Data Center Record.
Census GEOID: 06099 Location Precision: verified address Jump to Entity & Permit Table Commercial & Bulk Data (CC BY-NC 4.0)

Last verified: · 1 reporting source

● Running First recorded October 21, 2026 · 1 Building

Ayera Technologies Modesto Data Center

Street address 801 Tenth Street, Modesto, CA 95354, Stanislaus County verified address Exact, at the address [1] ayera.com

Overview, regulatory gates and specifications

Ayera Technologies operates a commercial colocation and wireless internet backbone data center at 801 Tenth Street in downtown Modesto, Stanislaus County, California, with 2 MW of power capacity. [1] Filings on the record specify 1 planned or operational building. [1] Verified facility status from California state agency permits, utility dockets, municipal planning filings, or operator campus specifications. [1]

1. Land & Parcel
Parcel located
2. Local Zoning
Zoning approved
3. Tax & EDA Deal
Not yet on file
4. Utility Grid Queue
Energized
5. Air & Water Permits
Not yet on file
What happens next: Facility is operational; air permit compliance, water reporting and utility filings are monitored.
Electricity Demand [1]
2 MW
the developer's figure

Equivalent to ~1,660 U.S. homes (U.S. EIA 830 homes/MW baseline) · 0.1% of Hoover Dam nameplate capacity (2,080 MW).

Grid interconnection and utility service tracked on file.

Cooling & Water
Not disclosed
Daily water volume not stated in public filings

U.S. EPA household water equivalence (300 gal/day per home) requires a disclosed daily or annual water figure.

No local property tax abatement amount disclosed in public filings.

Site & Buildings [1]
1 building
operator page

Assessor parcel acreage and building square footage are added when municipal or county filings are published.

Location: 801 Tenth Street, Modesto, CA 95354.

Taxes & Permanent Jobs
Not disclosed
Tax and job figures not yet on file

State and local tax abatement agreements and permanent job commitments are recorded when filed.

No local property tax abatement amount disclosed in public filings.

Key specifications on the record

Power capacity
2 MW developer figure Equivalent to the continuous electricity demand of about 1,660 average U.S. homes based on U.S. Energy Information Administration residential consumption data. Less than 0.1 percent (0.02 percent) of New York City's summer peak demand in 2024.
[1] ayera.com
Water usage
Not disclosed
Land area
Not disclosed
Buildings
1 building operator page
[1] ayera.com
Backup generators
Not disclosed
Capital investment
Not disclosed
Commissioned
Operational since 2018 (8 years)
Who leads it
Ayera Technologies as stated by the source
Not disclosed
Who would use it, Jobs once it runs, Tax each year
The math behind the comparison
  1. Ayera Technologies Modesto Data Center, capacity: 2 MW.
  2. New York City (NYISO Zone J) summer peak demand, actual, 2024: 10,245 MW (2024).
  3. 2 ÷ 10,245 = 0.0002 (MW over MW).

Sources:

A comparison is arithmetic on two published rows and is never a new fact (how comparisons are made).

Who is connected to this project

Connected government officials, corporate entities, utilities and local rules on the public record.

Builder, Shell LLC & Utilities

BUILDER
Operator / Developer: Ayera Technologies
UTILITIES
Electric utility: Not disclosed

Citizen privacy standard: Elected officials, corporate applicants and utility executives are named in full. Private residents who speak at public comment are cited as Resident First L. unless they hold public office or speak on behalf of an organization.

Technical specification and permit ledger

Disclosed engineering ceilings, reported actuals and primary regulatory basis for Ayera Technologies Modesto Data Center.

Field / Parameter Disclosed Ceiling Reported Actual Basis & Primary Source
Electrical Capacity (MW) 2 MW 2 MW the developer's figure [1] ayera.com
Site Footprint (Acres)
Data Hall Buildings 1 building 1 operator page [1] ayera.com
Cooling & Water System
Backup Diesel / Gas Generators
Tax Abatement & Annual Revenue

Blank cell: not disclosed by any source on file.

Still not public, and where it would show up

The record adds each the day a source gives it. Why these documents.

  • Water use A state water right filing or a water supply agreement.
  • Who would use it A lease announcement or a tenant named in a filing.
  • Jobs and tax An incentive agreement, a county's economic development filing or a fiscal note.

Hearings and statements on the record

August 11, 2026 Modesto, CA Modesto City Council Regular Meeting Modesto City Council 2 clips

Modesto Mayor Sue Zwahlen opened the City Council meeting by announcing that large data centers are not a permitted zoning use in Modesto and that city staff is exploring a formal moratorium following resident opposition over agricultural water supplies.

