Google, through Jupiter Star Holdings LLC, is building its first Wyoming data center campus on a 716 acre site in Switchgrass Industrial Park south of Cheyenne in Laramie County, part of a $17 billion investment announced November 5, 2026 with partners Tallgrass Energy, Black Hills Energy, American Electric Power and Related Digital, using Bloom Energy as fuel cell supplier. The campus was first developed by Crusoe with Tallgrass as Project Jade before Google took it over through Jupiter Star Holdings LLC in 2026. Campus load is not disclosed. [14] Google announced its first Wyoming data center campus, part of a $17 billion long term investment in Laramie County with partners Tallgrass Energy, Black Hills Energy, American Electric Power and Related Digital, contracted with AEP for a 702 MW fuel cell development with carbon capture and storage using Bloom Energy solid oxide fuel cells. [3]
U.S. EIA residential equivalence (~830 homes per MW) will compute automatically once a permit or filing states facility megawatts.
Electric utility territory: Contracted generation: 702 MW AEP fuel cell plant (Cheyenne Fuel Cell, LLC, using Bloom Energy fuel cells with carbon capture and storage). Utility planning figure: 2.7 GW resource portfolio (Black Hills Energy, including up to 590 MW of grid connected service, 564 MW of natural gas generation at Cheyenne Prairie Generating Station and about 2.1 GW of third party contracted resources through a private microgrid).
U.S. EPA household water equivalence (300 gal/day per home) requires a disclosed daily or annual water figure.
No local property tax abatement amount disclosed in public filings.
4 planned data hall buildings totaling 3,080,000 square feet (revised from 5 buildings and 4,025,500 square feet under Laramie County case PZ-26-00058).
Location: 2500 Commerce Cir, High Plains Business Park, Cheyenne, WY 82007.
State and local tax abatement agreements and permanent job commitments are recorded when filed.
No local property tax abatement amount disclosed in public filings.
Connected government officials, corporate entities, utilities and local rules on the public record.
Together, these efforts represent a novel approach to powering data centers efficiently, accelerating the commercialization of CCS, and creating pathways to reduce the carbon emissions associated with natural gas generation(November 6, 2026) [11]
Citizen privacy standard: Elected officials, corporate applicants and utility executives are named in full. Private residents who speak at public comment are cited as Resident First L. unless they hold public office or speak on behalf of an organization.
Disclosed engineering ceilings, reported actuals and primary regulatory basis for Google Cheyenne Data Center Campus (Project Tembo, formerly Project Jade).
| Field / Parameter | Disclosed Ceiling | Reported Actual | Basis & Primary Source |
|---|---|---|---|
| Electrical Capacity (MW) | |||
| Site Footprint (Acres) | 716 acres | 716 acres | the developer's figure [11] datacenterdynamics.com |
| Data Hall Buildings | 4 buildings (3,080,000 sq ft) | Revised from 5 buildings (4,025,500 sq ft) | Laramie County case PZ-26-00058 (Project Tembo site plan amendment, processed administratively; certificate of review issued October 23, 2026, valid through April 23, 2028) and PZ-26-00057 (Conditional Use Permit B at 260 US 85 south of Cheyenne; Planning Commission public hearing August 13, 2026; approved by administrative approval September 30, 2026) [7] laramiecountywy.gov |
| Cooling & Water System | |||
| Backup Diesel / Gas Generators | |||
| Tax Abatement & Annual Revenue |
Blank cell: not disclosed by any source on file.
The record adds each the day a source gives it. Why these documents.
Wyoming Tribune Eagle Newsroom report on Cheyenne City Council and community proceedings in Cheyenne, WY: Cheyenne official, resident discuss pros and cons of recent data center boom (May 1, 2026).
"capital city as a premier destination for data centers, residents are beginning to fight back citing concerns with water usage, property values, electricity rates and much more. But those in the community who advocate for data center development are pushing back on those opinions. This week I spoke with Cheyenne LEADS CEO Betsey Hale as well as Cheyenne resident XC Brown. As head of Cheyenne's leading economic development organization, Hale is one of many residents who says she thinks data centers have more of a"
"So first Betsey, I just wanted to ask you how many data centers do we have in Cheyenne currently and how many are proposed or under construction? So it's important to differentiate what a data center is versus a data hall versus a data center campus. So right now we have 12 operating data centers and that's not just Microsoft, that's companies like EchoStar and Lunavi which was formerly"
"when we talk about how many data centers are operating because a lot of people seem to think that they're all Microsoft or Meta. The Meta campus isn't actually operational yet but it should be later this year and we have five under construction. So also want to point out that a data hall, so let's say your listeners go over to Christensen Road and they go across the overpass over the railroad tracks and off to the left they"
Using this data in a report? Support the record.
