Projects / PAX-1 Data Center / Timeline

PAX-1 Data Center, in order

What happened with this project, oldest first: the stages it reached, what the county and its cities decided, and every dated step on the record. Each entry links its source.

4 events, January 30, 2025 to September 3, 2026. Also on the record, under the month each belongs to: 2 statements, 1 figure from another source and 1 date when a source page was read and verified. The facts, newest first: the record; the place: Pennsylvania.

A plain date is the day it happened, as the source states it, or as the line's own sentence states it ("voted on July 6"), which is where the line sits even when it was filed later. "Reported" and a date is the day a source published a line that carries no date of its own. Those lines, and lines that describe rather than report an act, sit under their month rather than on the timeline, with what was said and the figures other sources gave. Every timeline on the site reads its lines by this one rule. How dates are read.

Stages

  1. waiting on permits
  2. reported
  3. stalled
  4. waiting on permits

Now: waiting on permits. A stage is the record's status after the entry that set it (the definitions).

2025 1 event

  1. (content date)

    waiting on permits

    The Pennsylvania DEP received the project's first permit application on January 30, 2025; its tracker lists the project as permits under review (21 permits: 9 issued, 4 pending, 8 not yet submitted). [1]

2026 3 events

  1. Also in July 2026: 2 statements and 1 figure from another source
    1. (said in the source itself)

      Statement · Greg Rothman, Pennsylvania state senator

      Rothman stated he had nothing to do with the actual data center deal but RSR Realtors received real estate fee for sale of land Spotlight PA (opens in a new tab) local outlet

    2. (said in the source itself)

      Statement · Greg Rothman, Pennsylvania state senator

      Pennsylvania state senator Greg Rothman made money from 30 million dollar sale of property in June 2025 to PAX-1 data center developer Spotlight PA (opens in a new tab) local outlet

    3. (source date; the content gives no date of its own)

      Figure · Spotlight PA

      15,000,000,000 dollars: PAX-1 is slated to be three campus 15 billion dollar facility with capacity of 1.35 gigawatts Spotlight PA (opens in a new tab) local outlet

  2. (source date; the content gives no date of its own)

    reported

    The PAX-1 data center project in Cumberland County does not have all the necessary permits to operate [4]

  3. Also in August 2026: 1 date when a source page was read and verified
    1. (source date; the content gives no date of its own)

      Entry

      The 700 acre PAX-1 property is located off Country Club Road and construction crews have already begun moving dirt [4]

  4. (content date)

    stalled

    A judge granted a partial victory to opponents of a data center in Cumberland County. pennlive.com (opens in a new tab) local outlet

  5. (content date)

    waiting on permits

    Middlesex Township supervisors approved PAX-1 data center development matters. cumberlink.com (opens in a new tab) news outlet

On the timeline: a stage change; an entry that reports an act on the day the source or its own sentence gives; and a decision, a published scorecard event on a row at or under the record's county, that reports an act. Under the months: a statement that names this record, a figure another source gave about it, matched by place and developer, an entry dated only by the day its source was published, and an entry or a decision that describes rather than reports an act. Each is on the record in its own right and keeps its own link.

For researchers
Stage
waiting on permits
Events on the timeline
4
Under the months
4
Stage changes
4
Decisions
0
Statements
2
Figures
1