New Mexico, year by year.
Every act on the record for New Mexico, on the day it happened, newest first by month. Under each month, one tap away, the background, plans and statements the same sources carried. The counts are the state hub's records; nothing is estimated.
The record by year
On the record as of October 27, 2026.
An act sits on the day it happened: the day its own sentence names, or the day its source gives for it. An act the record knows only from the date of the article that reported it sits under that article's month, one tap away, marked Reported with the article's date. So do background, plans and statements, which are not acts. The same act reported by several sources is one line with the reports behind it, on its day where any of them dates it. The milestones alone, for every state, are on the timeline.
21 acts on the line for New Mexico, from 107 dated lines in the records' histories and the scorecard. 31 more acts are dated only by the article that reported them and sit under their month. 21 lines report an act already listed. 34 lines are background, plans or statements. 8 lines sit on a date other than the one they were filed under, because their own sentence names the day, the month or the year it happened; each says so. Where a line sits is read from its own words and the row is never changed (how dates are read).
2026 20 acts on the line from 35 reports; 30 reported, dated only by the article; 34 lines of background, plans and statements
October 2026 2 acts on the line
Grant County commissioners approved a one year moratorium on data center development.
santafenewmexican.com (opens in a new tab), local outlet
Oracle reported that construction on Project Jupiter data center campus is moving quickly with strong progress on site, and will achieve 100% carbon free energy matching by 2031.
finance.yahoo.com (opens in a new tab), national outlet
September 2026 6 acts on the line from 14 reports; 28 reported; 31 lines of background, plans and statements
Oracle issued a force majeure notice to STACK Infrastructure on September 24, allowing it to protect itself contractually if Project Jupiter fails to launch as planned in 2028
tradingview.com (opens in a new tab), national outlet
1 more report of this
- Reported September 24 Oracle issued force majeure notice to Project Jupiter developers finance.yahoo.com (opens in a new tab)
Sen. Martin Heinrich blocked a bipartisan bill in the Senate on Thursday seeking to fast track the Ratepayer Protection Act
deseret.com (opens in a new tab), local outlet
New Mexico Supreme Court denied petitions filed by New Energy Economy and the Center for Biological Diversity on September 17
lcsun-news.com (opens in a new tab), local outlet
7 more reports of this
- Reported September 17 New Mexico Supreme Court denied writ of mandamus requested by New Energy Economy against state Environment Department regarding air quality permit for Project Jupiter kvia.com (opens in a new tab)
- Reported September 17 New Mexico Supreme Court denied writ of mandamus requested by Center for Biological Diversity against state engineer regarding water use for Project Jupiter kvia.com (opens in a new tab)
- Reported September 17 New Mexico Supreme Court denied challenges from New Energy Economy and Center for Biological Diversity to regulatory proceedings for Project Jupiter yahoo.com (opens in a new tab)
- Reported September 17 New Mexico Supreme Court denied petitions filed by environmental groups against the hyperscale data center Project Jupiter. santafenewmexican.com (opens in a new tab)
- Reported September 17 New Mexico Supreme Court lifted two stays and denied petitions regarding Project Jupiter lcsun-news.com (opens in a new tab)
- Reported September 21 New Mexico Supreme Court denied New Energy Economy petition requesting cancellation of the air quality permit hearing for Project Jupiter. in.investing.com (opens in a new tab)
- Reported September 21 New Mexico Supreme Court denied Center for Biological Diversity challenge to emergency authorization for water well access at Project Jupiter. in.investing.com (opens in a new tab)
City of Clovis Commission voted 5-3 on Thursday to reject a proposed 120 day moratorium on building any data centers within city limits.
abc7amarillo.com (opens in a new tab), local outlet
New Mexico Supreme Court rulings on September 17 unanimously denied emergency petitions and restored Oracle's access to non potable groundwater via private supplier.
