A plain date is the day it happened, as the source states it, or as the line's own sentence states it ("voted on July 6"), which is where the line sits even when it was filed later. "Reported" and a date is the day a source published a line that carries no date of its own. Those lines, and lines that describe rather than report an act, sit under their month rather than on the timeline, with what was said and the figures other sources gave. Every timeline on the site reads its lines by this one rule. How dates are read.
2026 3 events
-
(the month its own sentence names; no day is given; filed under Jun 1, 2026)
Decision · Monterey Park (city)
Monterey Park voters approved a data center ban in June 2026. pressenterprise.com (opens in a new tab)
-
(the month its own sentence names; no day is given; filed under Sep 14, 2026)
Decision · Monterey Park (city)
Monterey Park voted in June 2026 to permanently ban data centers bisnow.com (opens in a new tab)
-
(the day its own sentence names; filed under Sep 16, 2026)
Decision · Irwindale (city)
Irwindale City Council unanimously approved data center ban Ordinance No. 821 on September 9, 2026, effective 30 days after adoption sgvtribune.com (opens in a new tab)
-
Also in September 2026: 2 lines that are not events of their own
-
(source date; the content gives no date of its own)
Decision · Vernon (city)
Vernon approaching capacity for data center projects, expanding infrastructure bisnow.com (opens in a new tab)
-
(source date; the content gives no date of its own)
Decision · Los Angeles County (county)
Los Angeles County planning director ordered temporary ban on large scale AI data center development in unincorporated areas smartcitiesdive.com (opens in a new tab)
-
On the timeline: a stage change; an entry that reports an act on the day the source or its own sentence gives; and a decision, a published scorecard event on a row at or under the record's county, that reports an act. Under the months: a statement that names this record, a figure another source gave about it, matched by place and developer, an entry dated only by the day its source was published, and an entry or a decision that describes rather than reports an act. Each is on the record in its own right and keeps its own link.
For researchers
- Stage
- not yet verified
- Events on the timeline
- 3
- Under the months
- 2
- Stage changes
- 0
- Decisions
- 5
- Statements
- 0
- Figures
- 0
- Entries and decisions under the months
- 2