Projects / QTS Clinton Data Center / Timeline

QTS Clinton Data Center, in order

What happened with this project, oldest first: the stages it reached, what the county and its cities decided, and every dated step on the record. Each entry links its source.

1 event, August 29, 2026 to August 29, 2026. Also on the record, under the month each belongs to: 4 statements, 1 figure from another source and 1 line that is not an event of its own. The facts, newest first: the record; the place: Iowa.

A plain date is the day it happened, as the source states it, or as the line's own sentence states it ("voted on July 6"), which is where the line sits even when it was filed later. "Reported" and a date is the day a source published a line that carries no date of its own. Those lines, and lines that describe rather than report an act, sit under their month rather than on the timeline, with what was said and the figures other sources gave. Every timeline on the site reads its lines by this one rule. How dates are read.

Stages

  1. reported

Now: reported. A stage is the record's status after the entry that set it (the definitions).

2026 1 event

  1. (source date; the content gives no date of its own)

    reported

    QTS proposes a 1,100 acre hyperscale data center estimated to cost 10 billion dollars between Clinton Municipal Airport, Valley Oaks Golf Course and Branden Hills residential area [2]

  2. Also in August 2026: 1 statement and 1 line that is not an event of its own
    1. (source date; the content gives no date of its own)

      Entry

      QTS is currently constructing a data center on 612 acres in Cedar Rapids at the Big Cedar Industrial Center [2]

    2. (said in the source itself)

      Statement · Clintonians Against Data Centers

      Clintonians Against Data Centers raised concerns about displacement of wildlife, local job creation, tax abatement, water usage, and effects on wildlife at the proposed QTS Clinton data center WVIK, Quad Cities NPR local outlet

  3. Also in September 2026: 3 statements and 1 figure from another source
    1. (said in the source itself)

      Statement · Robbie Bahr

      Free concert and peaceful protest scheduled for Sunday, September 13 from 2 to 10 p.m. at Riverview Bandshell in opposition to data center cbs2iowa.com local outlet

    2. (said in the source itself)

      Statement · Robbie Bahr, former concert promoter and Clinton resident

      Robbie Bahr called for a moratorium of roughly 500 to 600 days to allow additional study and public discussion cbs2iowa.com local outlet

    3. (source date; the content gives no date of its own)

      Figure · cbs2iowa.com

      10,000,000,000 dollars: QTS project investment estimated at up to $10 billion cbs2iowa.com local outlet

    4. (said in the source itself)

      Statement · Robbie Bahr

      NO Data Center Concert organized by Robbie Bahr held in protest on September 13 from 2 to 10 p.m. at Clinton, Iowa Bandshell quadcities.com local outlet

On the timeline: a stage change; an entry that reports an act on the day the source or its own sentence gives; and a decision, a published scorecard event on a row at or under the record's county, that reports an act. Under the months: a statement that names this record, a figure another source gave about it, matched by place and developer, an entry dated only by the day its source was published, and an entry or a decision that describes rather than reports an act. Each is on the record in its own right and keeps its own link.

For researchers
Slug
qts-clinton-data-center-ia
Status value
rumored
Events on the timeline
1
Under the months
6
Stage changes
1
Decisions
0
Statements
4
Figures
1
Entries and decisions under the months
1