Data Center Record.
Census GEOID: 17119 Location Precision: city centroid Jump to Entity & Permit Table Commercial & Bulk Data (CC BY-NC 4.0)

Last verified: · 3 primary and local sources

● Proposed Campus Announced October 30, 2026 · Cloverleaf Infrastructure

Cloverleaf Infrastructure Granite City data center

Location Granite City, Madison County, Illinois city centroid Town level, the center of the city

Overview, regulatory gates and specifications

Cloverleaf Infrastructure proposed a two site, 300 to 500 megawatt data center campus along the Route 3 industrial corridor in Granite City, Madison County, Illinois. [2] Filings on the record specify disclosed capacity of 300 MW (the developer's figure). [3]

Verified Site & Permit Summary
Verified address
Granite City, Madison County, Illinois city centroid
Operator / developer
Cloverleaf Infrastructure
Permit / registry ID
Cloverleaf Infrastructure on file [1]

How much water it would use and who would use it have not been disclosed.

What happens next: Next public milestones include utility queue filings, state environmental permits and local site plan review.

Key specifications on the record

Power capacity
300 MW developer figure Equivalent to the continuous electricity demand of about 249,000 average U.S. homes based on U.S. Energy Information Administration residential consumption data. About 3 percent of New York City's summer peak demand in 2024.
[3] granitecitydatacenter.com
Water usage
Not disclosed
Land area
Not disclosed
Buildings
Not disclosed
Backup generators
Not disclosed
Capital investment
Not disclosed
Who leads it
Cloverleaf Infrastructure as stated by the source
[3] granitecitydatacenter.com
Not disclosed
Who would use it, Jobs once it runs, Tax each year
The math behind the comparison
  1. Cloverleaf Infrastructure Granite City data center, capacity: 300 MW.
  2. New York City (NYISO Zone J) summer peak demand, actual, 2024: 10,245 MW (2024).
  3. 300 ÷ 10,245 = 0.03 (MW over MW).

Sources:

A comparison is arithmetic on two published rows and is never a new fact (how comparisons are made).

Who is connected to this project

Connected government officials, corporate entities, utilities and local rules on the public record.

Builder, Shell LLC & Utilities

BUILDER
Operator / Developer: Cloverleaf Infrastructure
UTILITIES
Electric utility: Not disclosed

Citizen privacy standard: Elected officials, corporate applicants and utility executives are named in full. Private residents who speak at public comment are cited as Resident First L. unless they hold public office or speak on behalf of an organization.

Technical specification and permit ledger

Disclosed engineering ceilings, reported actuals and primary regulatory basis for Cloverleaf Infrastructure Granite City data center.

Field / Parameter Permitted / Disclosed Ceiling Reported Actual Basis & Primary Source
Electrical Capacity (MW) 300 MW the developer's figure [3] granitecitydatacenter.com
Site Footprint (Acres)
Data Hall Buildings
Cooling & Water System
Backup Diesel / Gas Generators
Tax Abatement & Annual Revenue

Blank cell: not disclosed by any source on file.

Still not public, and where it would show up

The record adds each the day a source gives it. Why these documents.

  • Water use A state water right filing or a water supply agreement.
  • Who would use it A lease announcement or a tenant named in a filing.
  • Jobs and tax An incentive agreement, a county's economic development filing or a fiscal note.

What was decided

Acts of Madison County and Granite City about data centers, on the record with their source. A rule about the area is not a decision about this record.

DateWhoDecisionSource
Venice Township Venice Township voters rejected the nonbinding advisory question on whether the construction and operation of new data centers should be permitted in the township on November 3, 2026, voting 311 yes (24.13 percent) to 978 no (75.87 percent). ballotpedia.org (opens in a new tab)
Nameoki Township Nameoki Township voters rejected the nonbinding advisory question on whether the construction and operation of new data centers should be permitted in the township on November 3, 2026, voting 602 yes (22.14 percent) to 2,117 no (77.86 percent). ballotpedia.org (opens in a new tab)
Granite City Township Granite City Township voters rejected the nonbinding advisory question on whether the construction and operation of new data centers should be permitted in the township on November 3, 2026, voting 1,959 yes (25.57 percent) to 5,703 no (74.43 percent). ballotpedia.org (opens in a new tab)
Chouteau Township Chouteau Township voters rejected the nonbinding advisory question on whether the construction and operation of new data centers should be permitted in the township on November 3, 2026, voting 365 yes (16.73 percent) to 1,817 no (83.27 percent). ballotpedia.org (opens in a new tab)
Venice Township Venice Township voters voted on a nonbinding advisory question on November 3, 2026 on whether the construction and operation of new data centers should be permitted in the township. cms4files.revize.com (opens in a new tab)
Nameoki Township Nameoki Township voters voted on a nonbinding advisory question on November 3, 2026 on whether the construction and operation of new data centers should be permitted in the township. cms4files.revize.com (opens in a new tab)
4 earlier decisions on the county's rows
DateWhoDecisionSource
Granite City Township Granite City Township voters voted on a nonbinding advisory question on November 3, 2026 on whether the construction and operation of new data centers should be permitted in the township. cms4files.revize.com (opens in a new tab)
Chouteau Township Chouteau Township voters voted on a nonbinding advisory question on November 3, 2026 on whether the construction and operation of new data centers should be permitted in the township. cms4files.revize.com (opens in a new tab)
Troy restrictive In March 2026, Troy City Council voted to put a six month moratorium on any data center project. timestribunenews.com (opens in a new tab)
Troy restrictive Troy Planning Commission voted 5 to 0 on September 10 to extend data center moratorium until March 2027. timestribunenews.com (opens in a new tab)

Timeline on the record

Chronological regulatory, corporate and permitting events on the record, newest first.

