Google Cheyenne Data Center Campus (Project Tembo, formerly Project Jade), in order
What happened with this project, oldest first: the stages it reached, what the county and its cities decided, and every dated step on the record. Each entry links its source.
9 events, July 2025 to November 5, 2026. Also on the record, under the month each belongs to: 1 statement, 3 figures from other sources and 1 date when a source page was read and verified. The facts, newest first: the record; the place: Wyoming.
A plain date is the day it happened, as the source states it, or as the line's own sentence states it ("voted on July 6"), which is where the line sits even when it was filed later. "Reported" and a date is the day a source published a line that carries no date of its own. Those lines, and lines that describe rather than report an act, sit under their month rather than on the timeline, with what was said and the figures other sources gave. Every timeline on the site reads its lines by this one rule. How dates are read.
2025 1 event
-
(content date, the month only; the source names no day)
proposed
Crusoe and Tallgrass announced Project Jade in July 2025 as a 1.8 GW data center campus near Cheyenne. [12]
2026 8 events
-
(content date)
Entry
Laramie County commissioners held the public hearing on the Project Jade site plan and the BFC Power and Cheyenne Power Hub site plan. [10]
-
(content date)
stalled
Crusoe paused development of Project Jade at the request of its customer. [14]
-
(content date)
waiting on permits
Site plan amendment submitted to Laramie County Planning and Development (confirmed through Cowboy State Daily pending the county application file). [8]
-
(content date)
being built
Laramie County told residents that Google, through Jupiter Star Holdings LLC, resubmitted the former Project Jade as Project Tembo after Crusoe withdrew, cutting the plan from five buildings to four and from 4,025,500 to 3,080,000 square feet. [7]
-
Also in August 2026: 1 date when a source page was read and verified
-
(content date)
Entry
Laramie County Planning Commission public hearing on Class B conditional use permit PZ-26-00057 for the Project Tembo office complex east of Switchgrass Industrial Park on US 85 (while site plan revision PZ-26-00058 is processed administratively). [7]
-
-
(content date)
Entry
Laramie County approved Conditional Use Permit B for Project Tembo (case PZ-26-00057) at 260 US 85 south of Cheyenne by administrative approval. [1]
-
(content date)
Entry
American Electric Power announced an investment of about $4 billion for a 702 MW fuel cell generation project near Cheyenne under a 20 year power purchase agreement with Google through Cheyenne Fuel Cell, LLC (about 92 percent owned by AEP and nearly 8 percent by funds advised by Basalt Infrastructure Partners, LLP), targeting full operation by the end of 2028, following Black Hills Corp. definitive agreements to serve the development under a 2.7 GW resource portfolio. [4]
-
(content date)
Entry
Laramie County issued a certificate of review for the Project Tembo site plan amendment (case PZ-26-00058), valid through April 23, 2028. [2]
-
Also in October 2026: 2 figures from other sources
-
(planned date, from the content)
Figure · Black Hills Corp.
2.7 GW: Planned 2.7 GW utility resource portfolio to serve the Google Cheyenne development, including up to 590 MW of grid connected service, about $1.8 billion in company owned capital investment for 564 MW of natural gas generation at the Cheyenne Prairie Generating Station and about 2.1 GW of third party contracted resources delivered through a private microgrid (generating capacity) Black Hills Corp. (opens in a new tab) primary source
-
(planned date, from the content)
Figure · American Electric Power (PR Newswire) and 2025 Annual Report
702 MW: Contracted 702 MW solid oxide fuel cell generation project with carbon capture and storage near Cheyenne under a 20 year power purchase agreement with Google (about $4 billion total investment; $2.65 billion January 2026 solid oxide fuel cell purchase agreement; about 92 percent owned by AEP and nearly 8 percent by funds advised by Basalt Infrastructure Partners, LLP) (generating capacity) American Electric Power (PR Newswire) and 2025 Annual Report (opens in a new tab) primary source
-
-
(content date)
Entry
Google announced its first Wyoming data center campus, part of a $17 billion long term investment in Laramie County with partners Tallgrass Energy, Black Hills Energy, American Electric Power and Related Digital, contracted with AEP for a 702 MW fuel cell development with carbon capture and storage using Bloom Energy solid oxide fuel cells. [3]
-
Also in November 2026: 1 statement and 1 figure from another source
-
(planned date, from the content)
Figure · Google
17,000,000,000 USD: Announced $17 billion long term investment in Laramie County, Wyoming, including Google first Wyoming data center campus near Cheyenne Google (opens in a new tab) primary source
-
(content date; reported from elsewhere)
Statement · Steve Walter, VP, Global Infrastructure and Energy
Together, these efforts represent a novel approach to powering data centers efficiently, accelerating the commercialization of CCS, and creating pathways to reduce the carbon emissions associated with natural gas generation
Data Center Dynamics (opens in a new tab) trade press
-
On the timeline: a stage change; an entry that reports an act on the day the source or its own sentence gives; and a decision, a published scorecard event on a row at or under the record's county, that reports an act. Under the months: a statement that names this record, a figure another source gave about it, matched by place and developer, an entry dated only by the day its source was published, and an entry or a decision that describes rather than reports an act. Each is on the record in its own right and keeps its own link.
For researchers
- Stage
- being built
- Events on the timeline
- 9
- Under the months
- 5
- Stage changes
- 4
- Decisions
- 0
- Statements
- 1
- Figures
- 3
- Entries and decisions under the months
- 1