Projects / Hyperscale Data Dowagiac AI Data Center / Timeline

Hyperscale Data Dowagiac AI Data Center, in order

What happened with this project, oldest first: the stages it reached, what the county and its cities decided, and every dated step on the record. Each entry links its source.

4 events, June 2026 to September 3, 2026. Also on the record, under the month each belongs to: 6 statements, 9 figures from other sources and 28 dates when source pages were read and verified. The facts, newest first: the record; the place: Michigan.

A plain date is the day it happened, as the source states it, or as the line's own sentence states it ("voted on July 6"), which is where the line sits even when it was filed later. "Reported" and a date is the day a source published a line that carries no date of its own. Those lines, and lines that describe rather than report an act, sit under their month rather than on the timeline, with what was said and the figures other sources gave. Every timeline on the site reads its lines by this one rule. How dates are read.

Stages

  1. being built
  2. running
  3. being built

Now: being built. A stage is the record's status after the entry that set it (the definitions).

2026 4 events

  1. (the month its own sentence names; no day is given; filed under Sep 3, 2026)

    Entry

    Unnamed California based neocloud customer signed lease agreement with Hyperscale Data in June 2026. [2]

  2. (source date; the content gives no date of its own)

    being built

    De Soto City Council approved Development Agreement with Mount Sunflower, LLC in August 2025 [12]

  3. Also in August 2026: 2 statements
    1. (said in the source itself)

      Statement · Donald Trump, President

      President Donald Trump argued that communities should embrace data centers and warned that widespread opposition could put the United States at a competitive disadvantage with China Michigan House Republicans (opens in a new tab) news outlet

    2. (said in the source itself)

      Statement · Steve Carra, Michigan House of Representatives

      Rep. Steve Carra stated that hyperscale data centers are an existential threat and may cause the extermination of humanity if not carefully managed Michigan House Republicans (opens in a new tab) news outlet

  4. (source date; the content gives no date of its own)

    being built

    Hyperscale Data ceased all Bitcoin mining operations on September 1, 2026, at its Dowagiac, Michigan facility. [2]

  5. (content date)

    running

    Hyperscale Data ceased Bitcoin mining at its 617,000 square foot Dowagiac, Michigan facility on September 1, 2026, and is converting it for a California neocloud customer deploying 20MW in Q4 2026 with potential to scale to 52MW under a 10 year lease. [1]

  6. Also in September 2026: 4 statements, 9 figures from other sources and 28 dates when source pages were read and verified
    1. (source date; the content gives no date of its own)

      Entry

      The master services agreement with a California neocloud provider is for deployment of 20 megawatts with an initial term of 10 years and two five year extension options [13]

    2. (source date; the content gives no date of its own)

      Entry

      Hyperscale Data ceased all Bitcoin mining operations at its Michigan data center effective September 1, 2026 [13]

    3. (said in the source itself)

      Statement · William Horne, Hyperscale Data Chief Executive Officer

      CEO William Horne said the transition to AI data center operations will allow focus on the facility's preparation for customer usage PR Newswire (opens in a new tab) press release

    4. (source date; the content gives no date of its own)

      Entry

      Hyperscale Data is converting the Michigan site into an AI data center [16]

    5. (source date; the content gives no date of its own)

      Entry

      Hyperscale Data ceased bitcoin mining in Michigan [16]

    6. (said in the source itself)

      Statement · William Horne, Hyperscale Data CEO

      William Horne, Hyperscale Data CEO, said the facility is being prepared for AI usage and customer deployment. Data Center Dynamics (opens in a new tab) trade press

    7. (source date; the content gives no date of its own)

      Figure · ForkLog

      20 MW: The contract includes 20 MW of power ForkLog (opens in a new tab) news outlet

    8. (source date; the content gives no date of its own)

      Figure · ForkLog

      1,200,000,000 USD: The agreement could generate over $1.2 billion in revenue over the maximum term ForkLog (opens in a new tab) news outlet

    9. (source date; the content gives no date of its own)

      Figure · Data Center Dynamics

      617,000 square feet: Hyperscale Data facility at 415 East Prairie Ronde Street, Dowagiac spans 617,000 square feet. Data Center Dynamics (opens in a new tab) trade press

    10. (source date; the content gives no date of its own)

      Figure · Data Center Dynamics

      20 MW: Customer will deploy 20MW operational in Q4 of 2026 at Dowagiac facility. Data Center Dynamics (opens in a new tab) trade press

    11. (source date; the content gives no date of its own)

      Figure · Data Center Dynamics

      52 MW: Customer could scale up to 52MW of compute capacity at Dowagiac facility. Data Center Dynamics (opens in a new tab) trade press

    12. (source date; the content gives no date of its own)

      Figure · ForkLog

      3,000,000,000 USD: An additional option for 32 MW could increase the agreement's value to over $3 billion ForkLog (opens in a new tab) news outlet

    13. (source date; the content gives no date of its own)

      Figure · Data Center Dynamics

      30 MW: Facility currently operates with 30MW of capacity and company aims to expand to 340MW including 40MW of behind the meter natural gas capacity. Data Center Dynamics (opens in a new tab) trade press

    14. (source date; the content gives no date of its own)

