● Running Recorded September 13, 2026 · 5 Buildings

Equinix Secaucus International Business Exchange Campus (NY2, NY4, NY5, NY6, and NY3)

Street address 800 Secaucus Road, 755 Secaucus Road, and 105 Enterprise Avenue South, Secaucus, NJ 07094, Hudson County verified address Exact, at the address [4] Equinix: Equinix NY4

Overview, regulatory gates and specifications

Equinix operates a 5 building financial interconnection and colocation campus in Secaucus, Hudson County, New Jersey (NY2, NY4, NY5, NY6, and NY3), delivering 85 MW of combined critical power capacity. [8] The leak began the evening of Friday, September 11, 2026 [16]

1. Land & Parcel
Parcel located
2. Local Zoning
Zoning approved
3. Tax & EDA Deal
Not yet on file
4. Utility Grid Queue
Energized
5. Air & Water Permits
Not yet on file
What happens next: Facility is operational; air permit compliance, water reporting and utility filings are monitored.
Electricity Demand [4]
85 MW
the developer's figure

Equivalent to ~70,550 U.S. homes (U.S. EIA 830 homes/MW baseline) · 4.1% of Hoover Dam nameplate capacity (2,080 MW).

Grid interconnection and utility service tracked on file.

Cooling & Water
Not disclosed
Daily water volume not stated in public filings

U.S. EPA household water equivalence (300 gal/day per home) requires a disclosed daily or annual water figure.

No local property tax abatement amount disclosed in public filings.

Site & Buildings [4]
5 buildings
operator page

Assessor parcel acreage and building square footage are added when municipal or county filings are published.

Location: 800 Secaucus Road, 755 Secaucus Road, and 105 Enterprise Avenue South, Secaucus, NJ 07094.

Taxes & Permanent Jobs
Not disclosed
Tax and job figures not yet on file

State and local tax abatement agreements and permanent job commitments are recorded when filed.

No local property tax abatement amount disclosed in public filings.

Key specifications on the record

Power capacity
85 MW developer figure Equivalent to the continuous electricity demand of about 70,600 average U.S. homes based on U.S. Energy Information Administration residential consumption data. About 0.8 percent of New York City's summer peak demand in 2024.
[4] equinix.com
Water usage
Not disclosed
Land area
Not disclosed
Buildings
5 buildings operator page
[4] equinix.com
Backup generators
Not disclosed
Capital investment
Not disclosed
Commissioned
Operational since 2001 (25 years)
Who leads it
Equinix as stated by the source
[17] patch.com
Official project website
equinix.com (opens in a new tab) verified October 28, 2026
equinix.com (opens in a new tab)
Archived promotional websites
equinix.com (opens in a new tab) [Wayback snapshot] (opens in a new tab) preserved in Internet Archive
tracked domains
Not disclosed
Who would use it, Jobs once it runs, Tax each year
The math behind the comparison
  1. Equinix Secaucus International Business Exchange Campus (NY2, NY4, NY5, NY6, and NY3), capacity: 85 MW.
  2. New York City (NYISO Zone J) summer peak demand, actual, 2024: 10,245 MW (2024).
  3. 85 ÷ 10,245 = 0.0083 (MW over MW).

Sources:

A comparison is arithmetic on two published rows and is never a new fact (how comparisons are made).

Who is connected to this project

Connected government officials, corporate entities, utilities and local rules on the public record.

David Kraatz

data center opponent and write-in candidate for Secaucus Council Ward 2 · New Jersey

DID Recorded statement at Patch (October 14, 2026)
SAID David Kraatz announced his candidacy for Secaucus town Council Ward 2 as a data center opponent (October 14, 2026) patch.com (opens in a new tab)

Michael Gonnelli

Secaucus Mayor · New Jersey

DID Recorded statement at thelocalgirl.com (September 17, 2026) [15]
SAID Mayor Michael Gonnelli said the leak stemmed from broken valves used in the tank's routine filtration process (September 17, 2026) [15]

New Jersey Department of Environmental Protection

Public Record Speaker

DID Recorded statement at communitynews.org (September 17, 2026) [16]
SAID New Jersey Department of Environmental Protection said no drinking water intakes sit near the spill site and no observed harm to local wildlife (September 17, 2026) [16]