Your Wyoming Link report on Laramie County Board of Commissioners and community proceedings in Cheyenne, WY: 800 Unit "Man Camp" proposed outside Cheyenne data center corridor (April 15, 2026).
"to where the majority of these projects are so that we aren't impacting the roadways, but more so that we're not pricing local people that have been here. But that surge is raising concerns. He warns it could overwhelm things like housing, rental availability, and hotel capability. The workers are coming, so they will be here. But what we don't want that want to happen is these workers who are"
"checkpoints. There would also be on site enforced rules like the ban of alcohol on property. It's meant to be for a worker to go in, lay their head down, it has a bathroom, it has a microwave, and then get up and go back to work. It will first go before the Laramie County Planning Commission. A public hearing is set for May 14th with a final decision by county commissioners expected June 2nd. Iron Guard Housing was not available for comment today, but"
Using this data in a report? Support the record.
Chronological regulatory, corporate and permitting events on the record, newest first.
(content date)
Google announced its first Wyoming data center campus, part of a $17 billion long term investment in Laramie County with partners Tallgrass Energy, Black Hills Energy, American Electric Power and Related Digital, contracted with AEP for a 702 MW fuel cell development with carbon capture and storage using Bloom Energy solid oxide fuel cells.
(content date)
Laramie County issued a certificate of review for the Project Tembo site plan amendment (case PZ-26-00058), valid through April 23, 2028.
(content date)
American Electric Power announced an investment of about $4 billion for a 702 MW fuel cell generation project near Cheyenne under a 20 year power purchase agreement with Google through Cheyenne Fuel Cell, LLC (about 92 percent owned by AEP and nearly 8 percent by funds advised by Basalt Infrastructure Partners, LLP), targeting full operation by the end of 2028, following Black Hills Corp. definitive agreements to serve the development under a 2.7 GW resource portfolio.
(content date)
Laramie County approved Conditional Use Permit B for Project Tembo (case PZ-26-00057) at 260 US 85 south of Cheyenne by administrative approval.
(content date)
Laramie County Planning Commission public hearing on Class B conditional use permit PZ-26-00057 for the Project Tembo office complex east of Switchgrass Industrial Park on US 85 (while site plan revision PZ-26-00058 is processed administratively).
· Status: being built Filing (content date)
Laramie County told residents that Google, through Jupiter Star Holdings LLC, resubmitted the former Project Jade as Project Tembo after Crusoe withdrew, cutting the plan from five buildings to four and from 4,025,500 to 3,080,000 square feet.
[7] laramiecountywy.gov, also [8] cowboystatedaily.com, also [13] datacenterdynamics.com
· Status: permitting Filing (content date)
Site plan amendment submitted to Laramie County Planning and Development (confirmed through Cowboy State Daily pending the county application file).
[8] cowboystatedaily.com, also [1] co-laramie-wy.smartgovcommunity.com, also [2] co-laramie-wy.smartgovcommunity.com
· Status: stalled or cancelled (content date)
Crusoe paused development of Project Jade at the request of its customer.
(content date)
Laramie County commissioners held the public hearing on the Project Jade site plan and the BFC Power and Cheyenne Power Hub site plan.
· proposed (content date, the month only; the source names no day)
Crusoe and Tallgrass announced Project Jade in July 2025 as a 1.8 GW data center campus near Cheyenne.
Moved primary Project Tembo resubmission summary to the July 8, 2026 Laramie County memo entry and kept June 30, 2026 as the site plan amendment submission date.
Expanded July 8, 2026 Laramie County memo timeline entry with building count and square footage revision details from the county memo.
· Building count (2 buildings to 4 buildings)
November 9, 2026: Updated building count from 2 buildings to 4 buildings (3,080,000 square feet, revised from 5 buildings and 4,025,500 square feet) per Laramie County's July 8, 2026 memo on site plan revision PZ-26-00058.
November 9, 2026: Updated project title from Project Tembo / Bloom Energy to Project Tembo, formerly Project Jade because Bloom Energy is the fuel cell supplier to AEP rather than the campus developer.