kunr.org (opens in a new tab), local outlet
New Mexico Supreme Court stayed air permit proceeding for proposed microgrid serving campus on Sept. 14
theenergymag.com (opens in a new tab), news outlet (the day its own sentence names; filed under Sep 24, 2026)
Reported in September 2026, dated only by the article that carried them: 28 acts
Oracle sent force majeure notice to Blue Owl Capital seeking payment deferral if project misses 2028 deadline
datacenterdynamics.com (opens in a new tab), trade press (dated only by the report that carried it, so under the month of the report)
5 more reports of this
- Reported September 24 Oracle sent a force majeure notice to Blue Owl Capital unit seeking to delay payments if data center fails to come online in 2028 proactiveinvestors.com (opens in a new tab)
- Reported September 24 Oracle sent force majeure notice to Blue Owl Capital on Project Jupiter after energy permit denial and pipeline delay. finance.yahoo.com (opens in a new tab)
- Reported September 24 Oracle sent Blue Owl a force majeure notice about Project Jupiter data center in New Mexico ai-cio.com (opens in a new tab)
- Reported September 24 Oracle sent a force majeure notice to Project Jupiter's developer in New Mexico. seekingalpha.com (opens in a new tab)
- Reported September 24 Oracle sent force majeure notice to Project Jupiter developer seeking to delay payments if data center misses 2028 operational target tradingview.com (opens in a new tab)
Oracle issued Request for Proposals to develop 2GW of renewable energy capacity in New Mexico for Project Jupiter
datacenterdynamics.com (opens in a new tab), trade press (dated only by the report that carried it, so under the month of the report)
Oracle sent a contractual notice tied to Project Jupiter seeking protection if construction delays disrupt its 2028 target
finance.yahoo.com (opens in a new tab), national outlet (dated only by the report that carried it, so under the month of the report)
Energy Transfer pipeline delayed to February 1, 2027 after regulatory denials.
finance.yahoo.com (opens in a new tab), national outlet (dated only by the report that carried it, so under the month of the report)
Oracle declared force majeure over possible power delays to Project Jupiter data center in New Mexico to delay transition to higher rent payments.
fool.com (opens in a new tab), national outlet (dated only by the report that carried it, so under the month of the report)
Green Chile pipeline was delayed from August 2026 target to February 2027 after New Mexico State Land Office denied right of way permits.
investing.com (opens in a new tab), national outlet (dated only by the report that carried it, so under the month of the report)
Oracle issued a force majeure notice to Blue Owl, the project developer unit, due to facility delays relative to the 2028 launch date.
investing.com (opens in a new tab), national outlet (dated only by the report that carried it, so under the month of the report)
Project Jupiter's Green Chile natural gas pipeline was delayed from August 2026 to February 2027.
seekingalpha.com (opens in a new tab), national outlet (dated only by the report that carried it, so under the month of the report)
Oracle sends force majeure notice on Project Jupiter data center in New Mexico
cnbc.com (opens in a new tab), national outlet (dated only by the report that carried it, so under the month of the report)
1 more report of this
- Reported September 24 Oracle sends force majeure notice seeking to defer payments if project delays beyond 2028 opening theenergymag.com (opens in a new tab)
Oracle sent a force majeure notice to the developer building Project Jupiter due to regulatory hurdles and local opposition.
fxstreet.com (opens in a new tab), news outlet (dated only by the report that carried it, so under the month of the report)
Oracle issued force majeure notice on major data center project in New Mexico where it is primary tenant
ground.news (opens in a new tab), national outlet (dated only by the report that carried it, so under the month of the report)
Center for Biological Diversity sued New Mexico State Engineer Elizabeth Anderson over water use.
kunr.org (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)
Deb Haaland, Democratic Gubernatorial Candidate, announced she will sign a moratorium on new data centers until state level protections are in place, including requirements for renewable energy infrastructure, closed loop water systems, union labor, environmental protections, and decommissioning bonds.