Equinix

Public Record Speaker

DID Recorded statement at communitynews.org (September 17, 2026) [16]
SAID Equinix said two broken valves used in the tank's routine filtration process caused the release (September 17, 2026) [16]

Builder, Shell LLC & Utilities

BUILDER
Operator / Developer: Equinix
UTILITIES
Electric utility: Not disclosed

View all 21 statements on the record in New Jersey →

Citizen privacy standard: Elected officials, corporate applicants and utility executives are named in full. Private residents who speak at public comment are cited as Resident First L. unless they hold public office or speak on behalf of an organization.

Technical specification and permit ledger

Disclosed engineering ceilings, reported actuals and primary regulatory basis for Equinix Secaucus International Business Exchange Campus (NY2, NY4, NY5, NY6, and NY3).

Field / Parameter Disclosed Ceiling Reported Actual Basis & Primary Source
Electrical Capacity (MW) 85 MW 85 MW the developer's figure [4] equinix.com
Site Footprint (Acres)
Data Hall Buildings 5 buildings 5 operator page [4] equinix.com
Cooling & Water System
Backup Diesel / Gas Generators
Tax Abatement & Annual Revenue

Blank cell: not disclosed by any source on file.

Still not public, and where it would show up

The record adds each the day a source gives it. Why these documents.

  • Water use A state water right filing or a water supply agreement.
  • Who would use it A lease announcement or a tenant named in a filing.
  • Jobs and tax An incentive agreement, a county's economic development filing or a fiscal note.

Timeline on the record

Chronological regulatory, corporate and permitting events on the record, newest first.

  1. (source date; the content gives no date of its own)

    Equinix said the facility has operated since 2001

    [16] communitynews.org

  2. (source date; the content gives no date of its own)

    By Monday, about 3,500 gallons of diesel had been recovered from the creek

    [16] communitynews.org

  3. (source date; the content gives no date of its own)

    The leak began the evening of Friday, September 11, 2026

    [16] communitynews.org

  4. (source date; the content gives no date of its own)

    The spill flowed into Anderson Creek, an unnamed tributary of the Hackensack River, but did not reach the river itself

    [16] communitynews.org

  5. (source date; the content gives no date of its own)

    Equinix NY2 facility leaked approximately 5,000 gallons of diesel fuel from a storage tank

    [16] communitynews.org

  6. (source date; the content gives no date of its own)

    Equinix said the facility has operated since 2001 and had never had a problem before

    [15] thelocalgirl.com

  7. (source date; the content gives no date of its own)

    About 3,500 gallons of diesel had been recovered from the creek by Monday

    [15] thelocalgirl.com

  8. (source date; the content gives no date of its own)

    The leak flowed into Anderson Creek, an unnamed tributary of the Hackensack River

    [15] thelocalgirl.com

27 earlier entries
  1. (source date; the content gives no date of its own)

    Equinix data center in Secaucus spilled approximately 5,000 gallons of diesel fuel from a storage tank

    [15] thelocalgirl.com

  2. (source date; the content gives no date of its own)

    An estimated 5,000 gallons of diesel fuel leaked from a storage tank at Equinix Data Center in Secaucus on Friday.

    [21] newser.com

  3. (source date; the content gives no date of its own)

    The Equinix data center in Secaucus has been operational since 2001

    [20] thedailybeast.com, also Gothamist (opens in a new tab) local outlet

  4. (source date; the content gives no date of its own)

    The diesel spill entered wetlands and a creek near the Equinix facility in Secaucus, New Jersey

    [20] thedailybeast.com

  5. (source date; the content gives no date of its own)

    The diesel spill entered Anderson Creek, a tributary of the Hackensack River, but the New Jersey Department of Environmental Protection confirmed no impact to the Hackensack River.

    [18] dailycaller.com

  6. (source date; the content gives no date of its own)

    Equinix data center at Hartz Way in Secaucus spilled approximately 5,500 gallons of diesel fuel into Anderson Creek on September 11, 2026, at approximately 7:30 p.m. The leak resulted from mechanical failure of two valves in a routine fuel filtration process.

