Stream Data Centers lists Stream Data Centers - Chicago I at 2080 Lunt Ave, Elk Grove Village, IL on its interconnection and facility directory. [1] Filings on the record specify 2 planned or operational buildings. [2] Verified facility status from primary Illinois EPA permit, municipal zoning docket, or operator campus specification. [2]
How much power it needs, how much water it would use and who would use it have not been disclosed.
Connected government officials, corporate entities, utilities and local rules on the public record.
Citizen privacy standard: Elected officials, corporate applicants and utility executives are named in full. Private residents who speak at public comment are cited as Resident First L. unless they hold public office or speak on behalf of an organization.
Disclosed engineering ceilings, reported actuals and primary regulatory basis for Stream Data Centers Chicago Campus (Chicago I / II Elk Grove Village).
| Field / Parameter | Permitted / Disclosed Ceiling | Reported Actual | Basis & Primary Source |
|---|---|---|---|
| Electrical Capacity (MW) | |||
| Site Footprint (Acres) | |||
| Data Hall Buildings | 2 buildings | 2 | operator page [2] streamdatacenters.com |
| Cooling & Water System | |||
| Backup Diesel / Gas Generators | |||
| Tax Abatement & Annual Revenue |
Blank cell: not disclosed by any source on file.
The record adds each the day a source gives it. Why these documents.
Acts of Cook County and Elk Grove Village about data centers, on the record with their source. A rule about the area is not a decision about this record.
| Date | Who | Decision | Source |
|---|---|---|---|
| Chicago | Alderman Bill Conway introduced an ordinance that would add additional regulations for data centers and ban them in some districts, though it stops short of a citywide moratorium. | blockclubchicago.org (opens in a new tab) | |
| Chicago | Mayor Brandon Johnson introduced an ordinance to Chicago City Council to pause construction of any new data center for 12 months and block material expansion of existing ones. | blockclubchicago.org (opens in a new tab) | |
| Chicago | Chicago Mayor Brandon Johnson proposed a one year moratorium on new data center construction to develop new regulations on zoning, water and power usage, and quality of life for residents. | nbcchicago.com (opens in a new tab) | |
| Chicago | Chicago Mayor Brandon Johnson announces a city wide temporary moratorium on data center development and expansion for 12 months while the city develops a comprehensive regulatory framework | talkingpointsmemo.com (opens in a new tab) | |
| Chicago | Mayor Johnson's executive order last month called for a moratorium while the city develops a regulatory framework for data centers | yahoo.com (opens in a new tab) | |
| Chicago | Chicago Mayor Brandon Johnson and aldermen Maria Hadden, Leni Manaa Hoppenworth and Lamont Robinson introduced an ordinance to pause data center development and material expansion for one year | yahoo.com (opens in a new tab) |
| Date | Who | Decision | Source |
|---|---|---|---|
| Chicago | Chicago executive order provided for enhanced evaluation of air pollution control permits, data center specific noise rules, and cross departmental review process for planned developments including data centers | thecentersquare.com (opens in a new tab) | |
| Chicago | Mayor Brandon Johnson issued an executive order last month to regulate data centers and called on the city council to pass a moratorium on new data centers | thecentersquare.com (opens in a new tab) | |
| Cicero | Chicagoland suburbs suing data center companies; Cicero mobilizing legal challenge to Digital Realty Hawthorne development | therealdeal.com (opens in a new tab) | |
| Chicago | Mayor Johnson called for a temporary moratorium on new data centers | springfieldnewssun.com (opens in a new tab) | |
| Chicago | Mayor Brandon Johnson signed an executive order creating stricter data center regulations and oversight | springfieldnewssun.com (opens in a new tab) | |
| Cook County | More than a dozen data centers near O'Hare airport received local property tax breaks in 2026. | abc7chicago.com (opens in a new tab) | |
| Cicero | Cicero trustees passed a resolution opposing data center development at Hawthorne in neighboring Stickney | chicago.suntimes.com (opens in a new tab) | |
| Stickney | Stickney board of trustees voted unanimously to block any data center proposals with a moratorium on zoning changes and approvals for data centers | chicago.suntimes.com (opens in a new tab) | |
| Cook County | Mayor Brandon Johnson was pressured by anti data center activists at a rally | chicagotribune.com (opens in a new tab) | |
| Chicago | The working group report recommended the city create a new program for issuing noise and air pollution permits and enhancing environmental review | news.wttw.com (opens in a new tab) | |
| Chicago | A city working group on sustainable data centers spent over a year and a half developing recommendations, with report released in July 2026 | news.wttw.com (opens in a new tab) | |
| Chicago | Mayor Brandon Johnson issued an executive order calling on Chicago City Council to pause new data center construction | news.wttw.com (opens in a new tab) | |
| Chicago | Chicago City Council voted near unanimously on an ordinance incentivizing data center development | news.wttw.com (opens in a new tab) | |
| Cook County | Mayor Brandon Johnson pushed new rules and moratorium on new data centers | axios.com (opens in a new tab) | |
| Chicago | Mayor Brandon Johnson called for a temporary moratorium on data centers | cbsnews.com (opens in a new tab) | |
| Chicago | Chicago Mayor Brandon Johnson signed an executive order for stricter data center regulations | cbsnews.com (opens in a new tab) | |
| Chicago | Johnson's executive order last month added some regulations surrounding noise and air pollution for data centers. | blockclubchicago.org (opens in a new tab) | |
| Chicago | Johnson created a task force in August via an executive order to establish a regulatory framework for data centers in Chicago. | blockclubchicago.org (opens in a new tab) | |
| Hoffman Estates | Karis Critical withdrew rezoning request for data center in Hoffman Estates | datacenterdynamics.com (opens in a new tab) | |
| Hoffman Estates | Developer withdrew rezoning request for data center in Hoffman Estates | capitolnewsillinois.com (opens in a new tab) |
Chronological regulatory, corporate and permitting events on the record, newest first.
