Point Pleasant Data Center, in order

What happened with this project, oldest first: the stages it reached, what the county and its cities decided, and every dated step on the record. Each entry links its source.

1 event, May 2, 2026. Also on the record, under the month each belongs to: 2 statements and 3 figures from other sources. The facts, newest first: the record; the place: West Virginia.

A plain date is the day it happened, as the source states it, or as the line's own sentence states it ("voted on July 6"), which is where the line sits even when it was filed later. "Reported" and a date is the day a source published a line that carries no date of its own. Those lines, and lines that describe rather than report an act, sit under their month rather than on the timeline, with what was said and the figures other sources gave. Every timeline on the site reads its lines by this one rule. How dates are read.

Stages

  1. reported

Now: reported. A stage is the record's status after the entry that set it (the definitions).

2026 1 event

  1. (source date; the content gives no date of its own)

    reported

    Point Pleasant data center has 3 buildings with nearly 1,000 natural gas and diesel engines [1]

  2. Also in August 2026: 1 statement and 3 figures from other sources
    1. (said in the source itself)

      Statement · Morgan King, climate and energy program manager, West Virginia Citizen Action Group

      Morgan King of West Virginia Citizen Action Group expressed grave concerns about air pollutants from the natural gas plant and generators herald-dispatch.com (opens in a new tab) local outlet

    2. (source date; the content gives no date of its own)

      Figure · herald-dispatch.com

      2.5 MW: Each generator will produce 2.5 megawatts of electricity herald-dispatch.com (opens in a new tab) local outlet

    3. (source date; the content gives no date of its own)

      Figure · herald-dispatch.com

      864 engines: Facility will have 864 reciprocating internal combustion engines herald-dispatch.com (opens in a new tab) local outlet

    4. (source date; the content gives no date of its own)

      Figure · herald-dispatch.com

      2.16 GW: Facility will have 2.16 gigawatts capacity herald-dispatch.com (opens in a new tab) local outlet

  3. Also in September 2026: 1 statement
    1. (said in the source itself)

      Statement · Ro Khanna, U.S. Representative

      Rep. Ro Khanna proposed a Data Center Bill of Rights that would ban construction within 2,500 feet of a home huffpost.com (opens in a new tab) national outlet

On the timeline: a stage change; an entry that reports an act on the day the source or its own sentence gives; and a decision, a published scorecard event on a row at or under the record's county, that reports an act. Under the months: a statement that names this record, a figure another source gave about it, matched by place and developer, an entry dated only by the day its source was published, and an entry or a decision that describes rather than reports an act. Each is on the record in its own right and keeps its own link.

For researchers
Stage
reported
Events on the timeline
1
Under the months
5
Stage changes
1
Decisions
0
Statements
2
Figures
3