    [17] patch.com

  7. (source date; the content gives no date of its own)

    The spill was reported September 12 and originated from a storage tank at the Equinix data center

    [14] thelocalgirl.com

  8. (source date; the content gives no date of its own)

    The spill was caused by a computer glitch in Equinix's software that the company was made aware of Friday night

    [14] thelocalgirl.com

  9. (source date; the content gives no date of its own)

    Equinix data center in Secaucus spilled about 5,500 gallons of diesel fuel into Anderson Creek on September 11

    [14] thelocalgirl.com

  10. (source date; the content gives no date of its own)

    The spill was caused by a computer glitch in an automated fueling system that kept calling for oil

    [13] yahoo.com

  11. (source date; the content gives no date of its own)

    Approximately 5,000 to 5,500 gallons of No. 2 diesel spilled from Equinix NY2 data center in Secaucus into Anderson Creek

    [13] yahoo.com

  12. (source date; the content gives no date of its own)

    Equinix data center has been operating in Secaucus since 2001

    [12] thedigestonline.com

  13. (source date; the content gives no date of its own)

    Equinix hired Clean Harbors to lead remediation of diesel spill

    [12] thedigestonline.com

  14. (source date; the content gives no date of its own)

    Spill was contained before reaching main Hackensack River according to DEP

    [12] thedigestonline.com

  15. (source date; the content gives no date of its own)

    Approximately 5,000 gallons of Diesel No. 2 spilled from Equinix tank into Anderson Creek tributary of Hackensack River

    [12] thedigestonline.com

  16. (source date; the content gives no date of its own)

    Equinix data center in Secaucus detected diesel fuel leak on Friday September 11, 2026 from on site storage tank

    [12] thedigestonline.com

  17. (source date; the content gives no date of its own)

    About 3,500 gallons recovered by September 14

    [9] streamlinefeed.co.ke

  18. (source date; the content gives no date of its own)

    Diesel contaminated Anderson Creek in Meadowlands, stopped short of Hackensack River

    [9] streamlinefeed.co.ke

  19. (source date; the content gives no date of its own)

    More than 5,000 gallons of No. 2 diesel escaped from storage tank at Equinix data center in Secaucus

    [9] streamlinefeed.co.ke

  20. (source date; the content gives no date of its own)

    NJDEP estimated cleanup would continue for several days

    [11] nbcnewyork.com

  21. (source date; the content gives no date of its own)

    Diesel was contained in Anderson Creek and did not reach the Hackensack River

    [11] nbcnewyork.com

  22. (source date; the content gives no date of its own)

    Approximately 3,500 gallons of diesel recovered by cleanup crews as of Monday after incident

    [11] nbcnewyork.com

  23. (source date; the content gives no date of its own)

    More than 5,000 gallons of diesel fuel leaked from Equinix data center storage tank into Anderson Creek tributary

    [11] nbcnewyork.com

  24. (source date; the content gives no date of its own)

    Thousands of gallons of diesel fuel spilled from AI data center in Secaucus

    [8] cbsnews.com

  25. (source date; the content gives no date of its own)

    Diesel fuel spill contained; did not reach Hackensack River, contained in Anderson Creek tributary

    [10] cbsnews.com

  26. (source date; the content gives no date of its own)

    Approximately 5,000 gallons of diesel fuel discharged from Equinix data center storage tank in Secaucus

    [10] cbsnews.com

  27. · running (content date)

    Equinix data center in Secaucus spilled approximately 5000 gallons of diesel fuel into unnamed tributary of Hackensack River

    [19] gothamist.com, also [13] yahoo.com, also Daily Mail (opens in a new tab) news outlet , also [21] newser.com

Every event in order

  • Read on September 14, 2026 (the day the page was read; it gives no date of its own)

    Equinix lists Equinix NY2, Equinix NY3, Equinix NY4, Equinix NY5, Equinix NY6 at Secaucus, New Jersey on its own page of data center locations, read September 14, 2026.

    [2] equinix.com

12 corrections to this record

Every correction, with its reason
  1. · Citation

    Cites the later report of the same claim by the same speaker (said again on September 15, 2026; the record's rules, October 10, 2026).