kob.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)
Democratic gubernatorial candidate Deb Haaland announced proposal for executive order calling for moratorium on large scale data centers
santafenewmexican.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)
Haaland presented an eight point list for data center regulation to be negotiated during the 2027 New Mexico legislative session.
buffalosfire.com (opens in a new tab), news outlet (dated only by the report that carried it, so under the month of the report)
Oracle sought to influence New Mexico Environment Department officials on air quality permit for natural gas powered fuel cell system
sourcenm.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)
Socorro County commissioners unanimously approved a one year moratorium on data centers
vasquez.house.gov (opens in a new tab), primary source (dated only by the report that carried it, so under the month of the report)
Raton commissioners approved a six month memorandum of understanding with Atterix LLC to study converting an old Kmart into an advanced digital hub
santafenewmexican.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)
Colfax County adopted a one year moratorium on data centers in unincorporated areas
santafenewmexican.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)
Socorro County adopted a yearlong moratorium on data centers
santafenewmexican.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)
Sierra County adopted an 18 month moratorium on data centers
santafenewmexican.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)
Santa Fe County unanimously approved an 18 month moratorium on data centers without a project pending
santafenewmexican.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)
A petition opposing data center construction in Raton gathered hundreds of signatures
santafenewmexican.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)
Community monitoring committee appointed to examine water, power, and air quality impacts
kfoxtv.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)
NM attorney general backed emergency petitions challenging data center air and water permits
kfoxtv.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)
New Mexico land commissioner rejected Canadian data center company pitch at Spaceport America
sourcenm.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)
New Mexico Commissioner of Public Lands Stephanie Garcia Richard blocked the Aetherion data center proposal at Spaceport America
sourcenm.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)
Two New Mexico Supreme Court cases placed key permitting processes for Project Jupiter on hold; parties responded Wednesday, September 2, 2026
santafenewmexican.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)
Also on the record for September 2026, not acts of their own: 31 lines of background, plans and statements
New Mexico State Land Office has repeatedly denied right of way permits for the Green Chile pipeline.
seekingalpha.com (opens in a new tab) (a description, not an act)
New Mexico State Commissioner of Public Lands and environmental groups have opposed the pipeline citing climate and resource strain concerns.
investing.com (opens in a new tab) (a description, not an act)
Project Jupiter faces public opposition and permitting delays in New Mexico.
fool.com (opens in a new tab) (a description, not an act)
Air quality permit for fuel cell system has November 23 deadline for state environment department decision.
finance.yahoo.com (opens in a new tab) (a description, not an act)
A natural gas pipeline needed for the facility has faced delays after permit denials
finance.yahoo.com (opens in a new tab) (a description, not an act)
Project planned to come online in 2028.
finance.yahoo.com (opens in a new tab) (a plan or a schedule, not an act yet)
Oracle says Project Jupiter construction remains on schedule despite force majeure notice.
fool.com (opens in a new tab) (a statement; who said what is on the statements pages)
Increased scrutiny followed by denial of a key permit raised questions about whether the data center will come online as planned
ai-cio.com (opens in a new tab) (a statement; who said what is on the statements pages)
Project Jupiter has a 2028 launch date target.
seekingalpha.com (opens in a new tab) (a description, not an act)
Project has faced denial of key permit amid growing public backlash over power demands and local impacts of massive data centers
finance.yahoo.com (opens in a new tab) (a description, not an act)
Oracle invoked force majeure provision to delay payments if Project Jupiter is delayed and facility does not come online in 2028
finance.yahoo.com (opens in a new tab) (a description, not an act)
Project Jupiter was scheduled to come online in 2028.
