Data Center Record.
Projects / Cedar Rapids Third Data Center (Southwest Side) / Timeline

Cedar Rapids Third Data Center (Southwest Side), in order

What happened with this project, oldest first: the stages it reached, what the county and its cities decided, and every dated step on the record. Each entry links its source.

1 event, July 9, 2026 to July 9, 2026. Also on the record, under the month each belongs to: 3 statements and 6 lines that are not events of their own. The facts, newest first: the record; the place: Iowa.

A plain date is the day it happened, as the source states it, or as the line's own sentence states it ("voted on July 6"), which is where the line sits even when it was filed later. "Reported" and a date is the day a source published a line that carries no date of its own. Those lines, and lines that describe rather than report an act, sit under their month rather than on the timeline, with what was said and the figures other sources gave. Every timeline on the site reads its lines by this one rule. How dates are read.

Stages

  1. reported

Now: reported. A stage is the record's status after the entry that set it (the definitions).

2026 1 event

  1. (source date; the content gives no date of its own)

    reported

    The newly approved facility would be about the size of half a Target Supercenter; facility location at 1515 33rd Ave. SW [2]

  2. Also in July 2026: 3 statements and 1 line that is not an event of its own
    1. (source date; the content gives no date of its own)

      Entry

      This area has been zoned for industrial use since early 2000s [2]

    2. (said in the source itself)

      Statement · Tag Greason, QTS Co-CEO

      QTS announced a five million dollar grant to local organizations including the Iowa Workforce Development Foundation thegazette.com local outlet

    3. (said in the source itself)

      Statement · Tag Greason, QTS Co-CEO

      Grant intended to address labor concerns for data center development thegazette.com local outlet

    4. (said in the source itself)

      Statement · Tiffany O'Donnell, Cedar Rapids mayor

      Cedar Rapids offered data center companies tax credits; companies pay less than a third of commercial property taxes for the first 20 years KCRG local outlet

  3. Also in August 2026: 4 lines that are not events of their own
    1. (source date; the content gives no date of its own)

      Decision · Linn County (county)

      Linn County implemented a data center moratorium thegazette.com

    2. (source date; the content gives no date of its own)

      Decision · Cedar Rapids (city)

      Cedar Rapids Solid Waste Agency found banned cardboard and recyclables at data center waste sites kcrg.com

    3. (source date; the content gives no date of its own)

      Decision · Linn County (county)

      Cedar Rapids/Linn County Solid Waste Agency board unanimously directed staff to prepare resolution requiring commercial sites including data centers to sort waste before landfill delivery thegazette.com

    4. (source date; the content gives no date of its own)

      Decision · Linn County (county)

      Linn County adopted a moratorium after developing an ordinance with independent water studies, setbacks, property owner protections, and community benefit investments. thegazette.com

  4. Also in September 2026: 1 line that is not an event of its own
    1. (source date; the content gives no date of its own)

      Decision · Cedar Rapids (city)

      residents seek answers on proposed south side data center at community meeting cbs2iowa.com

On the timeline: a stage change; an entry that reports an act on the day the source or its own sentence gives; and a decision, a published scorecard event on a row at or under the record's county, that reports an act. Under the months: a statement that names this record, a figure another source gave about it, matched by place and developer, an entry dated only by the day its source was published, and an entry or a decision that describes rather than reports an act. Each is on the record in its own right and keeps its own link.

For researchers
Slug
cedar-rapids-third-data-center-southwest-side-ia
Status value
rumored
Events on the timeline
1
Under the months
9
Stage changes
1
Decisions
5
Statements
3
Figures
0
Entries and decisions under the months
6