial Park North. [5]

  2. Also in March 2026: 1 statement
    1. (content date; reported from elsewhere)

      Statement · Bob Stephenson, Common Council Member, District 2

      I prefer to see these projects come forward individually for both annexation and rezoning, so they would come before this council one at a time. Once they're out of here, and you guys all know this, they'll never come back before us unless there's an abatement. Kokomo Lantern (opens in a new tab) news outlet

  3. (content date)

    Entry

    The Kokomo Common Council advanced a municipal data center zoning ordinance on first reading by a 6 to 2 vote after declining a proposed moratorium. wishtv.com (opens in a new tab) local outlet

  4. (content date)

    proposed

    Proposed: the city is considering a data center ordinance or code amendment, with no application in a project's name on file yet. [7]

  5. (content date)

    waiting on permits

    Eleven residents spoke against the proposed data center zoning ordinance during public comment before the Kokomo Common Council, citing utility use and quality of life impacts. [7]

  6. (content date)

    Entry

    The Kokomo Common Council data center zoning ordinance (September 14, 2026) adding Section 6.75 DC 01 Data Center Standards passed with one dissenting vote (Councilmember Bob Stephenson); reported as 8 to 1 by the Kokomo Lantern and 7 to 1 by WRTV, setting a 350 foot separation from existing residences, a 200 foot setback from residential districts, a 50 dBA residential property line sound limit and a master site plan requirement. [6]

  7. (content date)

    Entry · Moratorium adopted

    The Howard County Board of Commissioners adopted Ordinance No. 2026 BCCO 33 establishing a one year moratorium on data centers in unincorporated Howard County, while the annexed Industrial Park North site remained under City of Kokomo jurisdiction. [2]

  8. Also in September 2026: 2 statements
    1. (said in the source itself)

      Statement · Tyler Moore, Kokomo Mayor

      No current data center projects in Kokomo WRTV (opens in a new tab) national outlet

    2. (content date; reported from elsewhere)

      Statement · Matt Grecu, Common Council Member

      Whether we argue that the setbacks are far enough, 10 times farther is better than where we are today, and we can always adjust this in the future. Kokomo Lantern (opens in a new tab) news outlet

  9. (content date)

    Entry

    Kokomo Mayor Tyler Moore and Digital Realty confirmed plans for the Digital Realty Kokomo Campus on 476 acres at Industrial Park North near U.S. 31 and County Road 400 North, comprising 3 buildings totaling about 3 million square feet and about 1,000 MW of IT capacity, with closed loop air cooled chillers, no property tax abatement and full completion targeted for 2033. [4]

  10. Also in October 2026: 1 statement
    1. (content date; reported from elsewhere)

      Statement · Tyler Moore, Mayor

      At a time when SEA 1 has put local governments across Indiana under tremendous budget pressure, this investment puts Kokomo in the driver's seat. InkFreeNews (opens in a new tab) news outlet

On the timeline: a stage change; an entry that reports an act on the day the source or its own sentence gives; and a decision, a published scorecard event on a row at or under the record's county, that reports an act. Under the months: a statement that names this record, a figure another source gave about it, matched by place and developer, an entry dated only by the day its source was published, and an entry or a decision that describes rather than reports an act. Each is on the record in its own right and keeps its own link.

For researchers
Stage
proposed
Events on the timeline
7
Under the months
4
Stage changes
3
Decisions
0
Statements
4
Figures
0
Entries and decisions under the months
0

Researcher view · basis and source tier on every row · docket and Census GEOIDs · citation and export tools

Commercial and bulk data