Ace Data Center, in order

What happened with this project, oldest first: the stages it reached, what the county and its cities decided, and every dated step on the record. Each entry links its source.

5 events, January 15, 2026 to October 20, 2026. Also on the record, under the month each belongs to: 16 lines that are not events of their own. The facts, newest first: the record; the place: Utah.

A plain date is the day it happened, as the source states it, or as the line's own sentence states it ("voted on July 6"), which is where the line sits even when it was filed later. "Reported" and a date is the day a source published a line that carries no date of its own. Those lines, and lines that describe rather than report an act, sit under their month rather than on the timeline, with what was said and the figures other sources gave. Every timeline on the site reads its lines by this one rule. How dates are read.

Stages

  1. running

Now: running. A stage is the record's status after the entry that set it (the definitions).

2026 5 events

  1. (content date)

    running

    Ace Data Center operates its colocation data center at 1950 South 950 East in Provo under Utah Division of Air Quality permit 4904900259. [1]

  2. (content date)

    Decision · Spanish Fork (city)

    After a six hour public hearing, Spanish Fork City Council tabled a vote on Title 15 amendments that would set rules for self powered data centers until September 1. heraldextra.com (opens in a new tab)

  3. Also in August 2026: 11 lines that are not events of their own
    1. (source date; the content gives no date of its own)

      Decision · Spanish Fork (city)

      The Spanish Fork City Council voted to table the ordinance after a six and a half hour meeting with extensive public comment abc4.com (opens in a new tab)

    2. (source date; the content gives no date of its own)

      Decision · Spanish Fork (city)

      City council tabled resolution to amend ordinance allowing data centers to generate their own power fox13now.com (opens in a new tab)

    3. (source date; the content gives no date of its own)

      Decision · Spanish Fork (city)

      Spanish Fork city council held five hour public hearing on data center proposal with dozens of commenters fox13now.com (opens in a new tab)

    4. (source date; the content gives no date of its own)

      Decision · Spanish Fork (city)

      Proposed amendments require closed loop, air cooled or dry cooling systems to limit water use heraldextra.com (opens in a new tab)

    5. (source date; the content gives no date of its own)

      Decision · Spanish Fork (city)

      Proposed amendments to Title 15 would cap a data center at 500 megawatts heraldextra.com (opens in a new tab)

    6. (source date; the content gives no date of its own)

      Decision · Spanish Fork (city)

      Spanish Fork City Council worked to establish requirements for data centers and other facilities that generate their own electricity by amending Title 15 of the municipal code heraldextra.com (opens in a new tab)

    7. (source date; the content gives no date of its own)

      Decision · Spanish Fork (city)

      The proposed regulations would limit no more than two data center sites with onsite power generation within city limits sltrib.com (opens in a new tab)

    8. (source date; the content gives no date of its own)

      Decision · Spanish Fork (city)

      Spanish Fork is considering changing city code to establish rules and requirements for data centers with onsite power generation facilities sltrib.com (opens in a new tab)

    9. (source date; the content gives no date of its own)

      Decision · Eagle Mountain (city)

      Eagle Mountain walked back its first tax hike but residents will still pay about double the old rate sltrib.com (opens in a new tab)

    10. (source date; the content gives no date of its own)

      Decision · Eagle Mountain (city)

      Meta and Google received tax incentives or breaks for data centers in Eagle Mountain sltrib.com (opens in a new tab)

    11. (source date; the content gives no date of its own)

      Decision · Eagle Mountain (city)

      Eagle Mountain raised property taxes 183% sltrib.com (opens in a new tab)

  4. (content date)

    Decision · Spanish Fork (city)

    Spanish Fork City Council delayed the Title 15 amendment vote a second time, for another two weeks. fox13now.com (opens in a new tab)

  5. Also in September 2026: 5 lines that are not events of their own
    1. (content date)

      Decision · Spanish Fork (city)

      A Spanish Fork public hearing on August 18 lasted more than six hours with dozens of residents expressing concerns about the Volition proposal ksl.com (opens in a new tab)

    2. (source date; the content gives no date of its own)

      Decision · Spanish Fork (city)

      Spanish Fork City Council decided not to amend Title 15 after months of study and a two week delay, deferring the final decision for another two weeks fox13now.com (opens in a new tab)

    3. (source date; the content gives no date of its own)

      Decision · Spanish Fork (city)

      City Council approved zoning change allowing data center at mouth of Spanish Fork Canyon sltrib.com (opens in a new tab)

    4. (source date; the content gives no date of its own)

      Decision · Spanish Fork (city)

      Spanish Fork City Council members limited the city to only one data center unless city leaders vote to change that in the future. ksl.com (opens in a new tab)

    5. (source date; the content gives no date of its own)

      Decision · Spanish Fork (city)

      Spanish Fork City Council voted to approve changes to city code for a data center. ksl.com (opens in a new tab)

  6. (content date)

    Decision · Utah County (county)

    The Utah County Commission voted to approve a land use ordinance for data centers without taking public comment on Oct. 20, 2026. universe.byu.edu (opens in a new tab)

  7. (content date)

    Decision · Utah County (county)

    Utah County Planning Commission voted to recommend approval of Application #2026-09 proposing amendments to UCLUO Sections 8.132, 2.08, 10.04, 12.28, 12.40, and 12.72 establishing a Data Center Overlay (DCO) Zone in Mining and Grazing (M&G-1) and Industrial (I-2) zones, advancing to the Board of County Commissioners for final adoption. codev.utahcounty.gov (opens in a new tab)

On the timeline: a stage change; an entry that reports an act on the day the source or its own sentence gives; and a decision, a published scorecard event on a row at or under the record's county, that reports an act. Under the months: a statement that names this record, a figure another source gave about it, matched by place and developer, an entry dated only by the day its source was published, and an entry or a decision that describes rather than reports an act. Each is on the record in its own right and keeps its own link.

For researchers
Stage
running
Events on the timeline
5
Under the months
16
Stage changes
1
Decisions
20
Statements
0
Figures
0
Entries and decisions under the months
16