Aligned Data Centers West Jordan (SLC-01, SLC-02, SLC-03), in order

What happened with this project, oldest first: the stages it reached, what the county and its cities decided, and every dated step on the record. Each entry links its source.

2 events, April 12, 2022 to October 21, 2026. Also on the record, under the month each belongs to: 2 statements and 1 date when a source page was read and verified. The facts, newest first: the record; the place: Utah.

A plain date is the day it happened, as the source states it, or as the line's own sentence states it ("voted on July 6"), which is where the line sits even when it was filed later. "Reported" and a date is the day a source published a line that carries no date of its own. Those lines, and lines that describe rather than report an act, sit under their month rather than on the timeline, with what was said and the figures other sources gave. Every timeline on the site reads its lines by this one rule. How dates are read.

Stages

  1. approved
  2. running

Now: running. A stage is the record's status after the entry that set it (the definitions).

2022 1 event

  1. (content date)

    approved

    Utah Division of Air Quality Approval Order AI Site 15939 (Project N160660003) and Salt Lake County Assessor parcel records document the 55 acre, 3 building Aligned campus at 3333 W. 9000 South in West Jordan, with one building inside a former semiconductor plant acquired in 2018. [5]

2026 1 event

  1. Also in September 2026: 1 date when a source page was read and verified
    1. (the day the page was read; it gives no date of its own)

      Entry

      Aligned Data Centers lists Aligned SLC-01, Aligned SLC-02 at West Jordan, Utah on its own page of data center locations, read September 14, 2026. [3]

  2. (content date)

    Entry

    The Salt Lake County Health Department opened a noise investigation into the Aligned West Jordan campus at 3333 W. 9000 South after receiving four formal complaints from nearby residents since August 2026, with the investigation scheduled to conclude in November 2026. [8]

  3. Also in October 2026: 2 statements
    1. (content date; reported from elsewhere)

      Statement · Aligned Data Centers, Data Center Operator

      Aligned Data Centers stated that it commissioned an acoustic study and installed a sound barrier at its West Jordan campus after residents reported humming noise from the facility. The Salt Lake Tribune (opens in a new tab) local outlet

    2. (content date; reported from elsewhere)

      Statement · Kevin Oyler, City Council Member

      Spanish Fork City Council member Kevin Oyler stated that the Novva data center campus five miles away in West Jordan is quiet. The Salt Lake Tribune (opens in a new tab) local outlet

On the timeline: a stage change; an entry that reports an act on the day the source or its own sentence gives; and a decision, a published scorecard event on a row at or under the record's county, that reports an act. Under the months: a statement that names this record, a figure another source gave about it, matched by place and developer, an entry dated only by the day its source was published, and an entry or a decision that describes rather than reports an act. Each is on the record in its own right and keeps its own link.

For researchers
Stage
running
Events on the timeline
2
Under the months
3
Stage changes
1
Decisions
0
Statements
2
Figures
0
Entries and decisions under the months
1