Oppidan Connect Cedar Rapids Data Center (CLOP Cedar Rapids), in order
What happened with this project, oldest first: the stages it reached, what the county and its cities decided, and every dated step on the record. Each entry links its source.
2 events, July 21, 2025 to July 8, 2026. Also on the record, under the month each belongs to: 3 statements and 2 dates when source pages were read and verified. The facts, newest first: the record; the place: Iowa.
A plain date is the day it happened, as the source states it, or as the line's own sentence states it ("voted on July 6"), which is where the line sits even when it was filed later. "Reported" and a date is the day a source published a line that carries no date of its own. Those lines, and lines that describe rather than report an act, sit under their month rather than on the timeline, with what was said and the figures other sources gave. Every timeline on the site reads its lines by this one rule. How dates are read.
Stages
2025 1 event
-
(source date; the content gives no date of its own)
approved
State and county investigating potentially illegal wells near data center construction site [4]
2026 1 event
-
(content date)
Entry
Cedar Rapids confirmed a third data center is planned for the southwest side of the city. [1]
-
Also in July 2026: 3 statements and 2 dates when source pages were read and verified
-
(source date; the content gives no date of its own)
Entry
This area has been zoned for industrial use since early 2000s [2]
-
(source date; the content gives no date of its own)
Entry
The newly approved facility would be about the size of half a Target Supercenter; facility location at 1515 33rd Ave. SW [2]
-
(said in the source itself)
Statement · Tag Greason, QTS Co-CEO
QTS announced a five million dollar grant to local organizations including the Iowa Workforce Development Foundation thegazette.com (opens in a new tab) local outlet
-
(said in the source itself)
Statement · Tag Greason, QTS Co-CEO
Grant intended to address labor concerns for data center development thegazette.com (opens in a new tab) local outlet
-
(said in the source itself)
Statement · Tiffany O'Donnell, Cedar Rapids mayor
Cedar Rapids offered data center companies tax credits; companies pay less than a third of commercial property taxes for the first 20 years KCRG (opens in a new tab) local outlet
-
On the timeline: a stage change; an entry that reports an act on the day the source or its own sentence gives; and a decision, a published scorecard event on a row at or under the record's county, that reports an act. Under the months: a statement that names this record, a figure another source gave about it, matched by place and developer, an entry dated only by the day its source was published, and an entry or a decision that describes rather than reports an act. Each is on the record in its own right and keeps its own link.
For researchers
- Stage
- approved
- Events on the timeline
- 2
- Under the months
- 5
- Stage changes
- 1
- Decisions
- 0
- Statements
- 3
- Figures
- 0
- Entries and decisions under the months
- 2