Projects / Global AI Weld County Data Center / Timeline

Global AI Weld County Data Center, in order

What happened with this project, oldest first: the stages it reached, what the county and its cities decided, and every dated step on the record. Each entry links its source.

4 events, September 1, 2026 to September 8, 2026. Also on the record, under the month each belongs to: 2 statements and 24 dates when source pages were read and verified. The facts, newest first: the record; the place: Colorado.

A plain date is the day it happened, as the source states it, or as the line's own sentence states it ("voted on July 6"), which is where the line sits even when it was filed later. "Reported" and a date is the day a source published a line that carries no date of its own. Those lines, and lines that describe rather than report an act, sit under their month rather than on the timeline, with what was said and the figures other sources gave. Every timeline on the site reads its lines by this one rule. How dates are read.

Stages

  1. waiting on permits
  2. approved

Now: approved. A stage is the record's status after the entry that set it (the definitions).

2026 4 events

  1. (content date)

    waiting on permits

    Weld County Commissioners prepared to vote on a Global AI data center permit, and the county opened an investigation into the facility for three violations. [1]

  2. (the day its own sentence names; filed under Sep 11, 2026)

    Entry

    Weld County Planning Commission unanimously voted September 1 to recommend approval of the permit [6]

  3. (source date; the content gives no date of its own)

    approved

    Council special meeting scheduled for Tuesday, September 9, 2026 at 6 p.m. to review the resolution [10]

  4. (the day its own sentence names; filed under Sep 11, 2026)

    Entry

    Greeley City Council passed pre annexation agreement with Global AI on September 8, giving 18 months to negotiate final agreement [6]

  5. Also in September 2026: 2 statements and 24 dates when source pages were read and verified
    1. (said in the source itself)

      Statement · Michael Canon, air logistics expert and co-author

      Canon proposes five conditions: complete cost causation, public contracts, closed loop cooling with hard caps, newcomers must bring generation, and strategic siting near airports The Denver Post (opens in a new tab) local outlet

    2. (said in the source itself)

      Statement · Michael Canon, air logistics expert

      QTS at full build will exceed Evraz steel mill in Pueblo as largest single customer Xcel has The Denver Post (opens in a new tab) local outlet

    3. (source date; the content gives no date of its own)

      Entry

      The first data hall could be operational later this year. [4]

    4. (source date; the content gives no date of its own)

      Entry

      Global AI bought the 438 acre property for about $15.6 million last December. [4]

    5. (source date; the content gives no date of its own)

      Entry

      The data center will be 41 acres in an unincorporated area near Windsor. [4]

    6. (source date; the content gives no date of its own)

      Entry

      Global AI obtained a will serve letter from Poudre Valley REA [12]

    7. (source date; the content gives no date of its own)

      Entry

      Greeley's agreement sets a path toward annexation by the end of March 2028 [12]

    8. (source date; the content gives no date of its own)

      Entry

      The project is located at the former Carestream Health industrial site between Windsor and Greeley [12]

    9. (source date; the content gives no date of its own)

      Entry

      The project is planned for the former Carestream Health site in unincorporated Weld County near Windsor [11]

    10. (source date; the content gives no date of its own)

      Entry

      The company's goal is to have the facility operating by the end of 2026 [13]

    11. (source date; the content gives no date of its own)

      Entry

      The data center is 41 acres at a former Kodak facility between Greeley and Windsor [13]

    12. (source date; the content gives no date of its own)

      Entry

      The permit is for phase one of four phases [5]

    13. (source date; the content gives no date of its own)

      Entry

      The company plans to have the facility operational by the end of 2026 [5]

    14. (source date; the content gives no date of its own)

      Entry

      GlobalAI's facility is already under construction [5]

    15. (source date; the content gives no date of its own)

      Entry

      The data center facility is 41 acres at a former Kodak factory east of Windsor [5]

    16. (source date; the content gives no date of its own)

      Entry

      Facility uses closed loop cooling system that continuously reuses water, requiring minimal ongoing water demand [6]

    17. (source date; the content gives no date of its own)

      Entry

      0.8 acre pad would house chillers, transformers and backup generators [6]

    18. (source date; the content gives no date of its own)

      Entry

      Building is 400,000 square feet and was built in 1971 [6]

    19. (source date; the content gives no date of its own)

      Entry

      Global AI purchased 483 acre industrial complex formerly part of Eastman Kodak's Windsor campus [6]

    20. (source date; the content gives no date of its own)

      Entry

      Weld Board of County Commissioners unanimously approved a use by special review permit for Global AI data center [6]

    21. (source date; the content gives no date of its own)

      Entry

      The data center will use a closed loop, air cooled water system [13]

    22. (source date; the content gives no date of its own)

      Entry

      The project will be built in phases with potential to become the largest data center in Colorado [13]

    23. (source date; the content gives no date of its own)

      Entry

      Permit conditions require submission of a decommissioning plan and bond within six months, ambient noise monitoring, and use of closed loop cooling system [7]

    24. (source date; the content gives no date of its own)

      Entry

      Global AI's application anticipates 27.5 megawatts for the first phase, with Poudre Valley Rural Electric Association prepared to deliver 35 megawatts [7]

    25. (source date; the content gives no date of its own)

      Entry

      Permit conditions require closed loop, air cooled cooling system with initial fill of approximately 65,000 gallons and annual top offs of about 6,500 gallons [7]

    26. (source date; the content gives no date of its own)

      Entry

      Global AI's proposal reuses a vacant industrial facility on the former Carestream Health/Eastman Kodak property, 41 acres within a 438 acre site in unincorporated Weld County [7]

On the timeline: a stage change; an entry that reports an act on the day the source or its own sentence gives; and a decision, a published scorecard event on a row at or under the record's county, that reports an act. Under the months: a statement that names this record, a figure another source gave about it, matched by place and developer, an entry dated only by the day its source was published, and an entry or a decision that describes rather than reports an act. Each is on the record in its own right and keeps its own link.

For researchers
Stage
approved
Events on the timeline
4
Under the months
26
Stage changes
2
Decisions
0
Statements
2
Figures
0
Entries and decisions under the months
24

Researcher view · basis and source tier on every row · docket and Census GEOIDs · citation and export tools