Data Center Record.

Proposed Built from one source

Joliet Technology Center

Joliet, Will County, ILDeveloper: PowerHouse Data CentersCensus GEOID 17197

Stage
Proposed
Power
1.8 GW
the developer's figure
Buildings
15 buildings
zoning application, verified October 26, 2026
Undisclosed in public filings
Land, Water

PowerHouse Data Centers developed a 795 acre, 1.8 GW capacity data center campus in Joliet with 24 buildings expected to generate 310 million dollars in property taxes over 30 years. It is approved, since March 24, 2026.

How much water it would use and who would use it have not been disclosed.

Last verified · 5 sources, 0 primary · Built from one source, not yet reviewed in depth by a person. · How to read this page

  • This record: Proposed, ringed
  • data center
  • Smaller pins: 47 other published records in Illinois
Details
  • this record's location, ringed
  • parcel outline, from the county parcel record
  • city limits, U.S. Census Bureau, on a town level record
  • county boundary

The other pins are the published projects in the same state, each in its stage color. The imagery beneath is the USGS national orthoimagery, public domain, shown so the land around the site can be read.

How to read this page. Every fact links to the source it rests on; a number in brackets is its place in the source list. A figure no source gives reads Not disclosed, and nothing is estimated. Where sources give different figures, each is shown with who gave it, and another source's figure never stands in for the record's own. Entries are added and never overwritten; corrections are listed under What happened.

What is known

Each figure as its source gave it. The number in brackets is its place in the source list.

Buildings
15 buildings zoning application, verified October 26, 2026
[1] joliet.gov
Power it would draw
1.8 GW the developer's figure About 0.18 times New York City's summer peak demand in 2024.
[1] joliet.gov
Who leads it
PowerHouse Data Centers as stated by the source
Undisclosed in public filings
Land, Water, Who would use it, Jobs once it runs, Tax each year
The math behind the comparison
  1. Joliet Technology Center, capacity: 1,800 MW.
  2. New York City (NYISO Zone J) summer peak demand, actual, 2024: 10,245 MW (2024).
  3. 1,800 ÷ 10,245 = 0.18 (MW over MW).

Sources:

A comparison is arithmetic on two published rows and is never a new fact (how comparisons are made).

Every field, with who said it and when (Researcher view)

Impact figures

FieldValueWho says soSourceLast verified
How much power it needs 1.8 GW the developer's figure [1] joliet.gov (opens in a new tab) October 26, 2026
How much water it would use
How loud it would be
Jobs once it runs
Tax it would pay each year

The record's fields

FieldValueWho says soSourceLast verified
Who is building it PowerHouse Data Centers as stated by the source October 26, 2026
Who is constructing it
How much land
Buildings 15 buildings zoning application, verified October 26, 2026 [1] joliet.gov (opens in a new tab) October 26, 2026
Where its power comes from
Grid connection
How it is cooled

A blank value cell means not disclosed by any source on file; a blank basis cell means the source gave the figure without saying on what basis.

The developer's figure is what the company said; what a permit allows is the ceiling a permit sets; measured means observed. Water is in gallons a day or a year, whichever the source stated; a tax claim given as a range shows both ends, each linked to the source that gave it.

Still not public, and where it would show up

The record adds each the day a source gives it. Why these documents.

  • Water use A state water right filing or a water supply agreement.
  • Who would use it A lease announcement or a tenant named in a filing.
  • Jobs and tax An incentive agreement, a county's economic development filing or a fiscal note.

What happened

  1. · Status: approved (content date)

    PowerHouse Data Centers developed a 795 acre, 1.8 GW capacity data center campus in Joliet with 24 buildings expected to generate 310 million dollars in property taxes over 30 years.

    [2] datacenterdynamics.com

The full Joliet Technology Center timeline, in order

The site

The pin is the site. The shaded outline is the parcel, from the county's own parcel record.

The site map is at the top of the page.

Where
Bernhard Rd and Rowell Ave, Joliet, IL 60433, Joliet, Will County, Illinois [1] joliet.gov (opens in a new tab)
How exactly it is located
Exact, on the parcel
The parcel
No parcel outline in the public record
Nearest homes
Not computed for a record placed at a place center

USGS NAIP aerial view of Joliet Technology Center
LAT 41.48120 / LON -88.04150 Imagery: U.S. Geological Survey / USDA NAIP (Public Domain)

Questions about this project

5 questions answered from the record

Answered from the rows on this page.

How big is Joliet Technology Center?

The record has 2 measures of its size: 1.8 GW (the developer's figure, joliet.gov (opens in a new tab)) and 15 buildings (zoning application, verified October 26, 2026, joliet.gov (opens in a new tab)). Its acreage is not disclosed.

Who is building Joliet Technology Center?

PowerHouse Data Centers is the developer. No construction contractor is named on the record yet.

How much power and water does Joliet Technology Center say it needs?

Power: 1.8 GW (the developer's figure, joliet.gov (opens in a new tab)). Water: not disclosed by any source on file.

What has Joliet or Will County decided about it?

No decision by Joliet or Will County about data centers is on the record. The Will County page and the Illinois scorecard list every rated row the day a person publishes one.

About this data

Last verified
Next check Feeds every four hours, pages daily.
Figures Each figure as its source gave it, with its basis; another source's figure never stands in for the record's own, and nothing is estimated.
License Data CC BY-NC 4.0 (opens in a new tab); free for personal, academic, civic and newsroom reporting with attribution. Commercial, enterprise, financial or AI training use needs a commercial license. Prose stays under copyright.
Cite this page Data Center Record, "Joliet Technology Center", https://datacenterrecord.org/projects/joliet-technology-center-il, last verified October 26, 2026. CSV · JSON
Cite this page

Data Center Record, "Joliet Technology Center", https://datacenterrecord.org/projects/joliet-technology-center-il. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.

The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Prose stays under copyright.

Report a change
For researchers
Stage
Proposed
Tier
built from one source
Tags
Built from one source
Coordinates
41.4812, -88.0415
How the location is known
Location from the county parcel record.
Location source
https://www.joliet.gov/government/city-council-agendas-minutes
Coordinate source
City of Joliet City Council Annexation and Special Use Permit approval (March 24, 2026)
How capacity was disclosed
the developer's figure
Capacity, if disclosed
1.8 GW, the developer's figure
Published
October 26, 2026
Last verified
October 26, 2026
Undisclosed in public filings
Location source number, Location last verified, EPA registry id, Uses, Tenancy, Cooling, How water was disclosed, How acreage was disclosed, Interconnection, Rating of the county's rows

Researcher view · Joliet Technology Center · 5 sources, 1 entry, 0 decisions nearby · basis and source tier on every row · verified October 26, 2026

Download CSV JSON