No dated entry is on the record yet.
Read on October 26, 2026 (the day the page was read; it gives no date of its own)
Verified facility status from primary Illinois EPA permit, municipal zoning docket, or operator campus specification.
Verified data center records in Illinois within 60 miles by straight line distance.
| Facility & Location | Distance | Stage | Operator / Tenant | Disclosed Scale |
|---|---|---|---|---|
| EdgeConneX Chicago Campus (CHI01 / CHI02) Elk Grove Village, Cook County | Less than 1 mi | Running | EdgeConneX | 2 buildings |
| Equinix Elk Grove Village Campus (CH3 / CH5) Elk Grove Village, Cook County | Less than 1 mi | Running | Equinix | 2 buildings |
| Stream Data Centers Chicago II (Elk Grove Village) Elk Grove Village, Cook County | Less than 1 mi | Running | Stream Data Centers | |
| Stream Data Centers Chicago III (Elk Grove Village) Elk Grove Village, Cook County | Less than 1 mi | Running | Stream Data Centers | 1 building |
| STACK Infrastructure Elk Grove Village (CHI01 / CHI02) Elk Grove Village, Cook County | Less than 1 mi | Running | STACK Infrastructure | 2 buildings |
| H5 Data Centers Chicago Elk Grove Village, Cook County | Less than 1 mi | Running | H5 Data Centers | 1 building |
Blank cell: not disclosed by any source on file.
Answered directly from the verified filings and local actions on this page.
Stream Data Centers is the developer. No construction contractor is named on the record yet.
Power: not disclosed by any source on file. Water: not disclosed by any source on file.
It is running; the date it reached that stage is not sourced, only the day a page was read. No dated entry is on the record yet.
Chicago (rated case by case): Alderman Bill Conway introduced an ordinance that would add additional regulations for data centers and ban them in some districts, though it stops short of a citywide moratorium (September 23, 2026, blockclubchicago.org (opens in a new tab)); and Chicago: Mayor Brandon Johnson introduced an ordinance to Chicago City Council to pause construction of any new data center for 12 months and block material expansion of existing ones (September 23, 2026, blockclubchicago.org (opens in a new tab)). 26 events are on the county's rows; a rule about the area is not a decision about this record.
2 sources on file.
This site is in the RFC West (RFCW) regional power market.
Every number on this page comes from a named source. Click any source to open the document in a new tab.
If a link has moved or a document has changed, let us know and we will update the record and log the change.
Every record on this page carries its sources and the date it was last verified. When you cite it in a story, a study or a public filing, link to this page and give the date you accessed it.
Data Center Record. Stream Data Centers Chicago Campus (Chicago I / II Elk Grove Village). Last verified November 6, 2026. https://datacenterrecord.org/projects/stream-data-centers-chicago-i-elk-grove-village-il. Accessed November 17, 2026.
Every row on this page is available to download with its source, its basis and the date it was last verified.
Download this page's records (CSV) JSON
Licensed CC BY-NC 4.0. Say where it came from and do not sell it or use it to train a commercial model without a license.
Free to use and republish with attribution for reporting, research, teaching and public filings under CC BY-NC 4.0. Commercial, enterprise, financial or AI training use needs a commercial license.
Data Center Record takes no money from data center developers, operators, utilities or trade groups. That rule does not change for licensing.
Data Center Record is an independent project and takes no money from data center developers, operators, utilities or trade groups. Reader support keeps the record free to read, with no ads and no paywall.
Last verified , first recorded . Every correction is logged on the corrections page. Report a correction · Send a tip about Stream Data Centers Chicago Campus (Chicago I / II Elk Grove Village)
Data Center Record, "Stream Data Centers Chicago Campus (Chicago I / II Elk Grove Village)", https://datacenterrecord.org/projects/stream-data-centers-chicago-i-elk-grove-village-il. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.