fxstreet.com (opens in a new tab) (a plan or a schedule, not an act yet)
Natural gas pipeline needed for facility has faced delays after permit denials
finance.yahoo.com (opens in a new tab) (a description, not an act)
Project Jupiter data center in New Mexico targeting 2028 completion
finance.yahoo.com (opens in a new tab) (no act in the sentence)
Oracle seeks to defer payments if Project Jupiter fails to come online in 2028 as planned
finance.yahoo.com (opens in a new tab) (a plan or a schedule, not an act yet)
New Mexico Supreme Court let permitting resume on September 17, 2026
finance.biggo.com (opens in a new tab) (no act in the sentence)
Gas pipeline serving site has twice been denied a state land crossing
finance.biggo.com (opens in a new tab) (a description, not an act)
Natural gas pipeline to serve campus has faced delays and legal challenges involving water and air quality permits
theenergymag.com (opens in a new tab) (a description, not an act)
Oracle data center delay reported in mid day stock market news
finance.yahoo.com (opens in a new tab) (a statement; who said what is on the statements pages)
Haaland proposes temporary data center moratorium via executive order
santafenewmexican.com (opens in a new tab) (a plan or a schedule, not an act yet)
Deb Haaland said she would issue an executive order on her first day to pause data center construction and development until regulations are approved by state lawmakers.
buffalosfire.com (opens in a new tab) (a statement; who said what is on the statements pages)
Haaland would sign an executive order establishing a temporary pause on data center development on her first day as governor.
santafenewmexican.com (opens in a new tab) (a plan or a schedule, not an act yet)
S&P downgraded Oracle in July, leaving its corporate rating one notch above junk
finimize.com (opens in a new tab) (no act in the sentence)
Haaland said her moratorium would not affect Project Jupiter, the Oracle- and OpenAI backed artificial intelligence data center campus under construction at the Santa Teresa Industrial Park.
kob.com (opens in a new tab) (a statement; who said what is on the statements pages)
New Mexico House Democratic Caucus said no industry should have free rein in the state and that members are working on legislation for the 2027 session to address data center concerns
sourcenm.com (opens in a new tab) (a statement; who said what is on the statements pages)
Democrat State Representatives Micaela Lara Cadena and Angelica Rubio plan to introduce legislation next year that would ban future data centers statewide.
yahoo.com (opens in a new tab) (a plan or a schedule, not an act yet)
Haaland's moratorium would not affect Project Jupiter, the Oracle- and OpenAI backed artificial intelligence data center campus under construction at the Santa Teresa Industrial Park.
yahoo.com (opens in a new tab) (a plan or a schedule, not an act yet)
Court unpaused regulatory proceedings that had been frozen since August, allowing air quality permit hearing to move forward
yahoo.com (opens in a new tab) (a description, not an act)
Atterix's six month agreement with Raton city expired in August without the company presenting its feasibility findings publicly
santafenewmexican.com (opens in a new tab) (no act in the sentence)
Bureau of Land Management said it would accelerate the review process for pipeline on federal land in May using 28 day emergency permitting
latitudemedia.com (opens in a new tab) (a statement; who said what is on the statements pages)
New Mexico has a court order to reduce Rio Grande water use
wyomingpublicmedia.org (opens in a new tab) (a description, not an act)
August 2026 4 acts on the line from 11 reports; 2 reported; 3 lines of background, plans and statements
New Mexico Supreme Court paused the air quality permitting process for Project Jupiter on August 23 while overseeing two legal challenges from environmental groups
arstechnica.com (opens in a new tab), national outlet
2 more reports of this
- Reported August 24 NM Supreme Court temporarily halted Project Jupiter air quality permit hearing sourcenm.com (opens in a new tab)
- Reported August 30 New Mexico Supreme Court halted AI data center permit process on or before August 30, 2026 yahoo.com (opens in a new tab)
Court lifted stay imposed on August 23 that had paused air permit proceeding and water use for Project Jupiter
kvia.com (opens in a new tab), local outlet (the day its own sentence names; filed under Sep 17, 2026)
New Mexico Supreme Court issued a unanimous stay pausing proceedings on Project Jupiter's air quality permit application on August 18, 2026.
