Data Center Record.
Census GEOID: 08031 Location Precision: verified address Jump to Entity & Permit Table Commercial & Bulk Data (CC BY-NC 4.0)

Last verified: · 1 reporting source

● Running First recorded October 21, 2026 · 1 Building

CoreSite Denver Carrier Hotel Data Center (DE1)

Street address 910 15th Street, Denver, CO 80202, Denver County verified address Exact, at the address [1] coresite.com

Overview, regulatory gates and specifications

CoreSite operates its DE1 carrier hotel and Rocky Mountain interconnection hub at 910 15th Street in downtown Denver, Denver County, Colorado. [1] Filings on the record specify disclosed capacity of 8 MW (the developer's figure), 1 planned or operational building. [1] Verified facility status from Colorado state agency permits, utility dockets, municipal planning filings, or operator campus specifications. [1]

1. Land & Parcel
Parcel located
2. Local Zoning
Zoning approved
3. Tax & EDA Deal
Not yet on file
4. Utility Grid Queue
Energized
5. Air & Water Permits
Not yet on file
What happens next: Facility is operational; air permit compliance, water reporting and utility filings are monitored.
Electricity Demand [1]
8 MW
the developer's figure

Equivalent to ~6,640 U.S. homes (U.S. EIA 830 homes/MW baseline) · 0.4% of Hoover Dam nameplate capacity (2,080 MW).

Grid interconnection and utility service tracked on file.

Cooling & Water
Not disclosed
Daily water volume not stated in public filings

U.S. EPA household water equivalence (300 gal/day per home) requires a disclosed daily or annual water figure.

No local property tax abatement amount disclosed in public filings.

Site & Buildings [1]
1 building
operator page

Assessor parcel acreage and building square footage are added when municipal or county filings are published.

Location: 910 15th Street, Denver, CO 80202.

Taxes & Permanent Jobs
Not disclosed
Tax and job figures not yet on file

State and local tax abatement agreements and permanent job commitments are recorded when filed.

No local property tax abatement amount disclosed in public filings.

Key specifications on the record

Power capacity
8 MW developer figure Equivalent to the continuous electricity demand of about 6,640 average U.S. homes based on U.S. Energy Information Administration residential consumption data. Less than 0.1 percent (0.078 percent) of New York City's summer peak demand in 2024.
[1] coresite.com
Water usage
Not disclosed
Land area
Not disclosed
Buildings
1 building operator page
[1] coresite.com
Backup generators
Not disclosed
Capital investment
Not disclosed
Commissioned
Operational since 2014 (12 years)
Who leads it
CoreSite as stated by the source
Not disclosed
Who would use it, Jobs once it runs, Tax each year
The math behind the comparison
  1. CoreSite Denver Carrier Hotel Data Center (DE1), capacity: 8 MW.
  2. New York City (NYISO Zone J) summer peak demand, actual, 2024: 10,245 MW (2024).
  3. 8 ÷ 10,245 = 0.00078 (MW over MW).

Sources:

A comparison is arithmetic on two published rows and is never a new fact (how comparisons are made).

Who is connected to this project

Connected government officials, corporate entities, utilities and local rules on the public record.

Builder, Shell LLC & Utilities

BUILDER
Operator / Developer: CoreSite
UTILITIES
Electric utility: Not disclosed

Citizen privacy standard: Elected officials, corporate applicants and utility executives are named in full. Private residents who speak at public comment are cited as Resident First L. unless they hold public office or speak on behalf of an organization.

Technical specification and permit ledger

Disclosed engineering ceilings, reported actuals and primary regulatory basis for CoreSite Denver Carrier Hotel Data Center (DE1).

Field / Parameter Disclosed Ceiling Reported Actual Basis & Primary Source
Electrical Capacity (MW) 8 MW 8 MW the developer's figure [1] coresite.com
Site Footprint (Acres)
Data Hall Buildings 1 building 1 operator page [1] coresite.com
Cooling & Water System
Backup Diesel / Gas Generators
Tax Abatement & Annual Revenue

Blank cell: not disclosed by any source on file.

Still not public, and where it would show up

The record adds each the day a source gives it. Why these documents.

  • Water use A state water right filing or a water supply agreement.
  • Who would use it A lease announcement or a tenant named in a filing.
  • Jobs and tax An incentive agreement, a county's economic development filing or a fiscal note.

Hearings and statements on the record

May 18, 2026 Denver, CO Denver City Council Unanimous One Year Data Center Moratorium Vote Denver City Council 3 clips

On May 18, 2026, the Denver City Council voted unanimously to enact a one year moratorium pausing new data center construction permits across the city so Denver Water, Xcel Energy, and city planners can establish binding water and clean energy guardrails.

