Hyperscale Data Dowagiac AI Data Center, in order
What happened with this project, oldest first: the stages it reached, what the county and its cities decided, and every dated step on the record. Each entry links its source.
3 events, August 2025 to August 10, 2026. Also on the record, under the month each belongs to: 6 statements, 11 figures from other sources and 36 lines that are not events of their own. The facts, newest first: the record; the place: Michigan.
A plain date is the day it happened, as the source states it, or as the line's own sentence states it ("voted on July 6"), which is where the line sits even when it was filed later. "Reported" and a date is the day a source published a line that carries no date of its own. Those lines, and lines that describe rather than report an act, sit under their month rather than on the timeline, with what was said and the figures other sources gave. Every timeline on the site reads its lines by this one rule. How dates are read.
Stages
2025 1 event
-
(the month its own sentence names; no day is given; filed under Aug 10, 2026)
Entry
De Soto City Council approved Development Agreement with Mount Sunflower, LLC in August 2025 [14]
2026 2 events
-
(the month its own sentence names; no day is given; filed under Sep 3, 2026)
Entry
Unnamed California based neocloud customer signed lease agreement with Hyperscale Data in June 2026. [1]
-
(source date; the content gives no date of its own)
being built
Beale Data Center is Kansas's first hyperscale data center campus being built in De Soto [14]
-
Also in August 2026: 2 statements, 2 figures from other sources and 5 lines that are not events of their own
-
(source date; the content gives no date of its own)
Entry
Google looking to potentially build data center development in Barber County near Sharon [14]
-
(source date; the content gives no date of its own)
Entry
Kanza Park Place LLC proposed Flint Hills Digital Campus covering 11 tracts of land in west Emporia [14]
-
(source date; the content gives no date of its own)
Entry
Beale Infrastructure pulled the plug on 300 acre data center project in eastern Gardner after community scrutiny [14]
-
(source date; the content gives no date of its own)
Entry
Project Bluestem proposed data center development from Cloverleaf Infrastructure in Leavenworth County near Tonganoxie Business Park [14]
-
(source date; the content gives no date of its own)
Entry
Digital Realty proposed a multiphase data center campus at Astra Enterprise Park in De Soto [14]
-
(source date; the content gives no date of its own)
Figure · Boothbay Register
7,500 GWH/year: Proposed data center would consume around 60% of Maine's annual electricity, approximately 7,500 GWH per year Boothbay Register local outlet
-
(source date; the content gives no date of its own)
Figure · Boothbay Register
1,700 to 2,300 jobs: Project would bring millions of dollars in taxes, 1,700 to 2,300 temporary construction jobs, and 100 to 200 permanent jobs Boothbay Register local outlet
-
(said in the source itself)
Statement · Donald Trump, President
President Donald Trump argued that communities should embrace data centers and warned that widespread opposition could put the United States at a competitive disadvantage with China Michigan House Republicans local outlet
-
(said in the source itself)
Statement · Steve Carra, Michigan House of Representatives
Rep. Steve Carra stated that hyperscale data centers are an existential threat and may cause the extermination of humanity if not carefully managed Michigan House Republicans local outlet
-
-
Also in September 2026: 4 statements, 9 figures from other sources and 31 lines that are not events of their own
-
(source date; the content gives no date of its own)
Entry
The master services agreement with a California neocloud provider is for deployment of 20 megawatts with an initial term of 10 years and two five year extension options [3]
-
(source date; the content gives no date of its own)
Entry
Hyperscale Data ceased all Bitcoin mining operations at its Michigan data center effective September 1, 2026 [3]
-
(said in the source itself)
Statement · William Horne, Hyperscale Data Chief Executive Officer
CEO William Horne said the transition to AI data center operations will allow focus on the facility's preparation for customer usage PR Newswire local outlet
-
(source date; the content gives no date of its own)
Entry
Hyperscale Data is converting the Michigan site into an AI data center [15]
-
(source date; the content gives no date of its own)
Entry
Hyperscale Data ceased bitcoin mining in Michigan [15]
-
(source date; the content gives no date of its own)
Entry
Hyperscale Data ceased all Bitcoin mining operations on September 1, 2026, at its Dowagiac, Michigan facility. [1]
-
(said in the source itself)
Statement · William Horne, Hyperscale Data CEO
William Horne, Hyperscale Data CEO, said the facility is being prepared for AI usage and customer deployment. Data Center Dynamics trade press
-
(said in the source itself)
Statement · Hyperscale Data
Hyperscale Data will continue cryptocurrency mining at its Montana site ForkLog local outlet
-
(source date; the content gives no date of its own)
Figure · ForkLog
20 MW: The contract includes 20 MW of power ForkLog local outlet
-
(source date; the content gives no date of its own)
Figure · ForkLog
1,200,000,000 USD: The agreement could generate over $1.2 billion in revenue over the maximum term ForkLog local outlet
-
(source date; the content gives no date of its own)
Figure · Data Center Dynamics
617,000 square feet: Hyperscale Data facility at 415 East Prairie Ronde Street, Dowagiac spans 617,000 square feet. Data Center Dynamics trade press
-
(source date; the content gives no date of its own)
Figure · Data Center Dynamics
20 MW: Customer will deploy 20MW operational in Q4 of 2026 at Dowagiac facility. Data Center Dynamics trade press
-
(source date; the content gives no date of its own)
Figure · Data Center Dynamics
52 MW: Customer could scale up to 52MW of compute capacity at Dowagiac facility. Data Center Dynamics trade press
-
(source date; the content gives no date of its own)
Figure · ForkLog
3,000,000,000 USD: An additional option for 32 MW could increase the agreement's value to over $3 billion ForkLog local outlet
-
(source date; the content gives no date of its own)
