Google Van Buren Township data center, in order

What happened with this project, oldest first: the stages it reached, what the county and its cities decided, and every dated step on the record. Each entry links its source.

2 events, February 11, 2026 to September 14, 2026. Also on the record, under the month each belongs to: 2 figures from other sources and 1 line that is not an event of its own. The facts, newest first: the record; the place: Michigan.

A plain date is the day it happened, as the source states it, or as the line's own sentence states it ("voted on July 6"), which is where the line sits even when it was filed later. "Reported" and a date is the day a source published a line that carries no date of its own. Those lines, and lines that describe rather than report an act, sit under their month rather than on the timeline, with what was said and the figures other sources gave. Every timeline on the site reads its lines by this one rule. How dates are read.

Stages

  1. being built

Now: being built. A stage is the record's status after the entry that set it (the definitions).

2026 2 events

  1. (content date)

    Decision · Van Buren Township (city)

    Van Buren Township Planning Commission approved preliminary site plan for Project Cannoli Data Center on Wednesday night with conditions wemu.org

  2. (the day the page was read; it gives no date of its own)

    being built

    Google lists Google Van Buren Township data center at Van Buren, Michigan on its own page of data center locations, read September 14, 2026. [1]

  3. Also in September 2026: 2 figures from other sources
    1. (source date; the content gives no date of its own)

      Figure · Planet Detroit

      1,700,000,000 dollars: DTE contracts with Google expected to have 1.7 billion dollars in positive affordability benefits for existing customers Planet Detroit local outlet

    2. (source date; the content gives no date of its own)

      Figure · Planet Detroit

      1 GW: Google data center in Van Buren Township has capacity of 1 gigawatt Planet Detroit local outlet

  4. Also in October 2026: 1 line that is not an event of its own
    1. (planned date, from the content)

      Entry

      The Van Buren Township Planning Commission is expected to review the final site plan at its meeting on October 14 [2]

On the timeline: a stage change; an entry that reports an act on the day the source or its own sentence gives; and a decision, a published scorecard event on a row at or under the record's county, that reports an act. Under the months: a statement that names this record, a figure another source gave about it, matched by place and developer, an entry dated only by the day its source was published, and an entry or a decision that describes rather than reports an act. Each is on the record in its own right and keeps its own link.

For researchers
Slug
google-van-buren-township-data-center-mi
Status value
under_construction
Events on the timeline
2
Under the months
3
Stage changes
1
Decisions
1
Statements
0
Figures
2
Entries and decisions under the months
1