  1. CBS Colorado Broadcast Report Broadcast Report transcribed from local broadcast report
    "Data centers. Chierstin the city council came together on this decision. And the vote from city council was unanimous. After hours of community testimony. There are already around 50 data centers in the city of Denver, and for many who spoke tonight, a pause isn't enough. They want to see an outright ban on the future construction. It's considered one of the most"
  2. CBS Colorado Broadcast Report Broadcast Report transcribed from local broadcast report
    "Had inhalers. According to a 2025 community health study, the globeville and elyria swansea neighborhoods have a 24% higher death rate than the Denver average. The purina factory, the suncor refinery and these have emitted many contaminants that are creating a lot of illnesses, including cancer. Now, Denver's largest data"
  3. CBS Colorado Broadcast Report Broadcast Report transcribed from local broadcast report
    "Steps away, the neighborhood's only park and community rec center. The views from above show smokestacks in either direction. We have a lot of companies in just district nine. To me, it feels like out of sight, out of mind for the city of Denver, and they for years have ignored us. And now these communities are front and center in the fight against new construction."

Timeline on the record

Chronological regulatory, corporate and permitting events on the record, newest first.

No dated entry is on the record yet.

Every event in order

  • Read on October 27, 2026 (the day the page was read; it gives no date of its own)

    Verified facility status from Colorado state agency permits, utility dockets, municipal planning filings, or operator campus specifications.

    [1] coresite.com

Nearest data centers in Colorado

Verified data center records in Colorado within 60 miles by straight line distance.

Facility & Location Distance Stage Operator / Tenant Disclosed Scale
CoreSite DE2 and Lumen Denver Interconnect Campus Denver, Denver County Less than 1 mi Running CoreSite / Lumen Technologies 10 MW
Iron Mountain Denver Data Center (DEN-1 / Fortrust) Denver, Denver County 3 mi Running Iron Mountain Data Centers 15 MW
CoreSite North Denver Data Center (DE3) Denver, Denver County 3 mi Being built CoreSite 18 MW
ColoradoColo Lakewood Data Center (LKWD) Lakewood, Jefferson County 7 mi Running ColoradoColo 4 MW
Flexential Aurora Data Center (DEN03) Aurora, Arapahoe County 10 mi Running Flexential 10 MW
H5 Data Centers Denver Tech Center Campus Denver, Denver County 10 mi Running H5 Data Centers 20 MW

Blank cell: not disclosed by any source on file.

Common questions about CoreSite Denver Carrier Hotel Data Center (DE1)

Answered directly from the verified filings and local actions on this page.

Who is building CoreSite Denver Carrier Hotel Data Center (DE1)?

CoreSite is the developer. No construction contractor is named on the record yet.

How much power and water does CoreSite Denver Carrier Hotel Data Center (DE1) say it needs?

Power: 8 MW (the developer's figure, coresite.com (opens in a new tab)). Water: not disclosed by any source on file.

Where does CoreSite Denver Carrier Hotel Data Center (DE1) stand today?

It is running; the date it reached that stage is not sourced, only the day a page was read. No dated entry is on the record yet.

Sources

Primary documents first: filings, minutes, dockets and official pages. Then reporting. The numbers are the ones the entries above cite.

Reporting

  1. CoreSite Denver Carrier Hotel Data Center (DE1) Official Disclosure (opens in a new tab), CoreSite, news outlet

1 source on file.

Regional grid context

This site is in the WECC Rockies (RMPA) regional power market.

Sources and data

Cite this page

Every record on this page carries its sources and the date it was last verified. When you cite it in a story, a study or a public filing, link to this page and give the date you accessed it.

Get this data

Every row on this page is available to download with its source, its basis and the date it was last verified.

Use this data in your work

Free to use and republish with attribution for reporting, research, teaching and public filings under CC BY-NC 4.0. Commercial, enterprise, financial or AI training use needs a commercial license.

About this data

Last verified
Next check Feeds every four hours, pages daily.
Figures Each figure as its source gave it, with its basis; another source's figure never stands in for the record's own, and nothing is estimated.
License Data CC BY-NC 4.0 (opens in a new tab); free for personal, academic, civic and newsroom reporting with attribution. Using this data in a report? Support the record. Commercial use needs a license. Prose stays under copyright.
Cite this page Data Center Record, "CoreSite Denver Carrier Hotel Data Center (DE1)", https://datacenterrecord.org/projects/coresite-denver-de1-co, last verified October 27, 2026. CSV · JSON
Using this data in a report? Support the record. Commercial use needs a license.
Cite this page

Data Center Record, "CoreSite Denver Carrier Hotel Data Center (DE1)", https://datacenterrecord.org/projects/coresite-denver-de1-co. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.

The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.

Report a change
For researchers
Stage
Running
Tier
built from one source
Tags
Built from one source
Coordinates
39.745636, -104.995636
How the location is known
Location from the site's street address.
Location source
https://www.coresite.com/data-centers/denver-data-centers/de1
Coordinate source
Denver County Assessor / CoreSite
How capacity was disclosed
the developer's figure
Capacity, if disclosed
8 MW, the developer's figure
Published
October 21, 2026
Last verified
October 27, 2026
Not disclosed
Location source number, Location last verified, EPA registry id, Uses, Tenancy, Cooling, How water was disclosed, How acreage was disclosed, Interconnection, Rating of the county's rows

Researcher view · CoreSite Denver Carrier Hotel Data Center (DE1) · 1 source, 1 entry · basis and source tier on every row · verified October 27, 2026

Download CSV JSON