November 9, 2026: Crusoe Project Jade record merged into this record after Laramie County's July 8, 2026 memo confirmed the same project under Google (Jupiter Star Holdings LLC).
· Contractor (Bloom Energy to Not disclosed)
Bloom Energy is the solid oxide fuel cell supplier for the 702 MW AEP fuel cell project (Cheyenne Fuel Cell, LLC), not the general construction contractor.
· Power capacity (702 MW to Not disclosed by developer)
702 MW is the capacity of American Electric Power's contracted fuel cell plant (Cheyenne Fuel Cell, LLC) that will supply the campus, not the campus electrical load; Google has not disclosed campus load.
The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.
The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.
The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.
Every correction on the record is on the corrections page.
Verified data center records in Wyoming within 60 miles by straight line distance.
| Facility & Location | Distance | Stage | Operator / Tenant | Disclosed Scale |
|---|---|---|---|---|
| SkyBox Data Center at Cox Ranch Cheyenne, Laramie County | ~5 mi | Proposed | SkyBox | |
| Laramie County Data Center (Bit-O-Wyo rezoning) Laramie County | ~5 mi | Proposed | ||
| Vantage Data Center south of Cheyenne Cheyenne, Laramie County | ~5 mi | Proposed | Vantage | |
| Meta Data Center Cheyenne Cheyenne, Laramie County | 5 mi | Running | Meta | 2 buildings |
| Microsoft Cheyenne Data Center Annexation Cheyenne, Laramie County | 5 mi | Running | Microsoft | 3 buildings |
Blank cell: not disclosed by any source on file.
American Electric Power (PR Newswire) and 2025 Annual Report, Oct 14, 2026
Answered directly from the verified filings and local actions on this page.
Google is the developer, blog.google (opens in a new tab). No construction contractor is named on the record yet.
Not disclosed. No source on file names a tenant, says whether the site is single or multi tenant, or states what it is for. The record keeps the use as not disclosed until one does; see Who it serves.
Power: not disclosed by any source on file. Water: not disclosed by any source on file.
It is being built, since July 8, 2026. The newest entry, November 5, 2026: Google announced its first Wyoming data center campus, part of a $17 billion long term investment in Laramie County with partners Tallgrass Energy, Black Hills Energy, American Electric Power and Related Digital, contracted with AEP for a 702 MW fuel cell development with carbon capture and storage using Bloom Energy solid oxide fuel cells. [3]
Not disclosed by any source on file: how much power it needs, how much water it would use, how loud it would be, jobs once it runs, tax it would pay each year, who is constructing it, grid connection, how it is cooled. No missing primary document is listed for this record yet; What the record lacks is where one appears when a person names it.
19 sources on file.
This site is in the WECC Rockies (RMPA) regional power market.
Every number on this page comes from a named source. Click any source to open the document in a new tab.
If a link has moved or a document has changed, let us know and we will update the record and log the change.
Every record on this page carries its sources and the date it was last verified. When you cite it in a story, a study or a public filing, link to this page and give the date you accessed it.
Data Center Record. Google Cheyenne Data Center Campus (Project Tembo, formerly Project Jade). Last verified November 10, 2026. https://datacenterrecord.org/projects/cheyenne-1-2-billion-data-center-campus-wy. Accessed November 22, 2026.
Every row on this page is available to download with its source, its basis and the date it was last verified.
Download this page's records (CSV) JSON
Licensed CC BY-NC 4.0. Say where it came from and do not sell it or use it to train a commercial model without a license.
Free to use and republish with attribution for reporting, research, teaching and public filings under CC BY-NC 4.0. Commercial, enterprise, financial or AI training use needs a commercial license.
Data Center Record takes no money from data center developers, operators, utilities or trade groups. That rule does not change for licensing.
Data Center Record is an independent project and takes no money from data center developers, operators, utilities or trade groups. Reader support keeps the record free to read, with no ads and no paywall.
Last verified , first recorded . Every correction is logged on the corrections page and under What happened. Report a correction · Send a tip about Google Cheyenne Data Center Campus (Project Tembo, formerly Project Jade)
Data Center Record, "Google Cheyenne Data Center Campus (Project Tembo, formerly Project Jade)", https://datacenterrecord.org/projects/cheyenne-1-2-billion-data-center-campus-wy. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.
The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.