No dated entry is on the record yet.

Every event in order

Nearest data centers in Illinois

Nearest records are not computed for a record placed at the center of its town. Browse all data centers in Illinois.

Common questions about Cloverleaf Infrastructure Granite City data center

Answered directly from the verified filings and local actions on this page.

Who is building Cloverleaf Infrastructure Granite City data center?

Cloverleaf Infrastructure is the developer, granitecitydatacenter.com (opens in a new tab). No construction contractor is named on the record yet.

How much power and water does Cloverleaf Infrastructure Granite City data center say it needs?

Power: 300 MW (the developer's figure, granitecitydatacenter.com (opens in a new tab)). Water: not disclosed by any source on file.

Where does Cloverleaf Infrastructure Granite City data center stand today?

It is proposed; the date it reached that stage is not sourced, only the day a page was read. No dated entry is on the record yet.

What has Granite City or Madison County decided about it?

Venice Township: Venice Township voters rejected the nonbinding advisory question on whether the construction and operation of new data centers should be permitted in the township on November 3, 2026, voting 311 yes (24.13 percent) to 978 no (75.87 percent), ballotpedia.org (opens in a new tab); and Nameoki Township: Nameoki Township voters rejected the nonbinding advisory question on whether the construction and operation of new data centers should be permitted in the township on November 3, 2026, voting 602 yes (22.14 percent) to 2,117 no (77.86 percent), ballotpedia.org (opens in a new tab). 10 events are on the county's rows; a rule about the area is not a decision about this record.

Sources

Primary documents first: filings, minutes, dockets and official pages. Then reporting. The numbers are the ones the entries above cite.

Tracked project domains

Promotional domains, campaign sites, and municipal portals preserved through the Internet Archive.

Reporting

  1. 2026 General Election Referenda Questions - Madison County Clerk (opens in a new tab), Madison County Clerk, August 28, 2026, news outlet
  2. Granite City Data Center information portal (opens in a new tab), Cloverleaf Infrastructure, February 15, 2026, trade press
  3. Madison County Informative Slides - Cloverleaf Infrastructure Granite City proposal (opens in a new tab), Cloverleaf Infrastructure, February 15, 2026, trade press

3 sources on file.

Regional grid context

This site is in the SERC Midwest (SRMW) regional power market.

Sources and data

Sources on this page

Every number on this page comes from a named source. Click any source to open the document in a new tab.

Cite this page

Every record on this page carries its sources and the date it was last verified. When you cite it in a story, a study or a public filing, link to this page and give the date you accessed it.

Get this data

Every row on this page is available to download with its source, its basis and the date it was last verified.

Use this data in your work

Free to use and republish with attribution for reporting, research, teaching and public filings under CC BY-NC 4.0. Commercial, enterprise, financial or AI training use needs a commercial license.

About this data

Last verified
Next check Feeds every four hours, pages daily.
Figures Each figure as its source gave it, with its basis; another source's figure never stands in for the record's own, and nothing is estimated.
License Data CC BY-NC 4.0 (opens in a new tab); free for personal, academic, civic and newsroom reporting with attribution. Using this data in a report? Support the record. Commercial use needs a license. Prose stays under copyright.
Cite this page Data Center Record, "Cloverleaf Infrastructure Granite City data center", https://datacenterrecord.org/projects/cloverleaf-granite-city-data-center-il, last verified October 31, 2026. CSV · JSON
Using this data in a report? Support the record. Commercial use needs a license.
Cite this page

Data Center Record, "Cloverleaf Infrastructure Granite City data center", https://datacenterrecord.org/projects/cloverleaf-granite-city-data-center-il. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.

The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.

Report a change
For researchers
Stage
Proposed
Tier
built from one source
Tags
Built from one source
Coordinates
38.7293, -90.1255
How the location is known
Location is the city center; exact site not disclosed.
Location source
City of Granite City, Madison County, Illinois (Census Gazetteer)
Coordinate source
City of Granite City, Madison County, Illinois (Census Gazetteer)
Location last verified
October 30, 2026
How capacity was disclosed
the developer's figure
Capacity, if disclosed
300 MW, the developer's figure
Rating of the county's rows
Restrictive
Published
October 30, 2026
Last verified
October 31, 2026
Not disclosed
Location source number, EPA registry id, Uses, Tenancy, Cooling, How water was disclosed, How acreage was disclosed, Interconnection

Researcher view · Cloverleaf Infrastructure Granite City data center · 3 sources, 0 entries, 10 decisions nearby · basis and source tier on every row · verified October 31, 2026

Download CSV JSON