  2. · Citation

    Cites the later report of the same claim by the same speaker (said again on September 16, 2026; the record's rules, October 10, 2026).

  3. · Citation

    Cites the later report of the same claim by the same speaker (said again on September 15, 2026; the record's rules, October 10, 2026).

  4. · Citation

    Cites the later report of the same claim by the same speaker (said again on September 15, 2026; the record's rules, October 10, 2026).

Every correction on the record is on the corrections page.

Nearest data centers in New Jersey

Verified data center records in New Jersey within 60 miles by straight line distance.

Facility & Location Distance Stage Operator / Tenant Disclosed Scale
Evocative Secaucus Data Center (EWR1) Secaucus, Hudson County Less than 1 mi Running Evocative 8 MW
Centersquare Secaucus Data Center (EWR5) Secaucus, Hudson County Less than 1 mi Running Centersquare 12 MW
CoreSite Secaucus Data Center (NY2) Secaucus, Hudson County Less than 1 mi Running CoreSite 24 MW
H5 Data Centers Secaucus (NJ01) Secaucus, Hudson County Less than 1 mi Running H5 Data Centers 6 MW
Equinix NY7 North Bergen Data Center North Bergen, Hudson County 2 mi Running Equinix 14 MW
Digital Realty and Centersquare Weehawken Data Center (300 JFK Boulevard East) Weehawken, Hudson County 3 mi Running Digital Realty / Centersquare / Lumen 18 MW

Blank cell: not disclosed by any source on file.

Common questions about Equinix Secaucus International Business Exchange Campus (NY2, NY4, NY5, NY6, and NY3)

Answered directly from the verified filings and local actions on this page.

Who is building Equinix Secaucus International Business Exchange Campus (NY2, NY4, NY5, NY6, and NY3)?

Equinix is the developer, patch.com (opens in a new tab). No construction contractor is named on the record yet.

How much power and water does Equinix Secaucus International Business Exchange Campus (NY2, NY4, NY5, NY6, and NY3) say it needs?

Power: 85 MW (the developer's figure, equinix.com (opens in a new tab)). Water: not disclosed by any source on file.

Where does Equinix Secaucus International Business Exchange Campus (NY2, NY4, NY5, NY6, and NY3) stand today?

It is running, since September 13, 2026. The newest entry, reported September 17, 2026: Equinix said the facility has operated since 2001 [16].

Sources

Primary documents first: filings, minutes, dockets and official pages. Then reporting. The numbers are the ones the entries above cite.

Tracked project domains

Promotional domains, campaign sites, and municipal portals preserved through the Internet Archive.

Primary documents

  1. Equinix: United States and Canada colocation data centers (opens in a new tab), Equinix, September 14, 2026
  2. Equinix: Equinix NY2 (opens in a new tab), Equinix, September 14, 2026
  3. Equinix: Equinix NY3 (opens in a new tab), Equinix, September 14, 2026
  4. Equinix: Equinix NY4 (opens in a new tab), Equinix, September 14, 2026
  5. Equinix: Equinix NY5 (opens in a new tab), Equinix, September 14, 2026
  6. Equinix: Equinix NY6 (opens in a new tab), Equinix, September 14, 2026

