Timestamped Speaker & Testimony Ledger
3 verified timestamped clips extracted chronologically from the closed caption record. Select any clip to play that exact window in the master player or copy a canonical clip link.
- Clip 1 · 0:23 WPLG Local 10 Broadcast Report Broadcast Report Questioning transcribed from local broadcast reportZoning Power & Grid Water
WPLG Local 10 broadcast report on Wellington, FL covering Palm Beach County Board of County Commissioners proceedings and community debate over data center siting, utility demand, and neighborhood impacts (Segment 1).
"We have a choice, use your voice. As data centers rise, No data centers. so does the backlash. NO DATA CENTERS, NOT TODAY. BIPARTISAN protests all over the country and now the fight has come to Florida. You'd have to be living under a rock to not realize how horrible these centers are. Project Tango, a proposed hyperscale data center, the first in the state, in western Palm Beach County."
- Clip 2 · 1:03 Resident public comment Resident Public Comment transcribed from local broadcast report
Resident interview in the WPLG Local 10 report on Wellington, FL addressing grid capacity and utility rates, zoning and land use rules before Palm Beach County Board of County Commissioners.
"The site chosen because it's just a few hundred feet away from a major power plant. And so you have one of the most connected pieces of electrical infrastructure in Florida with the largest power plant in the state of Florida immediately next to a site that's been zoned and used for industrial uses for decades. But it's the location also generating fierce opposition. Project Tango"
- Clip 3 · 1:31 WPLG Local 10 Broadcast Report Broadcast Report Questioning transcribed from local broadcast reportZoning Power & Grid Water
WPLG Local 10 broadcast report on Wellington, FL covering Palm Beach County Board of County Commissioners proceedings and community debate over water consumption, tax incentives and revenue projections (Segment 3).
"and an elementary school, both just outside of Wellington. Project Tango's original master plan was approved 10 years ago, but now developers are seeking permission to expand that plan by 1.5 million square feet, mostly they say for warehouses but could also be used for more data center space. Dozens of data centers already exist in Miami Dade County like this one, Iron Mountain, set to open later this year,"
Read full auto generated transcript (3 segments)
[0:23] WPLG Local 10 Broadcast Report: We have a choice, use your voice. As data centers rise, No data centers. so does the backlash. NO DATA CENTERS, NOT TODAY. BIPARTISAN protests all over the country and now the fight has come to Florida. You'd have to be living under a rock to not realize how horrible these centers are. Project Tango, a proposed hyperscale data center, the first in the state, in western Palm Beach County.
[1:03] Resident public comment: The site chosen because it's just a few hundred feet away from a major power plant. And so you have one of the most connected pieces of electrical infrastructure in Florida with the largest power plant in the state of Florida immediately next to a site that's been zoned and used for industrial uses for decades. But it's the location also generating fierce opposition. Project Tango
[1:31] WPLG Local 10 Broadcast Report: and an elementary school, both just outside of Wellington. Project Tango's original master plan was approved 10 years ago, but now developers are seeking permission to expand that plan by 1.5 million square feet, mostly they say for warehouses but could also be used for more data center space. Dozens of data centers already exist in Miami Dade County like this one, Iron Mountain, set to open later this year,