Clean Cloud Energy Mahomet data center
Mahomet, Champaign County, ILDeveloper: Clean Cloud EnergyCensus GEOID 17019
- Stage
- Proposed
- Undisclosed in public filings
- Power, Land, Buildings, Water
Clean Cloud Energy Mahomet data center It is reported; the record holds no sourced date for when it reached that stage.
How much power it needs, how much water it would use and who would use it have not been disclosed.
Tap a pin for the data center, the parcel for its record
- This record: Proposed, ringed
- data center
- Dashed edge: the exact site is not in the public record
- Smaller pins: 38 other published records in Illinois
Details
- this record's location, ringed
- parcel outline, from the county parcel record
- city limits, U.S. Census Bureau, on a town level record
- county boundary
The other pins are the published projects in the same state, each in its stage color. The imagery beneath is the USGS national orthoimagery, public domain, shown so the land around the site can be read.
How to read this page. Every fact links to the source it rests on; a number in brackets is its place in the source list. A figure no source gives reads Not disclosed, and nothing is estimated. Where sources give different figures, each is shown with who gave it, and another source's figure never stands in for the record's own. Entries are added and never overwritten; corrections are listed under What happened.
What is known
Each figure as its source gave it. The number in brackets is its place in the source list.
- Undisclosed in public filings
- Land, Buildings, Power it would draw, Water, Who would use it, Jobs once it runs, Tax each year
Every field, with who said it and when (Researcher view)
Impact figures
| Field | Value | Who says so | Source | Last verified |
|---|---|---|---|---|
| How much power it needs | ||||
| How much water it would use | ||||
| How loud it would be | ||||
| Jobs once it runs | ||||
| Tax it would pay each year |
The record's fields
| Field | Value | Who says so | Source | Last verified |
|---|---|---|---|---|
| Who is building it | Clean Cloud Energy | as stated by the source | [1] mahometdaily.com (opens in a new tab) | October 20, 2026 |
| Who is constructing it | ||||
| How much land | ||||
| Buildings | ||||
| Where its power comes from | ||||
| Grid connection | ||||
| How it is cooled |
A blank value cell means not disclosed by any source on file; a blank basis cell means the source gave the figure without saying on what basis.
The developer's figure is what the company said; what a permit allows is the ceiling a permit sets; measured means observed. Water is in gallons a day or a year, whichever the source stated; a tax claim given as a range shows both ends, each linked to the source that gave it.
Still not public, and where it would show up
The record adds each the day a source gives it. Why these documents.
- Water use A state water right filing or a water supply agreement.
- Who would use it A lease announcement or a tenant named in a filing.
- Power the campus would draw A utility or public service commission docket, an interconnection filing, or an air permit for an on site plant.
- Jobs and tax An incentive agreement, a county's economic development filing or a fiscal note.
What was decided
Acts of Champaign County and Mahomet about data centers, on the record with their source. A rule about the area is not a decision about this record.
| Date | Who | Decision | Source |
|---|---|---|---|
| Champaign County | The Champaign County Data Center Activities Task Force drafted an ordinance to set regulations for large data center development. | dailyillini.com (opens in a new tab) | |
| Champaign County | Ordinance draft must be approved by Champaign Zoning Board of Appeals before Champaign County Board can vote on it | ipmnewsroom.org (opens in a new tab) | |
| Champaign County | Task force will send ordinance to Champaign County Environment and Land Use Committee for review | ipmnewsroom.org (opens in a new tab) | |
| Champaign County | Temporary ban on large scale data centers currently in effect expires in mid April 2027 | ipmnewsroom.org (opens in a new tab) | |
| Champaign County | Proposed ordinance would limit size and geographic location of new large data centers; for example, to avoid or mitigate impact on wildlife to sustainable level of mortality | ipmnewsroom.org (opens in a new tab) | |
| Champaign County | Proposed ordinance would require data centers to comply with most recent International Energy Conservation Code | ipmnewsroom.org (opens in a new tab) |
4 earlier decisions on the county's rows
| Date | Who | Decision | Source |
|---|---|---|---|
| Champaign County | Champaign County Data Center Activities Task Force formed to propose guardrails for large data centers after moratorium is lifted | ipmnewsroom.org (opens in a new tab) | |
| Champaign County | Champaign County implemented 1 year moratorium on large data center construction in April 2026 | ipmnewsroom.org (opens in a new tab) | |
| Champaign County | Public task force meeting held on August 31, 2026 to discuss ordinance with residents | ipmnewsroom.org (opens in a new tab) | |
| Champaign County | Champaign County Board enacted a moratorium in April halting all data center construction, set to expire the following year. | dailyillini.com (opens in a new tab) |
What happened
No dated entry is on the record yet.
The site
Where in Mahomet is not in the public record. The pin marks the center of Mahomet, not a building, and the outline is Champaign County.
- Where
- Mahomet, Champaign County, Illinois
- How exactly it is located
- Town level, the center of the city
- The parcel
- No parcel outline in the public record
- Nearest homes
- Not computed for a record placed at a place center
- Nearest records
- Nearest records are not computed for a record placed at the center of its town.
Keep going
Questions about this project
4 questions answered from the record
Who is building Clean Cloud Energy Mahomet data center?
-
Clean Cloud Energy is the developer, mahometdaily.com (opens in a new tab). No construction contractor is named on the record yet.
How much power and water does Clean Cloud Energy Mahomet data center say it needs?
-
Power: not disclosed by any source on file. Water: not disclosed by any source on file.
Where does Clean Cloud Energy Mahomet data center stand today?
-
It is reported; the date it reached that stage is not sourced, only the day a page was read. No dated entry is on the record yet.
What has Mahomet or Champaign County decided about it?
-
Champaign County (rated restrictive): The Champaign County Data Center Activities Task Force drafted an ordinance to set regulations for large data center development (reported September 28, 2026, dailyillini.com (opens in a new tab)); and Champaign County: Ordinance draft must be approved by Champaign Zoning Board of Appeals before Champaign County Board can vote on it (reported September 1, 2026, ipmnewsroom.org (opens in a new tab)). 10 events are on the county's rows; a rule about the area is not a decision about this record.
Sources
Reporting
- Mahomet’s ‘preliminary’ data center talks: 10 months, NDAs and a $17 million draft deal (Emails Included) - Mahomet Daily (opens in a new tab), Mahomet Daily, September 28, 2026, news outlet
1 source on file.
About this data
Last verified , first recorded . Every correction is logged on the corrections page. Report a correction · Send a tip about Clean Cloud Energy Mahomet data center
Cite this page
Data Center Record, "Clean Cloud Energy Mahomet data center", https://datacenterrecord.org/projects/clean-cloud-energy-mahomet-data-center-il. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.
The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Prose stays under copyright.
For researchers
- Stage
- Proposed
- Tier
- built from one source
- Tags
- Built from one source
- Coordinates
- 40.1901, -88.3895
- How the location is known
- Location is the city center; exact site not disclosed.
- Coordinate source
- U.S. Census Bureau 2020 gazetteer place point
- Rating of the county's rows
- Restrictive
- Published
- October 1, 2026
- Last verified
- October 20, 2026
- Undisclosed in public filings
- Location source, Location source number, Location last verified, EPA registry id, Uses, Tenancy, Cooling, How capacity was disclosed, How water was disclosed, How acreage was disclosed, Interconnection, Capacity, if disclosed