  1. California News item

    Vantage Data Centers Campus, Phase 1: Buildings 1&2 - enr.com. Vantage Data Centers Phase 1 at Santa Clara campus received an Award of Merit for two four story, 385,000 square foot buildings with 45 MW total capacity and LEED Silver certification. enr.com, 2021-10-01. enr.com local outlet (reported on this date) (reported on; the source's own date)

    CAvantage-data-centers-santa-clara-ca