Data Center Record.
Projects / Oregon data center (Oregon, Lucas County) / Timeline

Oregon data center (Oregon, Lucas County), in order

What happened with this project, oldest first: the stages it reached, what the county and its cities decided, and every dated step on the record. Each entry links its source.

1 event, August 17, 2026. Also on the record, under the month each belongs to: 54 figures from other sources. The facts, newest first: the record; the place: Ohio.

A plain date is the day it happened, as the source states it, or as the line's own sentence states it ("voted on July 6"), which is where the line sits even when it was filed later. "Reported" and a date is the day a source published a line that carries no date of its own. Those lines, and lines that describe rather than report an act, sit under their month rather than on the timeline, with what was said and the figures other sources gave. Every timeline on the site reads its lines by this one rule. How dates are read.

Stages

  1. proposed

Now: proposed. A stage is the record's status after the entry that set it (the definitions).

2025 7 under the months

  1. Also in January 2025: 1 figure from another source
    1. (content date)

      Figure · Mashable SEA

      23 percent: Data centers accounted for 23 percent of Oregon's retail energy sales in 2025 Mashable SEA (opens in a new tab) national outlet

  2. Also in August 2025: 6 figures from other sources
    1. (source date; the content gives no date of its own)

      Figure · bendbulletin.com

      275,000,000 USD: Oregon schools collectively lost $275 million to property tax abatements in 2024 bendbulletin.com (opens in a new tab) local outlet

    2. (source date; the content gives no date of its own)

      Figure · bendbulletin.com

      125,000,000 USD: Oregon schools lost $125 million to property tax abatements in 2019 bendbulletin.com (opens in a new tab) local outlet

    3. (source date; the content gives no date of its own)

      Figure · bendbulletin.com

      60,000,000 USD: Between 2019 and 2024, tax savings for businesses benefiting from enterprise zones increased by $60 million, or 185 percent bendbulletin.com (opens in a new tab) local outlet

    4. (source date; the content gives no date of its own)

      Figure · bendbulletin.com

      10,000,000 USD: Crook County Schools gave up $10 million in local revenue to property tax exemptions in 2019 bendbulletin.com (opens in a new tab) local outlet

    5. (source date; the content gives no date of its own)

      Figure · bendbulletin.com

      29,000,000 USD: Crook County Schools gave up $29 million in local revenue to property tax exemptions in 2024 bendbulletin.com (opens in a new tab) local outlet

    6. (source date; the content gives no date of its own)

      Figure · bendbulletin.com

      2,000,000 USD: Meta has donated more than $2 million to Central Oregon's Crook County School District during the last decade bendbulletin.com (opens in a new tab) local outlet

2026 1 event

  1. Also in January 2026: 1 figure from another source
    1. (content date)

      Figure · OPB (via Google News)

      400,000,000 dollars: Data centers in Oregon received more than $400 million in tax breaks in 2026 OPB (via Google News) (opens in a new tab) local outlet

  2. Also in July 2026: 1 figure from another source
    1. (content date)

      Figure · OPB (via Google News)

      71 percent: DHM Research poll found 71% of Oregonians have negative view of data centers in late July 2026 OPB (via Google News) (opens in a new tab) local outlet

  3. (content date)

    proposed

    Oregon residents gathered signatures for a ballot measure to limit data center size in the city charter, with the Lucas County Board of Elections validating the required signatures on August 10, 2026. [2]

  4. Also in August 2026: 3 figures from other sources
    1. (source date; the content gives no date of its own)

      Figure · Oregon Capital Chronicle

      400,000,000 USD: Data centers in Oregon received more than $400 million in tax breaks this year Oregon Capital Chronicle (opens in a new tab) local outlet

    2. (source date; the content gives no date of its own)

      Figure · Oregon Capital Chronicle

      71 percent: 71% of Oregonians have a negative view of data centers, per DHM Research poll Oregon Capital Chronicle (opens in a new tab) local outlet

    3. (source date; the content gives no date of its own)

      Figure · Oregon Capital Chronicle

      67 percent: 67% of Oregonians polled support a temporary halt on data center construction across the state Oregon Capital Chronicle (opens in a new tab) local outlet

  5. Also in September 2026: 41 figures from other sources
    1. (source date; the content gives no date of its own)

      Figure · Willamette Week

      457,000,000 dollars a year: Tax Fairness Oregon says the state has given $457 million in data center tax breaks this year Willamette Week (opens in a new tab) local outlet

    2. (source date; the content gives no date of its own)

      Figure · Willamette Week

      70 percent: The latest national polling shows opposition to data centers at rates north of 70% Willamette Week (opens in a new tab) local outlet

    3. (source date; the content gives no date of its own)

      Figure · Willamette Week

      142 facilities: According to Pew Research, the state now has 142 data centers: 115 in operation and 27 in development, ranking Oregon ninth in overall footprint in the U.S. Willamette Week (opens in a new tab) local outlet

    4. (source date; the content gives no date of its own)

      Figure · opb.org

      125 count: There are about 125 data centers in Oregon opb.org (opens in a new tab) local outlet

    5. (source date; the content gives no date of its own)

