Projects / Applied Digital North Dakota (Oliver County third data center) / Timeline

Applied Digital North Dakota (Oliver County third data center), in order

What happened with this project, oldest first: the stages it reached, what the county and its cities decided, and every dated step on the record. Each entry links its source.

3 events, January 1, 2025 to August 28, 2026. Also on the record, under the month each belongs to: 11 statements and 5 lines that are not events of their own. The facts, newest first: the record; the place: North Dakota.

A plain date is the day it happened, as the source states it, or as the line's own sentence states it ("voted on July 6"), which is where the line sits even when it was filed later. "Reported" and a date is the day a source published a line that carries no date of its own. Those lines, and lines that describe rather than report an act, sit under their month rather than on the timeline, with what was said and the figures other sources gave. Every timeline on the site reads its lines by this one rule. How dates are read.

Stages

  1. reported

Now: reported. A stage is the record's status after the entry that set it (the definitions).

2025 2 events

  1. (the year its own sentence names; filed under Sep 9, 2026)

    Entry

    The city of Ellendale annexed Applied Digital's property in early 2025. [7]

  2. (the year its own sentence names; filed under Sep 9, 2026)

    Entry

    City of Ellendale annexed Applied Digital's property in early 2025 [4]

2026 1 event

  1. (source date; the content gives no date of its own)

    reported

    Applied Digital is building 3 billion dollar data center on 160 acres near Harwood [5]

  2. Also in August 2026: 2 statements and 1 line that is not an event of its own
    1. (source date; the content gives no date of its own)

      Entry

      Applied Digital data center expected to be operational in early 2027 [5]

    2. (said in the source itself)

      Statement · Vern Thompson, Agriculture Commissioner candidate

      Vern Thompson, Agriculture Commissioner candidate, declared data centers North Dakota's number one problem InForum local outlet

    3. (said in the source itself)

      Statement · Vern Thompson, Agriculture Commissioner candidate

      Thompson proposed one year moratorium on data centers to allow ordinances to be developed InForum local outlet

  3. Also in September 2026: 9 statements and 4 lines that are not events of their own
    1. (said in the source itself)

      Statement · Randy Christmann, Public Service Commission Chair

      Public service commission chair said agency could develop a decommissioning program for data centers modeled on coal mine reclamation and wind farm rules journalnd.com local outlet

    2. (said in the source itself)

      Statement · Dave Nehring, Applied Digital Director of Local & Regional Affairs

      Applied Digital is projected to be the largest property taxpayer in North Dakota by 2028 or 2029, at more than $25 million a year Jamestown Sun local outlet

    3. (said in the source itself)

      Statement · Don Flaherty, Ellendale Mayor

      Ellendale Mayor predicted population growth of 400 to 600 people over the next five years Jamestown Sun local outlet

    4. (said in the source itself)

      Statement · Don Flaherty, Ellendale Mayor

      Ellendale Mayor Don Flaherty predicted the Applied Digital data center will bring 300 to 350 full time employees to the small town Jamestown Sun local outlet

    5. (said in the source itself)

      Statement · Don Flaherty, Ellendale Mayor

      Ellendale's taxable value at the end of 2025 was $3.5 million, expected to grow more than tenfold Jamestown Sun local outlet

    6. (source date; the content gives no date of its own)

      Entry

      Harwood city council approved the Applied Digital data center and signed a three billion dollar deal within 21 days of initial announcement [2]

    7. (said in the source itself)

      Statement · Applied Digital, company officials

      Applied Digital held a town hall meeting on its Harwood data center in August 2025 after construction plans were finished The Mighty 790 KFGO local outlet

    8. (source date; the content gives no date of its own)

      Entry

      Applied Digital signed a 2.4 billion dollar design and build agreement with Base Electron [3]

    9. (source date; the content gives no date of its own)

      Entry

      Applied Digital facility in North Dakota is expected to be operational by late 2028 [3]

    10. (source date; the content gives no date of its own)

      Entry

      Applied Digital ordered 1.2 gigawatts of industrial boiler fed steam turbines for a data center in North Dakota [3]

    11. (said in the source itself)

      Statement · Wes Cummins, Applied Digital chairman and CEO

      Lead times for gas turbine orders extend to 2032 ET Datacenters local outlet

    12. (said in the source itself)

      Statement · Gerardo Lara, vice president of Boiler Sales at Rentech Boiler Systems

      Rentech Boiler Systems can deliver a packaged boiler within a year ET Datacenters local outlet

    13. (said in the source itself)

      Statement · Mary Tintes, Civic West Steering Committee member

      Civic West hosting Fire Hall Chat on September 17 at 7 p.m. to discuss data center benefits and drawbacks with residents and Applied Digital representative InForum local outlet

On the timeline: a stage change; an entry that reports an act on the day the source or its own sentence gives; and a decision, a published scorecard event on a row at or under the record's county, that reports an act. Under the months: a statement that names this record, a figure another source gave about it, matched by place and developer, an entry dated only by the day its source was published, and an entry or a decision that describes rather than reports an act. Each is on the record in its own right and keeps its own link.

For researchers
Slug
applied-digital-north-dakota-oliver-county-third-data-center-nd
Status value
rumored
Events on the timeline
3
Under the months
16
Stage changes
1
Decisions
0
Statements
11
Figures
0
Entries and decisions under the months
5