Figure · Data Center Dynamics
30 MW: Facility currently operates with 30MW of capacity and company aims to expand to 340MW including 40MW of behind the meter natural gas capacity. Data Center Dynamics trade press
-
(source date; the content gives no date of its own)
Figure · Data Center Dynamics
1,200,000,000 USD: Lease agreement will run for initial term of ten years with two five year extension options, valued at approximately $1.2 billion. Data Center Dynamics trade press
-
(source date; the content gives no date of its own)
Entry
Alliance Cloud Services executed master services agreement with California based customer for initial 20 MW deployment at Michigan Campus [5]
-
(source date; the content gives no date of its own)
Entry
Hyperscale Data explores sale or IPO of Michigan AI data center campus targeting valuation between 750 million and 1.25 billion dollars [4]
-
(source date; the content gives no date of its own)
Entry
Hyperscale Data is evaluating options including outright sale, continued development or initial public offering of Sentinum subsidiary [6]
-
(source date; the content gives no date of its own)
Entry
Michigan campus could eventually support more than 300 megawatts, depending on financing, regulatory approvals, utility agreements and customer demand [6]
-
(source date; the content gives no date of its own)
Entry
Alliance Cloud Services signed a master services agreement covering initial 20 megawatts of AI computing capacity with 10 year term and two five year extension options [6]
-
(source date; the content gives no date of its own)
Entry
Customer has rights to additional 32 MW of capacity at Michigan campus. [8]
-
(source date; the content gives no date of its own)
Entry
Master services agreement initial 10 year term with two five year extension options. [8]
-
(source date; the content gives no date of its own)
Entry
Alliance Cloud Services master services agreement with neocloud provider for deployment of 20 megawatts of AI compute capacity at Michigan campus. [8]
-
(source date; the content gives no date of its own)
Entry
Management exploring options including selling campus, IPO of Sentinum subsidiary or continued development [7]
-
(source date; the content gives no date of its own)
Entry
New 20 megawatt contract with California cloud provider [7]
-
(source date; the content gives no date of its own)
Entry
Company is evaluating options including sale, continued development or IPO of Sentinum subsidiary [4]
-
(source date; the content gives no date of its own)
Entry
Campus could eventually support more than 300 megawatts [4]
-
(source date; the content gives no date of its own)
Entry
20 megawatt master services agreement with California cloud provider has 10 year term and two five year extension options [4]
-
(said in the source itself)
Statement · Hyperscale Data Inc
Management does not plan to recommend sale below 750 million dollars GuruFocus local outlet
-
(source date; the content gives no date of its own)
Entry
Customer has right to increase critical AI compute capacity up to 52 MW [10]
-
(source date; the content gives no date of its own)
Entry
Initial Master Services Agreement provides for 20 megawatts of critical AI compute capacity with 10 year initial term plus two 5 year extension options [10]
-
(source date; the content gives no date of its own)
Entry
Operations under Master Services Agreement expected to begin in November 2026 [10]
-
(source date; the content gives no date of its own)
Entry
The company is working toward commencing operations under a previously announced master services agreement in November 2026 [9]
-
(source date; the content gives no date of its own)
Entry
The master services agreement provides for an initial 20 megawatts of critical AI compute capacity and has an initial 10 year term with two five year extension options [9]
-
(source date; the content gives no date of its own)
Entry
Hyperscale Data has invested more than $70 million into its Michigan AI data center facility as of September 15, 2026 [9]
-
(source date; the content gives no date of its own)
Entry
Michigan facility targeting November 2026 start for 20 MW contract with Alliance Cloud Services [11]
-
(source date; the content gives no date of its own)
Entry
Company plans to resume operations in Dowagiac in November with new equipment for AI computing [12]
-
(source date; the content gives no date of its own)
Entry
Hyperscale Data Inc. ceased bitcoin mining operation on September 2 to retool facility for artificial intelligence computing [12]
-
(source date; the content gives no date of its own)
Decision · Dowagiac (city)
Dowagiac city imposed tougher noise ordinance setting new daytime and nighttime decibel limits for industrial facilities detroitnews.com
-
(source date; the content gives no date of its own)
Figure · The Detroit News
30 MW: Hyperscale Data facility capacity is 30 megawatts of electricity The Detroit News local outlet
-
(source date; the content gives no date of its own)
Entry
Hyperscale Data facility will resume operations in November 2026 supporting artificial intelligence computing. [13]
-
(source date; the content gives no date of its own)
Entry
Hyperscale Data Inc. data center in Dowagiac operated as bitcoin mining facility with fan based cooling until early September 2026, causing noise concerns. [13]
-
(source date; the content gives no date of its own)
Decision · Dowagiac (city)
Dowagiac amended its noise pollution ordinance in response to data center noise from Hyperscale Data facility. detroitnews.com
-
On the timeline: a stage change; an entry that reports an act on the day the source or its own sentence gives; and a decision, a published scorecard event on a row at or under the record's county, that reports an act. Under the months: a statement that names this record, a figure another source gave about it, matched by place and developer, an entry dated only by the day its source was published, and an entry or a decision that describes rather than reports an act. Each is on the record in its own right and keeps its own link.
For researchers
- Slug
- hyperscale-data-dowagiac-ai-data-center-mi
- Status value
- under_construction
- Events on the timeline
- 3
- Under the months
- 53
- Stage changes
- 1
- Decisions
- 2
- Statements
- 6
- Figures
- 11
- Entries and decisions under the months
- 36