PPL Archbald data center power plants

PPL completed a land deal in Archbald to pave the way for massive data center power plants. It is reported; the record holds no sourced date for when it reached that stage.

How much power it needs, how much water it would use and who would use it have not been disclosed.

Last verified · 3 sources, 0 primary · A skeleton record: built from one source, not yet reviewed in depth by a person. · How to read this page

How to read this page. Every fact links to the source it rests on; a number in brackets is its place in the source list. A figure no source gives reads Not disclosed, and nothing is estimated. Where sources give different figures, each is shown with who gave it, and another source's figure never stands in for the record's own. Entries are added and never overwritten; corrections are listed under What happened.

What is known

Each figure as its source gave it. The number in brackets is its place in the source list.

Land
500 acres
third party estimate [1]
Power it would draw
Not disclosed
Water
Not disclosed
Who leads it
PPL
as stated by the source
Who would use it
Not disclosed
Jobs once it runs
Not disclosed
Tax each year
Not disclosed
Where its power comes from
potential power plants for data centers
as stated by the source [1]
Every field, with who said it and when (Researcher view)

Impact figures

FieldValueWho says soSourceLast verified
How much power it needs Not disclosed
How much water it would use Not disclosed
How loud it would be Not disclosed
Jobs once it runs Not disclosed
Tax it would pay each year Not disclosed

The record's fields

FieldValueWho says soSourceLast verified
Who is building it PPL as stated by the source September 25, 2026
Who is constructing it Not disclosed
How much land 500 acres third party estimate [1] finance.yahoo.com September 25, 2026
Where its power comes from potential power plants for data centers as stated by the source [1] finance.yahoo.com September 25, 2026
Grid connection Not disclosed
How it is cooled Not disclosed

The developer's figure is what the company said; what a permit allows is the ceiling a permit sets; measured means observed. Water is in gallons a day or a year, whichever the source stated; a tax claim given as a range shows both ends, each linked to the source that gave it.

Still not public, and where it would show up

The record adds each the day a source gives it. Why these documents.

  • Water useA state water right filing or a water supply agreement.
  • Who would use itA lease announcement or a tenant named in a filing.
  • Power the campus would drawA utility or public service commission docket, an interconnection filing, or an air permit for an on site plant.
  • Jobs and taxAn incentive agreement, a county's economic development filing or a fiscal note.

What was decided

Acts of Lackawanna County and Archbald about data centers, on the record with their source. A rule about the area is not a decision about this record.

DateWhoDecisionSource
Lackawanna County case by case Lackawanna County Commissioners approved contract for AI data center health impact study paenvironmentdaily.blogspot.com
Lackawanna County case by case Lackawanna County is conducting an air quality and public health impact assessment study for data center and power plant development. thetimes-tribune.com

What happened

No dated entry is on the record yet.

3 corrections to this record

Every correction, with its reason
  1. · the speaker role of a statements row

    Speaker read again from the statement's source line, "Governor Josh Shapiro, Pennsylvania": the title in front of the name (Governor) is the role, not part of the name. The old and new text.

  2. · the speaker of a statements row

    Speaker read again from the statement's source line, "Governor Josh Shapiro, Pennsylvania": the title in front of the name (Governor) is the role, not part of the name. The old and new text.

  3. · the kind of source of a history entry

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of 2026-09-23). The link did not change. The day's label corrections.

Every correction on the record is on the corrections page.

What was said

Governor Josh Shapiro mentioned his visit to Archbald ahead of signing an executive order reining in large scale data center development
Josh Shapiro, Governor, Pennsylvania · August 21, 2026 · paraphrased · The Allegheny Front local outlet

Every statement about data centers in Pennsylvania, by speaker

The site

Where in Lackawanna County is not in the public record. The pin marks the county seat, not a building, and the outline is the county.

  • This record: Proposed, ringed
  • data center
  • Dashed edge: the exact site is not in the public record
  • Smaller pins: 19 other published records in Pennsylvania
Details
  • this record's location, ringed
  • parcel outline, from the county parcel record
  • city limits, U.S. Census Bureau, on a town level record
  • county boundary

The other pins are the published projects in the same state, each in its stage color. The imagery beneath is the USGS national orthoimagery, public domain, shown so the land around the site can be read.

Where
Archbald, Lackawanna County, Pennsylvania
How exactly it is located
County level, the county seat
The parcel
No parcel outline in the public record
Nearest homes
Not computed for a record placed at a place center
Nearest records
Nearest records are not computed for a record placed at a county seat.

Questions about this project

5 questions answered from the record

Answered from the rows on this page.

How big is PPL Archbald data center power plants?

The record has one measure of its size: 500 acres (third party estimate, source). Its power capacity is not disclosed.

Who is building PPL Archbald data center power plants?

PPL is the developer. No construction contractor is named on the record yet.

How much power and water does PPL Archbald data center power plants say it needs?

Power: not disclosed by any source on file. Water: not disclosed by any source on file.

Where does PPL Archbald data center power plants stand today?

It is reported; the date it reached that stage is not sourced, only the day a page was read. No dated entry is on the record yet.

What has Archbald or Lackawanna County decided about it?

Lackawanna County (rated case by case): Lackawanna County Commissioners approved contract for AI data center health impact study (reported September 17, 2026, source); and Lackawanna County: Lackawanna County is conducting an air quality and public health impact assessment study for data center and power plant development. (reported September 6, 2026, source). 2 events are on the county's rows; a rule about the area is not a decision about this record.

Sources

Primary documents first: filings, minutes, dockets and official pages. Then reporting. The numbers are the ones the entries above cite.

Reporting

  1. PPL (PPL) And Blackstone Buy 500 Acres For Potential Data Center Power Plants, finance.yahoo.com, August 17, 2026, local outlet
  2. Lackawanna County Commissioners hire firm to study environmental and health impacts of data centers and power plants, www.wvia.org, September 16, 2026, local outlet
  3. PPL land deal in Archbald, Upvalley paves way for massive data center power plants [Updated] - Scranton Times-Tribune, Scranton Times-Tribune, August 30, 2026, local outlet

3 sources on file.

Cite this record

Data Center Record, "PPL Archbald data center power plants", https://datacenterrecord.org/projects/ppl-archbald-data-center-power-plants-pa, last verified September 25, 2026.

Last verified , first recorded . Every correction is logged on the corrections page and under What happened.

Cite this page

Data Center Record, "PPL Archbald data center power plants", https://datacenterrecord.org/projects/ppl-archbald-data-center-power-plants-pa. Data: Data Center Record, datacenterrecord.org, CC BY 4.0.

The structured rows are CC BY 4.0. Link to this page; that is what turns a reuse into a citation. Prose stays under copyright.

Report a change
For researchers
Slug
ppl-archbald-data-center-power-plants-pa
Status value
rumored
Stage
Proposed
Tier
skeleton
Tags
skeleton
Place id
us/pa/lackawanna-county/archbald
Coordinates
41.40897, -75.66241
Location precision
county
Location source
County seat (Scranton), Wikidata, placed at county level
Coordinate source
wikidata county seat
Location source number
Not disclosed
Location last verified
September 16, 2026
EPA registry id
Not disclosed
Use type values
not_disclosed
Tenancy value
not_disclosed
Cooling type value
not_disclosed
Capacity basis
not_disclosed
Water basis
not_disclosed, gallons_per_day
Acreage basis
third_party_estimate
Interconnection value
not_disclosed
Capacity, if disclosed
Not disclosed
Rating of the county's rows
Case by case
Published
2026-09-04
Last verified
2026-09-25