Amazon Data Services, Inc. IAD-75 IAD-85 IAD-95 IAD-96, in order
What happened with this project, oldest first: the stages it reached, what the county and its cities decided, and every dated step on the record. Each entry links its source.
1 event, October 21, 2024. The facts, newest first: the record; the place: Virginia.
A plain date is the day it happened, as the source states it, or as the line's own sentence states it ("voted on July 6"), which is where the line sits even when it was filed later. "Reported" and a date is the day a source published a line that carries no date of its own. Those lines, and lines that describe rather than report an act, sit under their month rather than on the timeline, with what was said and the figures other sources gave. Every timeline on the site reads its lines by this one rule. How dates are read.
Stages
2024 1 event
-
(content date)
waiting on permits
Virginia DEQ issued a minor New Source Review air permit (Article 6, 9VAC5-80) to Amazon Data Services, Inc., registration 74115 (permit action 74115-4), Prince William County, on October 21, 2024. The permit action supersedes the earlier permit action dated March 29, 2018. The permit document authorizes 88 emergency backup generators totaling 220 MW of permitted backup generator rating at 8180, 8190, 8200, and 8210 Bethlehem Road (IAD-95, IAD-96, IAD-75, and IAD-85), Manassas, Virginia 20109. [1]
Local jurisdiction rules 6 decisions
County and municipal actions on the record in Prince William County County, listed separately from this facility's own timeline.
-
(source date; the content gives no date of its own)
Decision · Prince William County (county)
Prince William dissolved the resident Data Center Ordinance Advisory Group and adopted a different measurement approach with advisory standards virginiamercury.com (opens in a new tab)
-
(source date; the content gives no date of its own)
Decision · Prince William County (county)
Supervisors voted 8 to 0 to reject a comprehensive plan amendment for Dulles South Innovation Center, a proposed campus covering about 1,940 acres with 43 million square feet of data center space theminermag.com (opens in a new tab)
-
(source date; the content gives no date of its own)
Decision · Prince William County (county)
Prince William County will vote to repeal zoning rules for one area of the county where data centers can be built without approval nbcwashington.com (opens in a new tab)
-
(source date; the content gives no date of its own)
Decision · Prince William County (county)
Several high profile projects in Prince William County were recently halted due to sustained community opposition ground.news (opens in a new tab)
-
(source date; the content gives no date of its own)
Decision · Prince William County (county)
Planning commission recommended a 120 day grace period for developers; supervisors were also considering eliminating the grace period entirely. patch.com (opens in a new tab)
-
(source date; the content gives no date of its own)
Decision · Prince William County (county)
Prince William County Board of Supervisors approved changes ending by right data center development and shrinking Data Center Opportunity Zone Overlay District from 9,698 acres to 3,641 acres commercialobserver.com (opens in a new tab)
On the timeline: a stage change; an entry that reports an act on the day the source or its own sentence gives; and a decision, a published scorecard event on a row at or under the record's county, that reports an act. Under the months: a statement that names this record, a figure another source gave about it, matched by place and developer, an entry dated only by the day its source was published, and an entry or a decision that describes rather than reports an act. Each is on the record in its own right and keeps its own link.
For researchers
- Stage
- waiting on permits
- Events on the timeline
- 1
- Under the months
- 0
- Stage changes
- 1
- Decisions
- 6
- Statements
- 0
- Figures
- 0
- Entries and decisions under the months
- 0