      Figure · Data Center Dynamics

      1,200,000,000 USD: Lease agreement will run for initial term of ten years with two five year extension options, valued at approximately $1.2 billion. Data Center Dynamics (opens in a new tab) trade press

    15. (source date; the content gives no date of its own)

      Entry

      Alliance Cloud Services executed master services agreement with California based customer for initial 20 MW deployment at Michigan Campus [5]

    16. (source date; the content gives no date of its own)

      Entry

      Hyperscale Data explores sale or IPO of Michigan AI data center campus targeting valuation between $750 million and $1.25 billion [4]

    17. (source date; the content gives no date of its own)

      Entry

      Hyperscale Data is evaluating options including outright sale, continued development or initial public offering of Sentinum subsidiary [6]

    18. (source date; the content gives no date of its own)

      Entry

      Michigan campus could eventually support more than 300 megawatts, depending on financing, regulatory approvals, utility agreements and customer demand [6]

    19. (source date; the content gives no date of its own)

      Entry

      Alliance Cloud Services signed a master services agreement covering initial 20 megawatts of AI computing capacity with 10 year term and two five year extension options [6]

    20. (source date; the content gives no date of its own)

      Entry

      Customer has rights to additional 32 MW of capacity at Michigan campus. [8]

    21. (source date; the content gives no date of its own)

      Entry

      Master services agreement initial 10 year term with two five year extension options. [8]

    22. (source date; the content gives no date of its own)

      Entry

      Alliance Cloud Services master services agreement with neocloud provider for deployment of 20 megawatts of AI compute capacity at Michigan campus. [8]

    23. (source date; the content gives no date of its own)

      Entry

      Management exploring options including selling campus, IPO of Sentinum subsidiary or continued development [7]

    24. (source date; the content gives no date of its own)

      Entry

      New 20 megawatt contract with California cloud provider [7]

    25. (source date; the content gives no date of its own)

      Entry

      Company is evaluating options including sale, continued development or IPO of Sentinum subsidiary [4]

    26. (source date; the content gives no date of its own)

      Entry

      Campus could eventually support more than 300 megawatts [4]

    27. (source date; the content gives no date of its own)

      Entry

      20 megawatt master services agreement with California cloud provider has 10 year term and two five year extension options [4]

    28. (said in the source itself)

      Statement · Hyperscale Data Inc

      Management does not plan to recommend sale below $750 million GuruFocus (opens in a new tab) national outlet

    29. (source date; the content gives no date of its own)

      Entry

      Customer has right to increase critical AI compute capacity up to 52 MW [9]

    30. (source date; the content gives no date of its own)

      Entry

      Initial Master Services Agreement provides for 20 megawatts of critical AI compute capacity with 10 year initial term plus two 5 year extension options [9]

    31. (source date; the content gives no date of its own)

      Entry

      Operations under Master Services Agreement expected to begin in November 2026 [9]

    32. (source date; the content gives no date of its own)

      Entry

      The company is working toward commencing operations under a previously announced master services agreement in November 2026 [14]

    33. (source date; the content gives no date of its own)

      Entry

      The master services agreement provides for an initial 20 megawatts of critical AI compute capacity and has an initial 10 year term with two five year extension options [14]

    34. (source date; the content gives no date of its own)

      Entry

      Hyperscale Data has invested more than $70 million into its Michigan AI data center facility as of September 15, 2026 [14]

    35. (source date; the content gives no date of its own)

      Entry

      Michigan facility targeting November 2026 start for 20 MW contract with Alliance Cloud Services [10]

    36. (source date; the content gives no date of its own)

      Entry

      Company plans to resume operations in Dowagiac in November with new equipment for AI computing [15]

    37. (source date; the content gives no date of its own)

      Entry

      Hyperscale Data Inc. ceased bitcoin mining operation on September 2 to retool facility for artificial intelligence computing [15]

    38. (source date; the content gives no date of its own)

      Figure · The Detroit News

      30 MW: Hyperscale Data facility capacity is 30 megawatts of electricity The Detroit News (opens in a new tab) local outlet

    39. (said in the source itself)

      Statement · Milton Ault III, Executive Chairman of Hyperscale Data

      Milton Ault stated Bitcoin mining and AI data center development have different capital requirements, operating priorities and value drivers Morningstar (opens in a new tab) press release

    40. (source date; the content gives no date of its own)

      Entry

      Hyperscale Data facility will resume operations in November 2026 supporting artificial intelligence computing. [11]

    41. (source date; the content gives no date of its own)

      Entry

      Hyperscale Data Inc. data center in Dowagiac operated as bitcoin mining facility with fan based cooling until early September 2026, causing noise concerns. [11]

On the timeline: a stage change; an entry that reports an act on the day the source or its own sentence gives; and a decision, a published scorecard event on a row at or under the record's county, that reports an act. Under the months: a statement that names this record, a figure another source gave about it, matched by place and developer, an entry dated only by the day its source was published, and an entry or a decision that describes rather than reports an act. Each is on the record in its own right and keeps its own link.

For researchers
Stage
being built
Events on the timeline
4
Under the months
43
Stage changes
3
Decisions
0
Statements
6
Figures
9
Entries and decisions under the months
28