Applied Digital Polaris Forge 2 (Harwood), in order
What happened with this project, oldest first: the stages it reached, what the county and its cities decided, and every dated step on the record. Each entry links its source.
2 events, September 10, 2025 to May 7, 2026. Also on the record, under the month each belongs to: 7 figures from other sources and 5 lines that are not events of their own. The facts, newest first: the record; the place: North Dakota.
A plain date is the day it happened, as the source states it, or as the line's own sentence states it ("voted on July 6"), which is where the line sits even when it was filed later. "Reported" and a date is the day a source published a line that carries no date of its own. Those lines, and lines that describe rather than report an act, sit under their month rather than on the timeline, with what was said and the figures other sources gave. Every timeline on the site reads its lines by this one rule. How dates are read.
Stages
2025 1 event
-
(the day its own sentence names; filed under Sep 13, 2026)
Entry
Polaris Forge 2 data center approved by Harwood City Council on September 10 2025 [11]
2026 1 event
-
(content date)
being built
Applied Digital began construction of a 280MW data center in Harwood in September 2025, representing a 3 billion dollar investment; North Dakota Public Service Commission approved a temporary variance for the 110 million dollar power project serving the campus. [1]
-
Also in August 2026: 2 lines that are not events of their own
-
Also in September 2026: 6 figures from other sources and 3 lines that are not events of their own
-
(source date; the content gives no date of its own)
Entry
Harwood city council approved the Applied Digital data center and signed a three billion dollar deal within 21 days of initial announcement [9]
-
(source date; the content gives no date of its own)
Figure · InForum
46,000,000 dollars: Customers in North Dakota and South Dakota have saved more than 46 million dollars in electricity bills since the Ellendale project started InForum (opens in a new tab) local outlet
-
(source date; the content gives no date of its own)
Entry
Remaining portion will open in early 2027 [11]
-
(source date; the content gives no date of its own)
Entry
Part of Harwood data center expected to become operational by end of 2026 [11]
-
(source date; the content gives no date of its own)
Figure · Grand Forks Herald
400 acres: Applied Digital owns 400 acres and moved dirt on 300 acres Grand Forks Herald (opens in a new tab) local outlet
-
(source date; the content gives no date of its own)
Figure · Grand Forks Herald
86,000 electrical connections: Buildings will have roughly 86,000 electrical connections and several miles of copper cable Grand Forks Herald (opens in a new tab) local outlet
-
(source date; the content gives no date of its own)
Figure · Grand Forks Herald
907,000 square feet: Two buildings at Polaris Forge 2 each measure 907,000 square feet Grand Forks Herald (opens in a new tab) local outlet
-
(source date; the content gives no date of its own)
Figure · Grand Forks Herald
280 MW: Polaris Forge 2 is a 280 megawatt data center Grand Forks Herald (opens in a new tab) local outlet
-
(source date; the content gives no date of its own)
Figure · Grand Forks Herald
112,000,000 USD: Applied Digital will pay $112 million for substation and transmission upgrades Grand Forks Herald (opens in a new tab) local outlet
-
-
Also in October 2026: 1 figure from another source
-
(source date; the content gives no date of its own)
Figure · InForum
540 MW: At full build out, Geronimo says the data center could use up to 540 megawatts of electricity InForum (opens in a new tab) local outlet
-
On the timeline: a stage change; an entry that reports an act on the day the source or its own sentence gives; and a decision, a published scorecard event on a row at or under the record's county, that reports an act. Under the months: a statement that names this record, a figure another source gave about it, matched by place and developer, an entry dated only by the day its source was published, and an entry or a decision that describes rather than reports an act. Each is on the record in its own right and keeps its own link.
For researchers
- Stage
- being built
- Events on the timeline
- 2
- Under the months
- 12
- Stage changes
- 1
- Decisions
- 0
- Statements
- 0
- Figures
- 7
- Entries and decisions under the months
- 5