TierPoint Fort Worth Data Center, in order

What happened with this project, oldest first: the stages it reached, what the county and its cities decided, and every dated step on the record. Each entry links its source.

2 events, August 12, 2026 to September 8, 2026. Also on the record, under the month each belongs to: 4 lines that are not events of their own. The facts, newest first: the record; the place: Texas.

A plain date is the day it happened, as the source states it, or as the line's own sentence states it ("voted on July 6"), which is where the line sits even when it was filed later. "Reported" and a date is the day a source published a line that carries no date of its own. Those lines, and lines that describe rather than report an act, sit under their month rather than on the timeline, with what was said and the figures other sources gave. Every timeline on the site reads its lines by this one rule. How dates are read.

Stages

  1. running

Now: running. A stage is the record's status after the entry that set it (the definitions).

2026 2 events

  1. (content date)

    Decision · Keller (city)

    Keller City Council issued unanimous resolution opposing data center on August 12 newsweek.com (opens in a new tab)

  2. (content date)

    Decision · Tarrant County (county)

    Tarrant County Commissioner Matt Krause hosted a town hall on data centers in Hurst on Tuesday with 23 speakers keranews.org (opens in a new tab)

  3. Also in September 2026: 3 lines that are not events of their own
    1. (source date; the content gives no date of its own)

      Decision · Fort Worth (city)

      Fort Worth Data Center & Infrastructure Commission report scheduled for City Council briefing November 3, 2026, before potential first public hearing on data center moratorium yahoo.com (opens in a new tab)

    2. (source date; the content gives no date of its own)

      Decision · Fort Worth (city)

      Fort Worth Data Center & Infrastructure Commission established with 11 voting members to evaluate data center impacts on electricity, water, economic development and neighborhood effects fortworthreport.org (opens in a new tab)

    3. (source date; the content gives no date of its own)

      Decision · Fort Worth (city)

      Fort Worth City Council voted for a moratorium on data center development fortworthreport.org (opens in a new tab)

  4. Also in October 2026: 1 line that is not an event of its own
    1. (the day the page was read; it gives no date of its own)

      Entry

      Verified facility status from primary EPA ECHO or operator record. [2]

On the timeline: a stage change; an entry that reports an act on the day the source or its own sentence gives; and a decision, a published scorecard event on a row at or under the record's county, that reports an act. Under the months: a statement that names this record, a figure another source gave about it, matched by place and developer, an entry dated only by the day its source was published, and an entry or a decision that describes rather than reports an act. Each is on the record in its own right and keeps its own link.

For researchers
Stage
running
Events on the timeline
2
Under the months
4
Stage changes
0
Decisions
5
Statements
0
Figures
0
Entries and decisions under the months
4

Researcher view · basis and source tier on every row · docket and Census GEOIDs · citation and export tools