abqjournal.com (opens in a new tab), local outlet
5 more reports of this
- Reported August 24 New Mexico Supreme Court pauses Project Jupiter permitting and air quality permit process santafenewmexican.com (opens in a new tab)
- Reported August 25 New Mexico Supreme Court paused Project Jupiter permitting processes santafenewmexican.com (opens in a new tab)
- Reported August 25 New Mexico court paused a data center permit and hearing law360.com (opens in a new tab)
- Reported September 17 New Mexico Supreme Court paused state regulatory proceedings for air quality and water use permits for Project Jupiter in response to environmental group petitions santafenewmexican.com (opens in a new tab)
- Reported September 18 New Mexico Supreme Court lifted stays it issued on August 23 lcsun-news.com (opens in a new tab)
New Mexico Supreme Court paused permit proceedings in late August
latitudemedia.com (opens in a new tab), trade press (the month its own sentence names; no day is given; filed under Sep 11, 2026)
Reported in August 2026, dated only by the article that carried them: 2 acts
The court paused the air permit proceedings in response to a petition by New Energy Economy arguing the New Mexico Environment Department cannot proceed without establishing the project's fuel source.
abqjournal.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)
NM residents protested pending Project Jupiter air quality permit outside Environment Department
sourcenm.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)
Also on the record for August 2026, not acts of their own: 3 lines of background, plans and statements
The NM Department of Justice is investigating Project Jupiter for fraudulent public comment submissions
dailylobo.com (opens in a new tab) (a description, not an act)
Reps. Angelica Rubio and Micaela Lara Cadena plan to introduce a statewide data center moratorium in the 2027 legislative session.
searchlightnm.org (opens in a new tab) (a plan or a schedule, not an act yet)
Santa Fe, Socorro and Sierra counties have passed data center moratoriums.
searchlightnm.org (opens in a new tab) (a description, not an act)
July 2026 5 acts on the line
The New Mexico State Land Office turned down requests by Energy Transfer to route the gas pipeline through state land in July 2026.
abqjournal.com (opens in a new tab), local outlet (the month its own sentence names; no day is given; filed under Aug 23, 2026)
A natural gas pipeline extension to feed the campus was rejected by state officials in July
datacenterdynamics.com (opens in a new tab), trade press (the month its own sentence names; no day is given; filed under Sep 9, 2026)
New Mexico land commissioner blocks Project Jupiter related pipeline from building on state land in July 2026
sourcenm.com (opens in a new tab), local outlet (the month its own sentence names; no day is given; filed under Jul 16, 2026)
Santa Fe County adopts data center moratorium in July 2026
sourcenm.com (opens in a new tab), local outlet (the month its own sentence names; no day is given; filed under Jul 1, 2026)
Natural gas pipeline extension rejected by state officials in July 2026
datacenterdynamics.com (opens in a new tab), trade press (the month its own sentence names; no day is given; filed under Sep 24, 2026)
June 2026 1 act on the line
New tensions flared over Project Jupiter data center in southern New Mexico
krqe.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)
January 2026 1 act on the line
Oracle announced as tenant of Project Jupiter in January 2026
datacenterdynamics.com (opens in a new tab), trade press (the month its own sentence names; no day is given; filed under Sep 24, 2026)
2026, no month given 1 act
New Mexico state land commissioner denied pipeline project's application for rights of way across state trust lands in spring 2026
latitudemedia.com (opens in a new tab), trade press (the year its own sentence names; filed under Sep 11, 2026)
2025 1 act on the line
October 2025 1 act on the line
New Mexico Office of the State Engineer authorized emergency drilling in October 2025
lcsun-news.com (opens in a new tab), local outlet (the month its own sentence names; no day is given; filed under Sep 18, 2026)
2022 0 acts on the line; 1 reported, dated only by the article
June 2022 No acts on the line; 1 reported
Reported in June 2022, dated only by the article that carried it: 1 act
H5 bought 505 Marquette in Albuquerque
datacenterdynamics.com (opens in a new tab), trade press (dated only by the report that carried it, so under the month of the report)