  1. Sue Zwahlen, Mayor, City of Modesto Elected Official transcribed from the official recording
    "Before we move to public comment, I understand there may be many individuals here and online who have concerns regarding data centers. The issue has received significant attention in the news and the city has received numerous comments and questions on this topic. As the city has previously stated publicly and to the press, large data centers are not currently in allowed use or under the"
  2. Resident public comment Resident Public Comment transcribed from the official recording
    "here in Modesto. I'm here to let you know we have already used up the majority of natural resources that the planet can regenerate this year. Not talking about exactly here in our region just yet, but AI data centers could pollute and waste what's left. Especially when we have finite resources, the water you need for your livestock, your agriculture, all of that could be gone. Your property values in time will tank too because nobody can"

Timeline on the record

Chronological regulatory, corporate and permitting events on the record, newest first.

No dated entry is on the record yet.

Every event in order

  • Read on October 27, 2026 (the day the page was read; it gives no date of its own)

    Verified facility status from California state agency permits, utility dockets, municipal planning filings, or operator campus specifications.

    [1] ayera.com

Nearest data centers in California

Verified data center records in California within 60 miles by straight line distance.

Facility & Location Distance Stage Operator / Tenant Disclosed Scale
Modesto East Claus Road Hyperscale Data Center Proposal Modesto, Stanislaus County 4 mi Proposed Modesto Industrial Development 1 building
EZ Network Systems Stockton Data Center Stockton, San Joaquin County 30 mi Running EZ Network Systems 2 MW
New York GreenCloud Ione Biomass Powered Data Center Proposal Ione, Amador County 49 mi Proposed New York GreenCloud 1 building
Equinix Silicon Valley Great Oaks Campus (SV1 / SV5 / SV10 San Jose) San Jose, Santa Clara County 51 mi Running Equinix 1 building
Equinix San Jose Great Oaks and North San Jose Campus (SV1, SV3, SV5, SV10, SV11, and SV12x) San Jose, Santa Clara County 51 mi Running Equinix 96 MW
Equinix Silicon Valley (SV3 1735 Lundy Avenue San Jose) San Jose, Santa Clara County 52 mi Running Equinix 1 building

Blank cell: not disclosed by any source on file.

Common questions about Ayera Technologies Modesto Data Center

Answered directly from the verified filings and local actions on this page.

Who is building Ayera Technologies Modesto Data Center?

Ayera Technologies is the developer. No construction contractor is named on the record yet.

How much power and water does Ayera Technologies Modesto Data Center say it needs?

Power: 2 MW (the developer's figure, ayera.com (opens in a new tab)). Water: not disclosed by any source on file.

Where does Ayera Technologies Modesto Data Center stand today?

It is running; the date it reached that stage is not sourced, only the day a page was read. No dated entry is on the record yet.

Sources

Primary documents first: filings, minutes, dockets and official pages. Then reporting. The numbers are the ones the entries above cite.

Reporting

  1. Ayera Technologies Modesto Data Center Official Disclosure (opens in a new tab), Ayera Technologies, news outlet

1 source on file.

Regional grid context

This site is in the WECC California (CAMX) regional power market.

Sources and data

Cite this page

Every record on this page carries its sources and the date it was last verified. When you cite it in a story, a study or a public filing, link to this page and give the date you accessed it.

Get this data

Every row on this page is available to download with its source, its basis and the date it was last verified.

Use this data in your work

Free to use and republish with attribution for reporting, research, teaching and public filings under CC BY-NC 4.0. Commercial, enterprise, financial or AI training use needs a commercial license.

About this data

Last verified
Next check Feeds every four hours, pages daily.
Figures Each figure as its source gave it, with its basis; another source's figure never stands in for the record's own, and nothing is estimated.
License Data CC BY-NC 4.0 (opens in a new tab); free for personal, academic, civic and newsroom reporting with attribution. Using this data in a report? Support the record. Commercial use needs a license. Prose stays under copyright.
Cite this page Data Center Record, "Ayera Technologies Modesto Data Center", https://datacenterrecord.org/projects/ayera-technologies-inc-801-tenth-street-modesto-ayera-ca, last verified October 27, 2026. CSV · JSON
Using this data in a report? Support the record. Commercial use needs a license.
Cite this page

Data Center Record, "Ayera Technologies Modesto Data Center", https://datacenterrecord.org/projects/ayera-technologies-inc-801-tenth-street-modesto-ayera-ca. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.

The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.

Report a change
For researchers
Stage
Running
Tier
built from one source
Tags
Built from one source
Coordinates
37.6385, -120.9968
How the location is known
Location from the site's street address.
Location source
https://www.ayera.com/datacenter/
Coordinate source
Stanislaus County Assessor / Ayera Technologies Modesto specification
How capacity was disclosed
the developer's figure
Capacity, if disclosed
2 MW, the developer's figure
Published
October 21, 2026
Last verified
October 27, 2026
Not disclosed
Location source number, Location last verified, EPA registry id, Uses, Tenancy, Cooling, How water was disclosed, How acreage was disclosed, Interconnection, Rating of the county's rows

Researcher view · Ayera Technologies Modesto Data Center · 1 source, 1 entry · basis and source tier on every row · verified October 27, 2026

Download CSV JSON