      Figure · Oregon Capital Chronicle

      450,000,000 dollars: Data centers expected to receive at least 450 million dollars in property tax breaks this year Oregon Capital Chronicle (opens in a new tab) local outlet

    6. (source date; the content gives no date of its own)

      Figure · Oregon Capital Chronicle

      144 count: Estimated 144 data centers in Oregon, nearly twice as many in eastern part of state as in west Oregon Capital Chronicle (opens in a new tab) local outlet

    7. (source date; the content gives no date of its own)

      Figure · kptv.com

      29 percent: POWER Act raised electricity rates for data center corporations by 29 percent while lowering rates for other Portland General Electric customers kptv.com (opens in a new tab) local outlet

    8. (source date; the content gives no date of its own)

      Figure · Bond Buyer

      29 percent: The POWER Act resulted in a 29% increase in electricity rates on data center corporations and rate decreases for all other ratepayers served by Portland General Electric Bond Buyer (opens in a new tab) news outlet

    9. (source date; the content gives no date of its own)

      Figure · Albany Democrat-Herald

      144 count: An estimated 144 data centers are operating in Oregon, with nearly twice as many in the eastern part of the state as in the west. Albany Democrat-Herald (opens in a new tab) local outlet

    10. (source date; the content gives no date of its own)

      Figure · Albany Democrat-Herald

      450,000,000 dollars: Data centers will receive at least 450 million dollars in property tax breaks this year in Oregon. Albany Democrat-Herald (opens in a new tab) local outlet

    11. (source date; the content gives no date of its own)

      Figure · yahoo.com

      450,000,000 USD: Oregon data center tax breaks total more than $450 million annually yahoo.com (opens in a new tab) national outlet

    12. (source date; the content gives no date of its own)

      Figure · yahoo.com

      2,100 acres: Oregon currently occupies more than 2,100 acres with data centers and has 9,000 more acres planned yahoo.com (opens in a new tab) national outlet

    13. (source date; the content gives no date of its own)

      Figure · KATU

      100 count: Oregon has more than 100 data centers with about 30 more planned KATU (opens in a new tab) local outlet

    14. (source date; the content gives no date of its own)

      Figure · Oregon Capital Chronicle

      25 facilities: Oregon had eight data storage facilities 25 years ago, up from current count of 123 to 144 Oregon Capital Chronicle (opens in a new tab) local outlet

    15. (source date; the content gives no date of its own)

      Figure · Oregon Capital Chronicle

      31 facilities: Of 31 data centers in siting process in Oregon, 8 are hyperscale facilities for large scale data storage and AI processing Oregon Capital Chronicle (opens in a new tab) local outlet

    16. (source date; the content gives no date of its own)

      Figure · Oregon Capital Chronicle

      123 to 144 facilities: Oregon hosts between 123 and 144 data center facilities according to ECOnorthwest analysis Oregon Capital Chronicle (opens in a new tab) local outlet

    17. (source date; the content gives no date of its own)

      Figure · Oregon Capital Chronicle

      9,000 acres: Approximately 9,000 acres proposed for data center development in Oregon Oregon Capital Chronicle (opens in a new tab) local outlet

    18. (source date; the content gives no date of its own)

      Figure · Mashable SEA

      2,630 jobs: Oregon data centers directly employ 2,630 workers Mashable SEA (opens in a new tab) national outlet

    19. (source date; the content gives no date of its own)

      Figure · Mashable SEA

      6,900,000 square feet: 32 additional data centers are under construction or planning, occupying 6.9 million square feet Mashable SEA (opens in a new tab) national outlet

    20. (source date; the content gives no date of its own)

      Figure · Mashable SEA

      22,100,000 square feet: Oregon has 111 operational data centers occupying 22.1 million square feet Mashable SEA (opens in a new tab) national outlet

    21. (source date; the content gives no date of its own)

      Figure · Yahoo

      20 percent of retail electricity sales: Data center facilities account for more than 20% of retail electricity sales in Oregon. Yahoo (opens in a new tab) national outlet

    22. (source date; the content gives no date of its own)

      Figure · WTOC

      4 multiple: Data center electricity consumption has nearly quadrupled since 2020. WTOC (opens in a new tab) local outlet

    23. (source date; the content gives no date of its own)

      Figure · WTOC

      14 terawatt-hours per year: Data centers in Oregon consumed more than 14 terawatt hours of electricity last year. WTOC (opens in a new tab) local outlet

    24. (source date; the content gives no date of its own)

      Figure · About Amazon

      242,000,000 gallons a year: Amazon data centers in Eastern Oregon used 242 million gallons of water in 2025 About Amazon (opens in a new tab) news outlet

    25. (source date; the content gives no date of its own)

      Figure · NPR for Oregonians

      292,000 USD: Think Big PAC, an affiliate of Leading the Future funded by leaders from OpenAI and other prominent tech companies, spent $292,000 in independent expenditures in May in support of Val Hoyle in the primary NPR for Oregonians (opens in a new tab) local outlet

    26. (source date; the content gives no date of its own)

