T5@Chicago IV Grayslake Data Center Campus, in order
What happened with this project, oldest first: the stages it reached, what the county and its cities decided, and every dated step on the record. Each entry links its source.
1 event, August 30, 2026. Also on the record, under the month each belongs to: 6 statements, 3 figures from other sources and 5 dates when source pages were read and verified. The facts, newest first: the record; the place: Illinois.
A plain date is the day it happened, as the source states it, or as the line's own sentence states it ("voted on July 6"), which is where the line sits even when it was filed later. "Reported" and a date is the day a source published a line that carries no date of its own. Those lines, and lines that describe rather than report an act, sit under their month rather than on the timeline, with what was said and the figures other sources gave. Every timeline on the site reads its lines by this one rule. How dates are read.
Stages
2026 1 event
-
Also in June 2026: 2 statements and 1 figure from another source
-
(said in the source itself)
Statement · Robin D. Meier, Mayor of Mundelein
The Village of Mundelein found out about this project after it was approved, permits issued, and construction started www.mundelein.org (opens in a new tab) news outlet
-
(said in the source itself)
Statement · Robin D. Meier, Mayor of Mundelein
Mundelein does not get any money or revenue from the Grayslake T5 Data Center project www.mundelein.org (opens in a new tab) news outlet
-
(source date; the content gives no date of its own)
Figure · www.facebook.com
10,000,000 square feet: T5 Data Center is 10 million square feet www.facebook.com (opens in a new tab) social media
-
-
(source date; the content gives no date of its own)
approved
T5 @ Chicago IV data center campus was given approvals in 2024 and 2025 by the Grayslake Village Board [5]
-
Also in August 2026: 1 statement
-
(said in the source itself)
Statement · Daniel Didech, Illinois State Representative
Daniel Didech said he is going to push for passage of the POWER Act when the General Assembly returns to Springfield for the fall veto session lakemchenryscanner.com (opens in a new tab) news outlet
-
-
Also in September 2026: 2 statements, 2 figures from other sources and 5 dates when source pages were read and verified
-
(content date)
Entry
T5 and the village of Grayslake are moving forward with a data center development that has received its first permit in what is described as an $18 billion development, while a resident lawsuit is ongoing. [1]
-
(source date; the content gives no date of its own)
Entry
Grayslake Data Center received first permit in $18 billion T5 development [9]
-
(source date; the content gives no date of its own)
Figure · Patch
18,000,000,000 USD: T5 Grayslake data center development is valued at $18 billion Patch (opens in a new tab) local outlet
-
(source date; the content gives no date of its own)
Figure · Patch
800,000 square feet: The 800,000 square foot facility is the first structure at the massive T5 campus Patch (opens in a new tab) local outlet
-
(source date; the content gives no date of its own)
Entry
T5 Grayslake campus planned to include 11 buildings totaling 6.75 million square feet [8]
-
(source date; the content gives no date of its own)
Entry
T5 Grayslake issued its first building permit for 800,000 square foot data center on 473 acre site [8]
-
(source date; the content gives no date of its own)
Entry
Residents filed lawsuit against T5 with hearing scheduled for November 2026 [7]
-
(content date; reported from elsewhere)
Statement · Peter Marin, T5 CEO
T5 stated it has a separate rate agreement with ComEd and will pay for all power consumed. NBC 5 Chicago (opens in a new tab) local outlet
-
(content date; reported from elsewhere)
Statement · Peter Marin, T5 CEO
T5 CEO Peter Marin stated the company followed all procedural requirements and conducted 18 public meetings with advance notice. NBC 5 Chicago (opens in a new tab) local outlet
-
-
Also in October 2026: 1 statement
-
(content date; reported from elsewhere)
Statement · Bob Landolfi, Coalition member
The village and T5 are barreling ahead and making unsubstantiated claims about jobs and revenue while omitting the costs. And at the end of the day, we can't buy quiet or clean air and water.
Chicago Tribune (opens in a new tab) local outlet
-
On the timeline: a stage change; an entry that reports an act on the day the source or its own sentence gives; and a decision, a published scorecard event on a row at or under the record's county, that reports an act. Under the months: a statement that names this record, a figure another source gave about it, matched by place and developer, an entry dated only by the day its source was published, and an entry or a decision that describes rather than reports an act. Each is on the record in its own right and keeps its own link.
For researchers
- Stage
- approved
- Events on the timeline
- 1
- Under the months
- 14
- Stage changes
- 1
- Decisions
- 0
- Statements
- 6
- Figures
- 3
- Entries and decisions under the months
- 5