QTS Blakely, in order
What happened with this project, oldest first: the stages it reached, what the county and its cities decided, and every dated step on the record. Each entry links its source.
2 events, August 22, 2026 to September 14, 2026. Also on the record, under the month each belongs to: 2 figures from other sources and 2 lines that are not events of their own. The facts, newest first: the record; the place: Georgia.
A plain date is the day it happened, as the source states it, or as the line's own sentence states it ("voted on July 6"), which is where the line sits even when it was filed later. "Reported" and a date is the day a source published a line that carries no date of its own. Those lines, and lines that describe rather than report an act, sit under their month rather than on the timeline, with what was said and the figures other sources gave. Every timeline on the site reads its lines by this one rule. How dates are read.
Stages
2026 2 events
-
(source date; the content gives no date of its own)
proposed
QTS Data Centers will invest at least $28.75 million in community betterment fund for Blakely and Early County Georgia data center development [3]
-
Also in August 2026: 2 figures from other sources and 2 lines that are not events of their own
-
(source date; the content gives no date of its own)
Entry
Data center campus will use closed loop cooling system that consumes no water for cooling once operational [3]
-
(source date; the content gives no date of its own)
Entry
QTS will make $7.5 million annual payments for three years beginning in December 2026 before construction starts [3]
-
(source date; the content gives no date of its own)
Figure · Construction Owners
4,500,000 to 12,500,000 dollars a year: QTS expects $4.5 million to $12.5 million annual payments per building once operational Construction Owners local outlet
-
(source date; the content gives no date of its own)
Figure · Construction Owners
60,000,000 to 85,000,000 dollars a year: QTS expects annual payments of $60 million to $85 million once data center buildings become operational based on current site plan Construction Owners local outlet
-
-
(the day the page was read; it gives no date of its own)
being built
QTS Data Centers lists QTS Blakely at Blakely, Georgia on its own page of data center locations, read September 14, 2026. [1]
On the timeline: a stage change; an entry that reports an act on the day the source or its own sentence gives; and a decision, a published scorecard event on a row at or under the record's county, that reports an act. Under the months: a statement that names this record, a figure another source gave about it, matched by place and developer, an entry dated only by the day its source was published, and an entry or a decision that describes rather than reports an act. Each is on the record in its own right and keeps its own link.
For researchers
- Slug
- qts-blakely-ga
- Status value
- under_construction
- Events on the timeline
- 2
- Under the months
- 4
- Stage changes
- 2
- Decisions
- 0
- Statements
- 0
- Figures
- 2
- Entries and decisions under the months
- 2