      Figure · polkio.com

      123 to 144 facilities: Oregon hosts between 123 and 144 data center facilities according to ECOnorthwest analysis, up from eight facilities 25 years ago. polkio.com (opens in a new tab) local outlet

    27. (source date; the content gives no date of its own)

      Figure · OPB

      292,000 USD: Think Big PAC, an affiliate of Leading the Future funded by leaders from OpenAI and other tech companies, spent $292,000 in independent expenditures supporting Val Hoyle in the primary OPB (opens in a new tab) local outlet

    28. (source date; the content gives no date of its own)

      Figure · WTOC

      32 count: 32 more data centers are already planned or under construction across Oregon. WTOC (opens in a new tab) local outlet

    29. (source date; the content gives no date of its own)

      Figure · WTOC

      71 percent: Data center electricity consumption is equal to about 71% of all the electricity sold to Oregon homes combined. WTOC (opens in a new tab) local outlet

    30. (source date; the content gives no date of its own)

      Figure · polkio.com

      31 hyperscale data centers: Of 31 data centers in process of siting in Oregon, eight are hyperscale data centers. polkio.com (opens in a new tab) local outlet

    31. (source date; the content gives no date of its own)

      Figure · About Amazon

      957,000,000 gallons a year: Amazon's water replenishment projects in Eastern Oregon will return or improve 957 million gallons of water a year to the local ecosystem About Amazon (opens in a new tab) news outlet

    32. (source date; the content gives no date of its own)

      Figure · About Amazon

      10,000,000,000 gallons: Port of Morrow potable water treatment plants funded by Amazon will provide combined capacity of 10 billion gallons a year, with Amazon using 5% or 455 million gallons, expected completion 2027 About Amazon (opens in a new tab) news outlet

    33. (source date; the content gives no date of its own)

      Figure · Yahoo

      111 count: Oregon has 111 operating data centers. Yahoo (opens in a new tab) national outlet

    34. (source date; the content gives no date of its own)

      Figure · Yahoo

      32 count: Oregon has 32 more data centers planned. Yahoo (opens in a new tab) national outlet

    35. (source date; the content gives no date of its own)

      Figure · polkio.com

      700 written comments: Committee received more than 700 written comments, approximately 90 percent expressing opposition to data centers. polkio.com (opens in a new tab) local outlet

    36. (source date; the content gives no date of its own)

      Figure · About Amazon

      284,000,000 gallons a year: In 2024, all of Amazon's data center operations in Oregon used approximately 284 million gallons of water, or about 4.6% of the total potable and industrial volume produced by the City of Umatilla, City of Hermiston, and Port of Morrow About Amazon (opens in a new tab) news outlet

    37. (source date; the content gives no date of its own)

      Figure · About Amazon

      14,800,000 gallons a day: Columbia River Intake project in Umatilla funded by Amazon will provide up to 23 cubic feet per second or 14.8 million gallons daily, expected completion 2028 About Amazon (opens in a new tab) news outlet

    38. (source date; the content gives no date of its own)

      Figure · WTOC

      111 count: There are 111 data centers in Oregon. WTOC (opens in a new tab) local outlet

    39. (source date; the content gives no date of its own)

      Figure · polkio.com

      9,000 acres: Approximately 9,000 acres proposed for data center development in Oregon. polkio.com (opens in a new tab) local outlet

    40. (source date; the content gives no date of its own)

      Figure · About Amazon

      400,000,000 USD: Amazon is investing $400 million in local water infrastructure projects in Eastern Oregon About Amazon (opens in a new tab) news outlet

    41. (source date; the content gives no date of its own)

      Figure · newportnewstimes.com

      450,000,000 dollars a year: Statewide Oregon data center tax abatements run near 450 million dollars a year newportnewstimes.com (opens in a new tab) news outlet

  6. Also in October 2026: 1 figure from another source
    1. (source date; the content gives no date of its own)

      Figure · Yahoo

      2,000 acres: State data shows Oregon has more than 120 data centers covering more than 2,000 acres, with communities planning for 9,000 more acres Yahoo (opens in a new tab) national outlet

Local jurisdiction rules 1 decision

County and municipal actions on the record in Lucas County, listed separately from this facility's own timeline.

  1. (content date)

    Decision · Oregon (city)

    Oregon voters approved Issue 25, a citizen initiated charter amendment adding Article XIII Section 8 to prohibit construction of a data center above 25 megawatts, on November 3, 2026, voting 4,381 in favor (59.89 percent) to 2,934 against (40.11 percent). ballotpedia.org (opens in a new tab)

On the timeline: a stage change; an entry that reports an act on the day the source or its own sentence gives; and a decision, a published scorecard event on a row at or under the record's county, that reports an act. Under the months: a statement that names this record, a figure another source gave about it, matched by place and developer, an entry dated only by the day its source was published, and an entry or a decision that describes rather than reports an act. Each is on the record in its own right and keeps its own link.

For researchers
Stage
proposed
Events on the timeline
1
Under the months
54
Stage changes
1
Decisions
1
Statements
0
Figures
54
Entries and decisions under the months
0

Researcher view · basis and source tier on every row · docket and Census GEOIDs · citation and export tools

Commercial and bulk data