Reporting

  1. NY4: Inside Equinix’s Crown Jewel in New Jersey - DataCenterKnowledge (opens in a new tab), DataCenterKnowledge, May 30, 2024, news outlet
  2. Thousands of gallons of diesel leak at AI data center in Secaucus - cbsnews.com (opens in a new tab), cbsnews.com, September 14, 2026, national outlet
  3. Equinix Data Center Diesel Spill Contaminates New Jersey Meadowlands Creek - streamlinefeed.co.ke (opens in a new tab), streamlinefeed.co.ke, September 15, 2026, international outlet
  4. Thousands of gallons of diesel spill from AI data center in Secaucus, N.J. - cbsnews.com (opens in a new tab), cbsnews.com, September 14, 2026, national outlet
  5. NJ data center leak spills 5,000 gallons of diesel fuel into river, officials say - NBC New York (opens in a new tab), NBC New York, September 15, 2026, local outlet
  6. A NJ Data Center Just Spilled 5K Gallons of Diesel Into a Secaucus Creek. Here's What We Know. - New Jersey Digest (opens in a new tab), New Jersey Digest, September 15, 2026, news outlet
  7. Thousands of Gallons of Diesel Spill at an AI Data Center in New Jersey - Gadget Review (opens in a new tab), Gadget Review, September 15, 2026, national outlet
  8. Thousands of Gallons of Diesel Spill Into Secaucus Creek From Data Center - The Local Girl (opens in a new tab), The Local Girl, September 15, 2026, news outlet
  9. AI Data Center Diesel Spill, NJ on Film, Plus More News You Missed in New Jersey - thelocalgirl.com (opens in a new tab), thelocalgirl.com, September 17, 2026, news outlet
  10. Secaucus Data Center Spills Thousands of Gallons of Diesel Into Hackensack River Tributary - communitynews.org (opens in a new tab), communitynews.org, September 17, 2026, local outlet
  11. Equinix Explains Diesel Spill Into Creek From Its Data Center - Patch (opens in a new tab), Patch, September 15, 2026, local outlet
  12. Data center spilled 5,000 gallons of diesel fuel into river tributary - bizpacreview.com (opens in a new tab), bizpacreview.com, September 15, 2026, national outlet
3 more sources
  1. Data center spills 5K gallons of diesel into New Jersey Meadowlands - Gothamist (opens in a new tab), Gothamist, September 14, 2026, local outlet
  2. Data Center Spills Thousands of Gallons of Diesel Into Wetlands in New Jersey - The Daily Beast (opens in a new tab), The Daily Beast, September 15, 2026, national outlet
  3. 5K Gallons of Diesel From Data Center Leaks Into NJ Creek - Newser (opens in a new tab), Newser, September 15, 2026, national outlet

21 sources on file.

Regional grid context

This site is in the RFC East (RFCE) regional power market.

Sources and data

Sources on this page

Every number on this page comes from a named source. Click any source to open the document in a new tab.

Cite this page

Every record on this page carries its sources and the date it was last verified. When you cite it in a story, a study or a public filing, link to this page and give the date you accessed it.

Get this data

Every row on this page is available to download with its source, its basis and the date it was last verified.

Use this data in your work

Free to use and republish with attribution for reporting, research, teaching and public filings under CC BY-NC 4.0. Commercial, enterprise, financial or AI training use needs a commercial license.

About this data

Last verified
Next check Feeds every four hours, pages daily.
Figures Each figure as its source gave it, with its basis; another source's figure never stands in for the record's own, and nothing is estimated.
License Data CC BY-NC 4.0 (opens in a new tab); free for personal, academic, civic and newsroom reporting with attribution. Using this data in a report? Support the record. Commercial use needs a license. Prose stays under copyright.
Cite this page Data Center Record, "Equinix Secaucus International Business Exchange Campus (NY2, NY4, NY5, NY6, and NY3)", https://datacenterrecord.org/projects/equinix-secaucus-nj, last verified October 27, 2026. CSV · JSON
Using this data in a report? Support the record. Commercial use needs a license.
Cite this page

Data Center Record, "Equinix Secaucus International Business Exchange Campus (NY2, NY4, NY5, NY6, and NY3)", https://datacenterrecord.org/projects/equinix-secaucus-nj. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.

The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.

Report a change
For researchers
Stage
Running
Tier
built from one source
Tags
Built from one source
Coordinates
40.7795, -74.0682
How the location is known
Location from the site's street address.
Location source
https://www.equinix.com/data-centers/americas-colocation/united-states-colocation/new-york-data-centers/ny4
Coordinate source
Hudson County MOD-IV / Equinix NY2, NY4, NY5, NY6 campus specifications
Location last verified
September 14, 2026
How capacity was disclosed
the developer's figure
Capacity, if disclosed
85 MW, the developer's figure
Published
September 14, 2026
Last verified
October 27, 2026
Not disclosed
Location source number, EPA registry id, Uses, Tenancy, Cooling, How water was disclosed, How acreage was disclosed, Interconnection, Rating of the county's rows

Researcher view · Equinix Secaucus International Business Exchange Campus (NY2, NY4, NY5, NY6, and NY3) · 21 sources, 36 entries · basis and source tier on every row · verified October 27, 2026